Superconducting Undulators WBS: APS-U1.03.04.03 Yury Ivanyushenkov Physicist, SCU Project Technical Leader ASD/Magnetic Devices Group DOE Lehman CD-2 Review.

Slides:



Advertisements
Similar presentations
SCU Development at LBNL Soren Prestemon Lawrence Berkeley National Laboratory Superconducting Undulator R&D Review Jan. 31, 2014.
Advertisements

The Use of Small Coolers for Hydrogen and Helium Liquefaction
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Undulator R & D Jim Clarke STFC Daresbury Laboratory, UK BAW-2 SLAC Jan 2011.
SCU Magnetic Measurement System Design and SCU0 Measurement Results Charles L. Doose Engineering Specialist ASD/Magnet Devices DOE Lehman CD-2 Review of.
SCU Measurements at LBNL
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Isaac Vasserman Magnetic Measurements and Tuning 10/14/ I. Vasserman LCLS Magnetic Measurements and Tuning.
Development of superconducting undulators at the Advanced Photon Source Yury Ivanyushenkov on behalf of the APS superconducting undulator project team.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Superconducting Undulator (SCU) Development at ANL Efim Gluskin on behalf of the APS/ANL team Superconducting Undulator R&D Review Jan. 31, 2014.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
BNG Industrial experience on Superconducting Undulators C. Boffo, T. Gehrard, B. Schraut, J. Steinmann, W. Walter, Babcock Noell GmbH T. Baumbach, S. Casalbuoni,
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
SPX - Cavity WBS U , U , U Genfa Wu SRF Scientist Accelerator Systems Division/RF Group DOE Lehman CD-2 Review of APS-Upgrade.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
P. Emma, …for the SCU R&D collaboration: ANL, LBNL, SLAC August 28, 2014 P. Emma, N. Holtkamp, H.-D. Nuhn, SLAC C. Doose, J. Fuerst, Q. Hasse, Y. Ivanyushenkov,
SuperConducting Undulator (SCU) R&D Motivation and Status P. Emma For the SCU R&D collaboration: ANL, LBNL, SLAC June 27, 2014.
STFC Technology undulator manufacture and measurement James Rochford On behalf of the Helical collaboration.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Technical Challenges and Concerns S. Sharma and R. Alforque, R. Beuman, C. Foerster, E. Haas, E. Hu, P. Montanez, P. Mortazavi, S. Pjerov, J. Skaritka,
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.
1 WANG,Li/SINAP WANG Li, WANG ShuHua, LIU YiYong, SUN Sen, HU Xiao, YIN LiXin Shanghai Institute of Applied Physics, CAS, Shanghai , China Shanghai.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
SCU1 Vertical Test Results Matt Kasa 9/16/2014. Vertical Cryostat Assembly Coil Training Record the current decay and the terminal voltage across the.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Helical Undulator Status Jim Clarke ASTeC, STFC Daresbury Laboratory.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Restoring Komag Yasuhiro Makida Consideration of restoring and modifying Komag for a stand alone operation without the refrigerator. Contents 1.Magnet.
X LCLS SCU NbTi Prototype Schedule Version: February 12, 2015 Update 23JUN2015 X X System complete and ready for test X System complete & tested w/Hall.
SCU 3-Lab Review Meeting, Dec. 16, 2014 SCU Presentations Today Intro. & Performance Motivations (P. Emma, SLAC, 20+5) Conceptual Cryostat Design: Option-A.
The integration of 420 m detectors into the LHC
ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Technical Design V. Kashikhin for Superconducting Magnet Team.
Alignment of Superconducting Undulators at the APS Jaromir M. Penicka for the APS SCU team IWAA2014 Beijing, October 13-17, 2014.
Advanced Photon Source Undulator Technology for Ultimate Storage Rings (USRs) By Mark Jaski.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
Summary of the 2014 Superconducting Undulator Workshop Jim Clarke STFC Daresbury Laboratory and The Cockcroft Institute Beam Dynamics Meets Magnets - II,
Summary of Presentation 1. Tolerances i. Vertical tolerances on BPMs (rf-BPM: ± 0.2μm, user BPMs: ±0.1μm, and X-BPMs: ± 0.1μm) ii. Tolerances on magnets’
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
September 27, 2007 ILC Main Linac - KOF 1 ILC Main Linac Superconducting Quadrupole V. Kashikhin for Magnet group.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Part 2: NbTi Magnet Performance Yury Ivanyushenkov for the APS SCU Team: S. Bettenhausen, C. Doose, M. Kasa, Q. Hasse, I. Kesgin, D. Jensen, S. Kim, G.
FEL SCU development at APS/ANL
CBM magnet overview of the BINP work
at STFC Daresbury laboratory
Cryogenic behavior of the cryogenic system
Status of the CLIC DR wiggler design and production at BINP
SC Quadrupole Magnets in ILC Cryomodules
Challenges of vacuum chambers with adjustable gap for SC undulators
Task 6: Short Period Nb3Sn Superconducting Helical Undulator
SCU Next Phase Meeting July 8, 2014.
Dan Potratz M.S. Student Mechanical Engineering
Technical Summary - ANL
A Cold SCU Phase-Shifter
Updated concept of the CBM dipole magnet
ILC Main Linac Superconducting Splittable Quadrupole
as a prototype for Super c-tau factory
Cryogenic behavior of the magnet
Presentation transcript:

