Air Permitting Update Yogesh Doshi ACE Academy New Jersey Department of Environmental Protection
Major Facility to Minor Facility Pre-application meeting to review the proposal If accepting any limitations, then Sig. Mod. If removing any equipment, then Minor Mod. Enforcement review Submit Preconstruction Permit (PCP) After PCP issuance, Title V terminated 2
Annual Certification Issuance For each applicable requirement, submit certification within 60 days after each calendar year Submit certification electronically through online NJDEP web portal Submission should be printed for submission to EPA 3
--Cont. For each applicable requirement – Statement weather compliance is continuous or intermittent, as defined in federal rules – Compliance schedule – Compliance with any ACO, if applicable – Not in compliance – Certification by Responsible Official 4
Emission Statement Submit an annual emission statement (if required) electronically to the NJDEP by May 15 of each year (or by mutually agreed upon date, but no later than June 15 of each year). 5
Application Overview Online permitting help: Application and Forms: 6
Application Overview Administrative Completeness Technical Completeness and review Compliance Plan Public Process 7
Temporary Mobile Equipment Allowed for short term for 90 days – Not installed or used permanently – Not circumvent any state or federal rules and performance standards – Must obtain PCP and comply with all terms and conditions specified – Operate less than 90 days in any calendar years – Record of all temporary mobile equipment on site, date, time and emissions 8
---Cont. Emissions must be included in netting analysis required by the facility If such short term activities re-occur on at least annual basis, permittee is required to include in Title V permit within one year of the first use, through permit modification 9
Facility Outstanding Bills Hyperlink to facility outstanding bills Must pay all outstanding bills before final permit is issued 10
GP and GOP 22 General Permits 3 General Operating Permits – SEGAP – CHP < 65 MMBTU/Hr, CT – CHP < 65 MMBTU/Hr, Reciprocating SI Engine 11
GP/GOP Development Schedule GP-001A – Storage Silos – Public Comment Period Ended8/15/13 – Testing Ended2/27/15 – Rollout 4/20/15 GP-005B and GOP-004 NG Emergency Generators – Public Comment Period Ended12/17/14 – Rollout (on paper form)5/4/15*** – Development starts3/15/15 – Testing begins6/15/15 – Rollout8/3/15 12
GP/GOP Development Schedule (more) GP-017A and GOP-007 Boilers <5 MMBTU/Hr – Public Comment Period Ended End of May – Development startsBeg of June – Testing beginsMid September – RolloutDecember 13