PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT /

Slides:



Advertisements
Similar presentations
© The McGraw-Hill Companies, Software Project Management 4th Edition Activity planning Chapter 6.
Advertisements

Chapter 7 Project Management
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Finding the Critical Path
Prosjektstyring A 5 WEEKS B 10 WEEKS C 12 WEEKS D 8 WEEKS E 6 WEEKS ACTIVITY (t) ESEF FL LS LF We have a network with.
ES=32 EF=34 LS=33 LF=35 ES=10 EF=16 LS=10 LF=16 ES=4+6=10 EF=10 LS=4
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Project Management Project  A series of related jobs usually directed toward some major output and requiring a significant time to perform Project management.
A simple set of tasks in “timeline-schedule” form Req. Gathering Req. Analysis High Level Design Detail Design & Code Test Case DevelopmentTest Execution.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
CEN th Lecture CEN 4021 Software Engineering II Instructor: Masoud Sadjadi Software Project Planning.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Stochastic Modeling & Simulation Lecture 6: Intro to Project Management – CPM.
MGMT 483 Week 8 Scheduling.
ELC 347 project management
Project Networks. A,4 B,3 C,4 D,6 E,3 H,6 F,5 G,4 I,2 St,0 Fin,0 Example Network - terminology C,t Activity Duration of Activity (ES, LS) Early Start.
Project Management Introduces Pert/CPM as a tool for planning, scheduling, and controlling projects Applied Management Science for Decision Making, 2e.
Prepared by Lee Revere and John Large
Network planning Learning objectives After these lectures you should be able to: - Produce and analyse activities networks - Calculate earliest and latest.
Project Management (2) Chapter 16, Part 2. EJR 2006 Review of Project Management, Part 1 What is a project? Examples of projects Project performance expectations.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Management Techniques.
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
Projmgmt-1/14 DePaul University Project Management I - Realistic Scheduling Instructor: David A. Lash.
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Project Management Chapter 16. MGMT 326 Foundations of Operations Introduction Strategy Managing Projects Quality Assurance Facilities Products & Processes.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PROJECT MANAGEMENT Definitions WBS = Work Breakdown Structure
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Welcome to MM305 Unit 7 Seminar Dr. Bob Project Management.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
5 th LectureCEN 4021: Software Engineering II Task Sequence and Effort representation  All tasks share at least two basic characteristics –Require effort.
1 TCOM 5143 Lecture 11 Project Management. 2 What’s Project Management? Project management involves planning and scheduling the different activities of.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
DEVELOPING A STATUS REPORT: A HYPOTHETICAL EXAMPLE Tong Wang P , Chapter 13 Process and performance Measurement and Evaluation, Project Management.
9-1 ELC 347 project management Day 19. Agenda Integrative Project –Part 4 Due –Part 5 Due Nov 24 (page 342) –Any of the first five sections can be resubmitted.
Welcome to MM305 Unit 7 Seminar Dr. Bill Wood Project Management.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management Chapter 8.
Project Management Chapter Topics
Project Management Chapter 13
Project Scheduling Chapter 14.
Project Time Management.
PERT-CRITICAL PATH-DECISION MAKING PROCESS/TOOLS
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Project Management CPM Method Tutorial-p2
Project Management Planning Models
ENM448-Project Planning and Management
Welcome to MM 305 Unit 8 Seminar!
Project Management CPM Method Tutorial-p1
תזמון פרויקטים.
Prepared by Lee Revere and John Large
مدیریت عمومی دانش کهن. مدیریت عمومی دانش کهن ارایه تحقیق پایان ترم 3 نمره امتحان پایان ترم 10 نمره ارایه تکالیف کلاس 2 نمره امتحانات.
BEST VIEWED IN SLIDE SHOW MODE
General Foundry Example of PERT/CPM
Slides Prepared by JOHN LOUCKS
Exercise – A small building.
Presentation transcript:

PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT / Cost is a modification of PERT that allows a manager to plan, schedule, monitor, and control cost as well as time. Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions Philip A. Vaccaro, PhD MGMT E-5050

The Budgeting Process STEPS STEPS Identify all costs associated with each task.  Identify all costs associated with each task. Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions

The Budgeting Process STEPS STEPS Identify all costs associated with each task.  Identify all costs associated with each task.  Convert the budgeted cost per task into a cost per time period. We assume that the cost per time period. We assume that the cost of completing a task is spent at a uni- cost of completing a task is spent at a uni- form rate over time. form rate over time.

The Budgeting Process STEPS STEPS Identify all costs associated with each task.  Identify all costs associated with each task.  Convert the budgeted cost per task into a cost per time period. We assume that the cost per time period. We assume that the cost of completing a task is spent at a uni- cost of completing a task is spent at a uni- form rate over time. form rate over time.  Using the earliest and latest start times, we find out how much money should be spent find out how much money should be spent during each week or month to finish the pro- during each week or month to finish the pro- ject by the desired date. ject by the desired date.