Superconducting Undulators WBS: APS-U Yury Ivanyushenkov Physicist, SCU Project Technical Leader ASD/Magnetic Devices Group DOE Lehman CD-2 Review of APS-Upgrade 4-6 December 2012

Outline  Science / Technical Significance  WBS Scope of this System  Staff / Org Chart  Requirements  Design  ES&H  Cost  Schedule  Previous Reviews Responses  Summary 2 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

Superconducting Undulators (SCUs) Motivation 3 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 Superconducting undulators generate extremely high photon brightness above 40 keV Brightness Tuning Curves

SCU Scope 4 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 WBSProgrammatic FundsU SCU0SCU1SCU2 SCU1 will use a modified cryostat from SCU0 and a new 1-m long magnet. SCU0 – Test deviceSCU1SCU2 The device is built and tested stand alone. SCU2 will use a longer cryostat with a 2-m long magnet.

DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU Cost Summary

SCU Requirements 6 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 SCU0SCU1SCU2 Energy at 1 st harmonic, keV * Period length, mm1618 Magnet length, m ~2.3* Cryostat length, m2.063 ~3.0*

SCU Org Chart 7 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 Core Team Management: E. Gluskin*(ASD-MD) Simulation: R. Dejus (ASD-MD) S. Kim (ASD-MD) R. Kustom (ASD-RF) E. Moog (ASD-MD) Y. Shiroyanagi (ASD-MD) Design: D. Pasholk (AED-DD) D. Skiadopoulos (AES-DD) E. Trakhtenberg (AES-MD) Cryogenics: J. Fuerst (ASD-MD) Q. Hasse (ASD-MD) Measurements: M. Abliz (ASD-MD) C. Doose (ASD-MD) M. Kasa (ASD-MD) I. Vasserman (ASD-MD) Controls: B. Deriy (ASD-PS) M. Smith (AES-C) J. Xu (AES-C) Tech. support: K. Boerste (ASD-MD) * Group Leader Budker Institute Collaboration (Cryomodule and Measurement System Design) N. Mezentsev V. Syrovatin V. Tsukanov V. Lev FNAL Collaboration (Resin Impregnation) A. Makarov UW-Madison Collaboration (Cooling System) J. Pfotenhauer D. Potratz D. Schick Y. Ivanyushenkov (ASD) Technical Leader Technical Support M. Borland (ASD-ADD) J. Collins (AES-MD) G. Decker* (ASD-D) P. Den Hartog* (AES-MD) L. Emery* (ASD-AOP) R. Farnsworth* (AES-C) J. Gagliano* (AES-VS) G. Goeppner* (AES-MOM) K. Harkay (ASD-AOP) V. Sajaev (ASD-AOP) J. Penicka* (AES-SA) J. Wang* (ASD-PS) A. Zholents (ASD-DD) *Group Leader M. White (APS-U) Associate Project Manager

