Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 8 Project Resource Management Resource Planning.

Slides:



Advertisements
Similar presentations
Project Management.
Advertisements

Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
CSCU 411 Software Engineering Chapter 2 Introduction to Software Engineering Management.
Project Plans CSCI102 - Systems ITCS905 - Systems MCS Systems.
Project Integration Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project.
BSBPMG501A Manage Project Integrative Processes 4.3 Direct and Manage Project Execution This is the process of performing the work defined in the project.
Project Management based on the Project Management book of knowledge Risk Identify, analyse and respond to risks Resources Make most effective use of human.
JOB ANALYSIS AND HUMAN RESOURCE PLANNING
© 2008 Prentice Hall11-1 Introduction to Project Management Chapter 11 Managing Project Execution Information Systems Project Management: A Process and.
Project Execution.
Other Planning Processes: Final Planning Touches
Top management jobs BP-Centro Finland Erno Karpoff
What is Business Analysis Planning & Monitoring?
BSBPMG506A Manage Project Human Resources 9.2 Acquire Project Team The process of confirming human resource availability and selecting the team members.
BSBPMG506A Manage Project Human Resources 9.1 Develop Human Resource Plan The process of identifying and documenting project roles, responsibilities, required.
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
Lecture 10 Human Resources Looking after the human side of the business. It is the set of activities that must be done to acquire.
Project Management Process Overview
PMP® Exam Preparation Course
Project Management for RIM Professionals Last Updated: 3/13/2011 Sarina Arcari, PMP VP Implementation & Product Planning Amerigroup Corporation 3/15/11.
Resources Performance time. resources Performance time 2.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 3 Project Management for Strategic Goal Achievement.
Certificate IV in Project Management Introduction to Project Management Course Number Qualification Code BSB41507.
FCS - AAO - DM COMPE/SE/ISE 492 Senior Project 2 System/Software Test Documentation (STD) System/Software Test Documentation (STD)
BSBPMG405A Apply Human Resource Management Approaches Apply Human Resource Management Approaches Human Resource Management Processes – Part 1 C ertificate.
Strong9 Consulting Services, LLC 1 PMI - SVC I-80 Breakfast Roundtable Monthly Meeting Thursday, October 12, :00 am – 9:00 am.
Lecture 11 Managing Project Execution. Project Execution The phase of a project in which work towards direct achievement of the project’s objectives and.
BSBPMG405A Apply Human Resource Management Approaches Apply Human Resource Management Approaches Unit Guide C ertificate IV in Project Management
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Certificate IV in Project Management Qualification Code BSB41507 Unit.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 4 Project Scope Management.
Project Charters Module 3
LECTURE IV. o Project HRM include the processes that organize, manage and lead the project team. o The project team is comprised of the people with assigned.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 2 Project Management Cycle.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 5 Project Integration Management.
Manage Project Human Resources Human Resource Management Processes – Part 1 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Professional Certificate in Electoral Processes Understanding and Demonstrating Assessment Criteria Facilitator: Tony Cash.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 1 Diploma of Project Management.
Project Human Resource Management. Presentation Team 1)Mrs. Mardia Ibrahim Osman(Mechanical Engineer) 2)Mr. Elsaeed Osman Elsheikh(Medical Doctor) 3)Mr.
Topic 5 Initiating a project
MITM743 Advanced Project Management Dr. Abdul Rahim Ahmad Assoc. Professor College of IT, UNITEN Project Management Body of Knowledge PMBOK 4 (Section2)
Project Management Project Integration Management Minder Chen, Ph.D. CSU Channel Islands
Fundamentals of Governance: Parliament and Government Understanding and Demonstrating Assessment Criteria Facilitator: Tony Cash.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
~ pertemuan 4 ~ Oleh: Ir. Abdul Hayat, MTI 20-Mar-2009 [Abdul Hayat, [4]Project Integration Management, Semester Genap 2008/2009] 1 PROJECT INTEGRATION.
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Week 4 Certificate IV in Project Management Qualification Code BSB41507.
Team-Based Development ISYS321 Managing the Information Systems Project.
Project Management Processes for a Project Chapter 3 PMBOK® Fourth Edition.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
Company LOGO. Company LOGO PE, PMP, PgMP, PME, MCT, PRINCE2 Practitioner.
PM B-03 Managing Organizational Development and Change Phase 4 Individual Project HR Planning and Project Management By John W. Casto Instructor.
The Project Management Process Groups
Agenda  Purpose  Processes  Deliverables  Executing Activities 4.3.
Project Management PTM721S
9.1 Plan Human Resource Management
Project Management PTM721S
Disaster and Emergency Planning
Systems Analysis and Design in a Changing World, 4th Edition
Project Management Processes
TechStambha PMP Certification Training
Chapter 3 Managing the Information Systems Project
PMI North Area PMP Exam Study Group
CIS12-3 IT Project Management
Project Management Process Groups
Project Management Processes
Project Integration Management
Project Integration Management
Closing a Project Close a Project or Phase Close Procurements.
Presentation transcript:

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 8 Project Resource Management Resource Planning

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project resource management What is resource planning The nature of human resources planning Organisational resource planning and inputs Tools and techniques

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project resources You need 7 resources in a project….. What are they? People Money Equipment Facilities Materials & Supplies Information Technology You need to estimate your project resources before you can complete the project plan

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project resource management Projects are carried out by people Often regarded as the most important resource in a project……. Project human resource management includes the processes required to make the most effective use of people involved with the project.