Early Start Budget Schedule GENERAL FOUNDRY EXAMPLE Task “A” Early Start Time - ES 0 Early Finish Time - EF 2 Expected Time - te 2 weeks Budgeted Task Cost $22, Budgeted Weekly Cost $11, * $22, / 2 WEEKS = $11, *

TASK Period 1 Period 2 Period 3 Period 4 A$11,000$11,000 B C D E F G H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “B” Early Start Time - ES 0 Early Finish Time - EF 3 Expected Time - te 3 weeks Budgeted Task Cost $30, Budgeted Weekly Cost $10, * $30, / 3 WEEKS = $10, *

TASK Period 1 Period 2 Period 3 Period 4 A B$10,000$10,000$10,000 C D E F G H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “C” Early Start Time - ES 2 Early Finish Time - EF 4 Expected Time - te 2 weeks Budgeted Task Cost $26, Budgeted Weekly Cost $13, * $26, / 2 WEEKS = $13, *

TASK Period 1 Period 2 Period 3 Period 4 A B C$13,000$13,000 D E F G H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “D” Early Start Time - ES 3 Early Finish Time - EF 7 Expected Time - te 4 weeks Budgeted Task Cost $48, Budgeted Weekly Cost $12, * $48, / 4 WEEKS = $12, *

TASK Period 4 Period 5 Period 6 Period 7 A B C D$12,000$12,000$12,000$12,000 E F G H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “E” Early Start Time - ES 4 Early Finish Time - EF 8 Expected Time - te 4 weeks Budgeted Task Cost $56, Budgeted Weekly Cost $14, * $56, / 4 WEEKS = $14, *

TASK Period 5 Period 6 Period 7 Period 8 A B C D E$14,000$14,000$14,000$14,000 F G H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “F” Early Start Time - ES 4 Early Finish Time - EF 7 Expected Time - te 3 weeks Budgeted Task Cost $30, Budgeted Weekly Cost $10, * $30, / 3 WEEKS = $10, *

TASK Period 5 Period 6 Period 7 Period 8 A B C D E F$10,000$10,000$10,000 G H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “G” Early Start Time - ES 8 Early Finish Time - EF 13 Expected Time - te 5 weeks Budgeted Task Cost $80, Budgeted Weekly Cost $16, * $80, / 5 WEEKS = $16, *

TASK Period 9 Period 10 Period 11 Period 12 A B C D E F G$16,000$16,000$16,000$16,000 H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

TASK Period 13 Period 14 Period 15 A B C D E F G$16,000 H PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedu le

GENERAL FOUNDRY EXAMPLE Task “H” Early Start Time - ES 13 Early Finish Time - EF 15 Expected Time - te 2 weeks Budgeted Task Cost $16, Budgeted Weekly Cost $8, * $16, / 2 WEEKS = $8, *

TASK Period 14 Period 15 A B C D E F G H$8,000$8,000 PERIOD TOTAL CUMULATIVE FROM START Early Start Budget Schedule

TASK Period 1 Period 2 Period 3 Period 4 A$11,000$11,000 B$10,000$10,000$10,000 C$13,000$13,000 D$12,000 E F G H PERIOD TOTAL $21,000$21,000$23,000$25,000 CUMULATIVE FROM START $21,000$42,000$65,000$90,000 Early Start Budget Schedule

TASK Period 5 Period 6 Period 7 Period 8 A B C D$12,000$12,000$12,000 E$14,000$14,000$14,000$14,000 F$10,000$10,000$10,000 G H PERIOD TOTAL $36,000$36,000$36,000$14,000 CUMULATIVE FROM START $126,000$162,000$198,000$212,000 Early Start Budget Schedule

TASK Period 9 Period 10 Period 11 Period 12 A B C D E F G$16,000$16,000$16,000$16,000 H PERIOD TOTAL $16,000$16,000$16,000$16,000 CUMULATIVE FROM START $228,000$244,000$260,000$276,000 Early Start Budget Schedule

TASK Period 13 Period 14 Period 15 A B C D E F G$16,000 H$8,000$8,000 PERIOD TOTAL $16,000$8,000$8,000 CUMULATIVE FROM START $292,000$300,000$308,000 Early Start Budget Schedule

Cumulative Budget Schedule EARLY START TIME $300,000. $250,000. $200,000. $150,000. $100,000. $50,000. $ weeks $308,000.00

Late Start Time Budget   Tasks that are not on the critical path can be started at a later date.  This type of budget will delay the expenditure of funds until the last possible moment.  Unfortunately, the risk is that any subsequent delays in these tasks will delay the entire pro- ject!