SCU Design – Major Challenges 8 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012  High field quality requirements: –low phase error: < 8 deg. rms –low field integrals*: SCU0: 1 st field integrals (Bx, By) ≤ 470 G-cm, 4700 G-cm, 2 nd field integrals (Bx, By) ≤ 4.32x10 4 G-cm 2, 1.3x10 5 G-cm 2 SCU1/SCU2 : TBD –measurement of SCU performance before installation into storage ring  Superconducting coils cooling in presence of heat load from the beam: –heat load on the beam chamber of ~10 W * Requirements for maximum possible change of absolute first- and second-field integral errors (based on local orbit modeling with x-ray BPMs participating in orbit correction)

SCU Design – Strategy to Solve Challenges DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December ChallengesStrategy to find a solutionProject phaseStatus High quality fieldDevelop magnetic design that achieves low field errors R&DCompleted Verify design by building and testing prototypesR&DCompleted Scale design to longer structuresSCU0 – SCU2Completed for SCU0 Build a high-quality horizontal measurement system SCU0Completed Cooling of superconducting coils in presence of beam heat load Estimate heat load from beamR&D – SCU0Completed Develop cooling scheme that minimizes heat load on superconducting coils SCU0Completed Verify the design in a test device – stand alone test SCU0Completed Check test device performance in the ringSCU0Installation into the SR is scheduled for January 2013 SCU0 goal: Verify design concept by building and testing in the beam a full-scale device.

SCU Design – Conceptual Points DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December  Magnetic structure: –Two identical magnet jaws separated by a gap of 9.5 mm –Superconducting (SC) coils are wound with NbTi round wire –A correction coil at each end of the main coil –No magnetic ‘shimming’  Beam vacuum chamber: –Thin-wall Al beam chamber with the vertical aperture of 7.2 mm  Cooling scheme: –SC coils are cooled by liquid helium (LHe) flowing through the channels in the cores –LHe is stored inside the cryostat in the LHe tank above the magnet that together with the cores and LHe piping forms a closed system –He vapor is re-condensed in the LHe tank that is cooled by two cryocoolers

SCU Design – Conceptual Points (2) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December  Cooling scheme (continued): –Beam chamber is thermally insulated from 4-K circuit –Beam chamber is cooled by two cryocoolers and is kept at K  Cryostat: –Contains a cold mass (SC magnet, LHe tank, beam chamber, and a support frame) –20-K and 60-K thermal shields –Current lead assemblies –Four cryocoolers

SCU Design – Cryostat Structure DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU design concept is implemented in the SCU0 design LHe vessel SC magnet He fill/vent turret 20 K radiation shield 60 K radiation shield Beam chamber thermal link to cryocooler LHe piping Design of SCU0 is based on the APS experience of making short SC magnetic structures and on experience by a team from Budker Institute, Novosibirsk, of making cryostats for their SC wigglers.

SCU0 Manufacture - Magnet DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU0 magnet design is based on the design developed at the APS during the R&D phase of the project The steel coil formers (cores) are manufactured by Hi-Tech, Chicago The coils are wound at the APS on a precise computer-controlled winder Resin vacuum impregnation is done at the APS Completed cores are tested in a vertical LHe bath cryostat Completed single magnet core Completed magnet assembly

SCU0 Manufacture - Cryostat DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU0 cryostat design follows the design of superconducting wigglers developed by Budker Institute, Novosibirsk, Russia Conceptual and detailed design of the SCU0 cryomodule is done at the APS The cryostat package, including vacuum vessel, two radiation shields, and LHe tank, was manufactured by PHPK Technologies, Columbus Internal components of the cryomodule were manufactured by Hi-Tech, Chicago Radiation shields fit test at PHPK Completed cryostat package at PHPK

SCU0 Assembly DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU0 was assembled at the APS in a new facility located in Bldg. 314 Several sub-systems were first assembled including cold mass and current lead blocks Current lead assemblies were tested in a dedicated cryostat before installation into the SCU0 cryostat LHe tank with He circuits were leak checked Several fit tests were done SCU0 assembly was completed in May 2012 SCU0 being assembled in the new facility Fully assembled cold mass Cold mass and current lead assemblies fit test