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project HR management..includes all stakeholders such as sponsors, customers, contributors (staff) and others It consists of the following major processes: organisational planning staff acquisition team development

Dr. Jana Jagodick Polytechnic of Namibia, 2012 The Nature of Planning Planning is future orientated - it is concerned with what is to be achieved and how it is to be achieved Plans can be strategic, tactical and operational and are contained in a written document 4 major components: objectives actions resources implementation

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Human Resources Planning “the systematic and continuing process of analysing an organisation’s human resources needs under changing conditions, and developing personnel policies appropriate to the longer term effectiveness of the organisation.”

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Organisational Resource Planning Takes place during the early project phases and is closely linked to communications planning for structures and channels of authority/ communications

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Organisational Resource Planning Inputs 1.Project interfaces 2. Staffing requirements 3. Constraints Tools & techniques 1.Templates 2. Human resources practices 3. Organisational theory 4. Stakeholder analysis Outputs 1.Role & responsibility assignment 2. Staffing management 3. Organisation chart 4. Supporting detail

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Organisational Planning - Inputs Inputs 1.Project interfaces 2. Staffing requirements 3. Constraints Tools & techniques 1.Templates 2. Human resources practices 3. Organisational theory 4. Stakeholder analysis Outputs 1.Role & responsibility assignment 2. Staffing management 3. Organisation chart 4. Supporting detail

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Interfaces Inputs 1.Project interfaces 2. Staffing requirements 3. Constraints Project interfaces are where diverse, independent groups interact These interfaces can be of an organisational, technical and/or interpersonal nature e.g. a technical interface in computer science is the point of communication between a computer and a human being – keyboard, mouse etc

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Staffing Requirements Inputs 1.Project interfaces 2. Staffing requirements 3. Constraints This is concerned with deciding what types of skills are required for the project (job descriptions), from what types of people and in what time frame

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Constraints Inputs 1.Project interfaces 2. Staffing requirements 3. Constraints Constraints which might be encountered are the organisational structure of the performing organisation, trade union agreements, preferences by the management team and skills and competencies of staff members

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Tools & Techniques Tools & techniques 1.Templates 2. Human resources practices 3. Organisational theory 4. Stakeholder analysis Many projects have areas of commonality and using a template can help make sure you don’t miss anything HR practices – policies, guidelines and procedures From books, internet, journals etc to understand stakeholder needs

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Outputs 1.Role & responsibility assignment 2. Staffing management 3. Organisation chart 4. Supporting detail Most important outputs are: role and responsibility assignments by using WBS and RAM (responsibility assignment matrix) a staffing management plan an organisation chart supporting detail such as an evaluation of the impact on the organisation, job descriptions and training needs

Dr. Jana Jagodick Polytechnic of Namibia, 2012 R&R Responsibility Assignment Often conducted using RASIC, RASCI or RASI matrix Tool to establish roles and responsibilities on a project esponsible pproving upporting informed onsulted

Dr. Jana Jagodick Polytechnic of Namibia, 2012 RASIC R - Responsible: solely and directly accountable for creating a work package or task A - Approving: and needs to review and assure the quality of the deliverables from that work package or task S - Supporting: any and all individuals or groups who help create the deliverables from the work package I - Informed: any and all people who need updated during the creation of the deliverables C - Consulted: any and all who help define the deliverables or quality review criteria Every ‘deliverable’ in the project must have a 'Responsible' person and an 'Approving' person

Dr. Jana Jagodick Polytechnic of Namibia, 2012 RASIC exercise Create a RASIC chart for the ‘Project Management course’ you are doing Stakeholders to be listed Activities /deliverables to be defined Allocate RASIC responsibilities

Dr. Jana Jagodick Polytechnic of Namibia, 2012 RASIC exercise – stakeholders Come up with a list of stakeholders

Dr. Jana Jagodick Polytechnic of Namibia, 2012 RASIC exercise – deliverables Initiation – objectives/outline of the course Planning – lesson plan, lesson preparation, assignment, test and exam setting Execution and control – delivery of lessons, conducting and marking assignment, test and exam Closure – completion of semester marks, exam marks, lessons learned Now that you have the deliverables and the stakeholders, you can complete the RASIC chart

Dr. Jana Jagodick Polytechnic of Namibia, 2012 RASIC exercise – deliverables Deliverable ACclassschoolPoly Course outline/objectives Lesson plan & prep Assignment, test and exam plan Carry out lessons Carry out assign, test & exam & record results Complete final marks Lessons learned

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Staff Acquisition Acquiring the right people is vital to the success of a project The main objective of staff acquisition is to obtain the best people to fill project posts Before the acquisition a post analysis has to be done to evaluate what the post entails that needs to be filled Once the analysis has been done, a post description (title, duties, resources, working conditions etc) and post specification (qualifications, experience and skills required) must be drawn up

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Staff Acquisition Getting the human resources needed assigned to and working on the project Not always possible to attract the desired level of skills, where functional and project managers compete for staff members

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Staff Acquisition Inputs 1.Staffing management plan 2. Staffing pool description 3. Recruitment Practices & policies Tools & techniques 1.Negotiation with functional managers 2. Pre-assignment or Project specification Outputs 1.Project staff Assigned 2. A project staff directory or database

Dr. Jana Jagodick Polytechnic of Namibia, 2012 Resource planning summary Each person to come up with 3 important things you remember from this session that will help your understanding of “project resource planning”