Late Start Budget Schedule GENERAL FOUNDRY EXAMPLE Task “A” Late Start Time - LS 0 Late Finish Time - LF 2 Expected Time - te 2 weeks Budgeted Task Cost $22, Budgeted Weekly Cost $11, * $22, / 2 WEEKS = $11, *

TASK Period 1 Period 2 Period 3 Period 4 A$11,000$11,000 B C D E F G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “B” Late Start Time - LS 1 Late Finish Time - LF 4 Expected Time - te 3 weeks Budgeted Task Cost $30, Budgeted Weekly Cost $10, * $30, / 3 WEEKS = $10, *

TASK Period 1 Period 2 Period 3 Period 4 A B$10,000$10,000$10,000 C D E F G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “C” Late Start Time - LS 2 Late Finish Time - LF 4 Expected Time - te 2 weeks Budgeted Task Cost $26, Budgeted Weekly Cost $13, * $26, / 2 WEEKS = $13, *

TASK Period 1 Period 2 Period 3 Period 4 A B C$13,000$13,000 D E F G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “D” Late Start Time - LS 4 Late Finish Time - LF 8 Expected Time - te 4 weeks Budgeted Task Cost $48, Budgeted Weekly Cost $12, * $48, / 4 WEEKS = $12, *

TASK Period 5 Period 6 Period 7 Period 8 A B C D$12,000$12,000$12,000$12,000 E F G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “E” Late Start Time - LS 4 Late Finish Time - LF 8 Expected Time - te 4 weeks Budgeted Task Cost $56, Budgeted Weekly Cost $14, * $56, / 4 WEEKS = $14, *

TASK Period 5 Period 6 Period 7 Period 8 A B C D E$14,000$14,000$14,000$14,000 F G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “F” Late Start Time - LS 10 Late Finish Time - LF 13 Expected Time - te 3 weeks Budgeted Task Cost $30, Budgeted Weekly Cost $10, * $30, / 3 WEEKS = $10, *

TASK Period 9 Period 10 Period 11 Period 12 A B C D E F$10,000$10,000 G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

TASK Period 13 Period 14 Period 15 A B C D E F$10,000 G H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “G” Late Start Time - LS 8 Late Finish Time - LF 13 Expected Time - te 5 weeks Budgeted Task Cost $80, Budgeted Weekly Cost $16, * $80, / 5 WEEKS = $16, *

TASK Period 9 Period 10 Period 11 Period 12 A B C D E F G$16,000$16,000$16,000$16,000 H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

TASK Period 13 Period 14 Period 15 A B C D E F G$16,000 H PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

GENERAL FOUNDRY EXAMPLE Task “H” Late Start Time - LS 13 Late Finish Time - LF 15 Expected Time - te 2 weeks Budgeted Task Cost $16, Budgeted Weekly Cost $8, * $16, / 2 WEEKS = $8, *

TASK Period 13 Period 14 Period 15 A B C D E F G H$8,000$8,000 PERIOD TOTAL CUMULATIVE FROM START Late Start Budget Schedule

TASK Period 1 Period 2 Period 3 Period 4 A$11,000$11,000 B$10,000$10,000$10,000 C$13,000$13,000 D E F G H PERIOD TOTAL $11,000$21,000$23,000$23,000 CUMULATIVE FROM START $11,000$32,000$55,000$78,000 Late Start Budget Schedule

TASK Period 5 Period 6 Period 7 Period 8 A B C D$12,000$12,000$12,000$12,000 E$14,000$14,000$14,000$14,000 F G H PERIOD TOTAL $26,000$26,000$26,000$26,000 CUMULATIVE FROM START $104,000$130,000$156,000$182,000 Late Start Budget Schedule

TASK Period 9 Period 10 Period 11 Period 12 A B C D E F$10,000$10,000 G$16,000$16,000$16,000$16,000 H PERIOD TOTAL $16,000$16,000$26,000$26,000 CUMULATIVE FROM START $198,000$214,000$240,000$266,000 Late Start Budget Schedule

TASK Period 13 Period 14 Period 15 A B C D E F$10,000 G$16,000 H$8,000$8,000 PERIOD TOTAL $26,000$8,000$8,000 CUMULATIVE FROM START $292,000$300,000$308,000 Late Start Budget Schedule

Cumulative Budget Schedule LATE START TIME $300,000. $250,000. $200,000. $150,000. $100,000. $50,000. $ weeks $308,000.00

Cumulative Budget Schedule EARLY START TIME $300,000. $250,000. $200,000. $150,000. $100,000. $50,000. $ weeks $308,000.00

Cumulative Budget Schedule FEASIBLE BUDGET RANGES $300,000. $250,000. $200,000. $150,000. $100,000. $50,000. $ weeks $308, EARLY START TIME LATE START TIME AREA AREA AREA

PERT / CPM with QM for WINDOWS

We Select The COST BUDGETING Sub Program

The Data Table Is Completed As Previously Shown

The Expected Project Completion Time ( 15 weeks )

The EARLY START BUDGET ( 1 st 11 weeks )

The EARLY START BUDGET ( 5 th through 15 th week )

The LATE START BUDGET ( 1 st 8 weeks )

The LATE START BUDGET ( 8 th through 15 th week )

The Feasible Budget Region

Excel cannot do project budgeting

PROJECT BUDGETING