SCU Horizontal Measurement System DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU warm-sensor measurement system is based on a concept developed at Budker Institute for characterizing superconducting wigglers. Scanning Hall probe: Specially developed three-sensor Hall probe (attached to carbon fiber tubing and driven by linear stage) to measure B y and B x simultaneously and determine the mid-plane field regardless of sensor vertical offset from magnetic mid-plane. On-the-fly Hall probe measurements (2 cm/s,  z 0.2 mm, typical z range ±35 cm) to determine local field errors and phase errors. Stretched Wire Coil Stretched wire rectangular, delta and ‘figure-8’ coils to determine static and dynamic 1 st and 2 nd field integrals. Rotary stages on upstream end of cryostat as well as on the Z axis linear stage to provide synchronized rotary motion for stretch coils. Coils can be translated along x axis approximately ±1 cm to measure integrated multipole components. SCU warm-sensor concept SCU0 horizontal measurement system

SCU Control System DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU0 control system is a fully working prototype for the SCU1 and SCU2 control systems Two versions of the SCU0 control system are being developed: LabVIEW-based system (stand alone system) EPICS-based system (final system) Cold tests of the SCU0 heavily use the LabVIEW system SCU0 in the storage ring will be controlled by EPICS system SCU0 hardware rack with power supplies, NI crate, temperature sensors, and other hardware Temperature window of the LabVIEW SCU0 control system

SCU0 Cold Test – Cryogenic Performance: Cool down DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December A design concept of cooling the undulator down with compact cryocoolers has been confirmed. The system achieved cool-down during a day, using cryocooler power alone requiring total three days to stabilize at LHe temperature. The temperatures of the 4-K cryocoolers during initial cool-down of SCU0. The cryocoolers are 2-stage devices, with the 1 st stage providing shield cooling and the 2 nd stage cooling the liquid helium reservoir and superconducting magnet.

SCU0 Cold Test – Cryogenic Performance: Steady state operation DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December Steady state cryogenic performance of the SCU0 has met all design goals. The observed temperatures in the system are below the design temperatures. Temperature window of the LabVIEW control system ComponentObserved temperature, K 60-K shield K shield8 Beam chamber 8-11 LHe circuit4.2

SCU0 Cold Test – Cryogenic Performance: Helium circuit operation DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December Stable operation of superconducting magnet coils indirectly cooled by LHe: A concept of using horizontal thermal syphon loop was proven. Helium loss-free operation for 1.5 months Cooling power exceeds the heat load: Ability to liquefy warm helium supplied from a gas bottle instead of using a liquid helium Dewar. Ability to operate below 4.2 K – Operation at 700 A (140% of the maximum operating current) at the temperature of 3.8 K in the LHe tank was demonstrated. This opens a way to higher fields. This figure shows increasing liquid helium level achieved by using the excess 4 K capacity of the system to re- liquefy helium gas added from an external cylinder to increase the LHe inventory in the reservoir.

SCU0 Cold Test – Cryogenic Performance: Heat load tests DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December Beam heat load was simulated by using a heater attached to the cold part of the SCU0 beam chamber. A heat load of 0-45 W was applied to the beam chamber at full operating current of 500 A The beam chamber temperature raised from 11 K to 30 K The LHe circuit temperature raised from 4.3 K to 4.4 K indicating a very good thermal insulation between the two circuits The magnet did not quench during the heat load tests Heater power, W Main coil current, A500 Beam chamber temperature, K LHe tank temperature, K

SCU0 Cold Test – Magnetic Field Performance DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December  The SCU0 magnet exceeds most of the design parameters  The magnet reached the maximum operating current of 500 A without quench  The design peak field of 0.64 T is achieved  The magnet operated stably at the elevated current of 600 A  The 1 st field integrals typically change less than 30 G-cm from 100 to 600 A for both fixed currents and dynamic changes in current.  The 2 nd field integrals change by less than 8000 G-cm 2 from 100 to 600 A dependent on the corrector current lookup table.  Phase errors are typically 1 degree rms or less from 100 A to 600 A. SCU0 magnet excitation curves Typical B y field with main coil current of 500 A and correction current of 51.7 A More details are in the presentation by Chuck Doose

SCU0 Cold Test Results Summary DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December The SCU0 is cryogenically stable. Since the initial cool-down and then filling the SCU0 with liquid helium on July 3, the device was kept cold until August 20. The SCU0 magnet is working at full design current. The SCU0 magnet coils achieved the design excitation current of 500 A upon the first current ramp without quenching. The magnet has at least 20% margin in operation current. The magnet has continuously been energized for up to a week at the maximum design current of 500 A, and for several days at 600 A without inadvertent quenching. At the LHe temperature of 3.8 K the magnet operated at a current of 700 A. The device has successfully passed a thermal load test. SCU0 did not quench at 500 A with 45 W of heat applied to the beam chamber for at least 1.5 hours. SCU0 being tested in July-August 2012

SCU0 – Status and Next Steps DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December SCU0 is re-assembled in September-October with a new beam chamber This new beam chamber has a larger aperture cold-to-room temperature transitions The SCU0 is being cold tested Installation of SCU0 into the APS storage ring is planned for December-January shutdown

SCU ES&H DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December  Integrated Safety Management System (ISMS) –APS-U Project following Argonne’s ISMS program requirements –Argonne Integrated Safety Management System (ISMS) Description recently revised and submitted to DOE ASO Describes framework for integrating ESH requirements with mission objectives References Argonne LMS procedures which implement specific portions of the ISMS  Design, manufacture, commissioning, and operation of superconductor undulators are aligned with the laboratory standards and policies: ES&H-4.10 Cryogenic Liquid Safety ES&H-13.1 Pressure Systems Safety APS_ APS Design Review Procedure Vacuum Systems Consensus Guideline for DOE Accelerator Laboratories 10 CFR 851 – Worker Safety and Health Program

SCU Risks / CEDU Contingency 26 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 Most of the risks in the SCU design and operability in the ring are mitigated by building and testing the first undulator – SCU0. Specific RiskMitigation Excessive beam heat loadBeam chamber is cooled by two cryocoolers instead of one (total cooling power is 40 W at 20 K); low heat conduction support structure minimizes heat leak into superconducting coils. Magnetic structure poor fabrication Three half-magnet cores are fabricated and tested, the best two are used in a cryomodule. Large field integralsTwo correction coils are implemented in each half-magnet core; additional beam correctors might be employed. Large phase errorTight mechanical tolerances, strict QA procedure, core test before installation into cryomodule. LHe cooling circuit does not work properly LHe buffer tank is incorporated into the cryomodule.

WBS U SCU BOE Contingency DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December

SCU Cost Summary Chart 28 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012  SCU1 and SCU2 costs are estimated based on the experience of fabricating the SCU0  Cost drivers: –High-precision magnetic structures including engineering development of magnet fabrication; –High-quality thermal links to minimize temperature gradients in the system; –Thin-wall beam chamber assembly to minimize the magnetic gap; –Cryostat including vacuum vessel, LHe tanks and two radiation shields.

WBS U SCU Cost Summary by FY 29 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

WBS U SCU Summary Schedule 30 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

Previous Reviews Responses DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December Recommendation Response The cost estimates for the cold mass for SCU1 and SCU2 deserve some clarification; the SCU1 cost apparently includes prototypes. Correct. Development costs are included in SCU1 and SCU2. Multipole requirements should show up on slide 3 of the measurement talk (not just 1st and 2nd integral requirements). The requirements for the multipole components will be shown on slide 3 of the talk on the experimental results. A preliminary plan for skew-quad correction should be provided. According to preliminary magnetic modeling, cross-over wires in the magnetic cores are the source of the measured skew-quad component. Additional correction coils might be used for skew-quad correction. A correction scheme is presented in the magnetic measurement talk.  CD-2 Director’s Review (September 11-13, 2012)

Work between CD-2 and CD-3 32 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012  Between CD-2 and CD-3 our work will be concentrating on – monitoring Programmatic activities on SCU0; – study of SCU0 performance; – magnetic design of the SCU1 and SCU2 magnets; – design modifications of the SCU1; – conceptual design of the SCU2.  Reviews: –SCU0 beam test review; –SCU1 magnetic design review.

Summary 33 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 This system includes delivery of two superconducting undulators - SCU1 and SCU2 The superconducting undulators will produce extremely high photon brightness above 40 keV The conceptual design is complete because the first test undulator SCU0 has successfully passed a stand alone cold test The cost is $3,942k We are ready to begin final design of the superconducting undulators required by APS-U We are ready for CD-2!