Presented By: Lisa LeBlanc, Associate Superintendent Framing the Next Steps – Bond Program Facilities Subcommittee – 2/26/15 DRAFT.

Slides:



Advertisements
Similar presentations
WCCUSD Bond Program Project Status Report
Advertisements

West Contra Costa USD Potential 2005 Measure J Bonding Capacity Waiver Presentation to the Facilities Subcommittee December 10, 2013.
West Contra Costa Unified School District Facilities Subcommittee Meeting March 11, 2014 State School Facility Program Seismic Funding Update.
West Contra Costa USD General Obligation Bond Update Presentation to the Facilities Subcommittee August 26, 2014.
I.The Building/Remodeling/ Renovating Project NSSED North Shore Academy (NSA) and Administration Office Building/Remodeling/Renovating Project.
Once again the State adopted a budget without realistically solving its own major deficit problem. “Mid-Year Triggers” is the latest catch phrase for.
West Contra Costa USD New Money GO Bond Sale: 2010 Measure D, Series C bonds and 2012 Measure E, Series B bonds Presentation to the Facilities Subcommittee.
WSSDA Webinar May 14, 2014 Barbara Posthumus, Director of Business Services Lake Washington School District
GUHSD CITIZENS COMMITTEE FEBRUARY 11, 2015 Election Information and Budget Overview.
February 11, SchoolApprovedConstructionProjected SiteBudgetEstimate/*BudgetCost at Comp.  Pinole Valley HS$180,000,000*$130,000,000$180,000,000.
Proposed Budget Presentation APRIL 21, 2015.
Superintendent’s Recommendations for District Improvement Related to Facility Needs VICTORIA PUBLIC SCHOOLS.
2015 Municipal Budget Overview Borough of Montvale April 14, 2015.
Updated FY2012 Revenue & Expenditures Park Hill Board of Education June 9, 2011.
BVUSD Facility Workshop September 17, Board Policy-BP 7110 The Board of Trustees recognizes the importance of long-range planning for school facilities.
Capital Appreciation Bonds (CABs): Do They Have a Legitimate Role in Municipal & School Finance September 25, 2012 Capitol Public Finance Group · 1900.
2009 Payable 2010 Levy Certification Independent School District 196 Rosemount-Apple Valley-Eagan Public Schools December 14, 2009 Educating our students.
Levy and Bond Recap Board Report September 10, 2013.
Public Meeting October 20,  Revenues  Expenses  Contract Services.
West Contra Costa USD General Obligation Bond Update Presentation to the Board of Education October 15, 2014.
Long Range Facility Planning assisted by Silver Falls School District.
West Contra Costa USD Presentation to the Facilities Subcommittee January 22, 2013.
Division of Budgets August 22, 2012 Budget and Allocation Capacity Update Presented to the California Transportation Commission Tab 14.
Budget Strategy Directors / Elected Officials - Meeting
Independent Review of FY 2008 Proposed Rates D.C. Water and Sewer Authority Public Hearing June 13, 2007.
Pinole Valley High School (PVHS) Project Status
West Contra Costa USD 2015 General Obligation Bond Presentation to the Facilities Subcommittee March 17, 2015.
West Contra Costa USD Facilities Sub Committee June 12, 2012 Peres Elementary School School Facility Program Funding Update.
Axahachie INDEPENDENT SCHOOL DISTRICT Long Range Facility Planning Committee Presentation October 2, 2014.
August 18, 2011 Facility Master Plan Master Plan Presentation “Listen” “Listen”“Understand”“Create”
NEXT STEPS – BOND PROGRAM Facilities Master Plan Update Facilities Subcommittee – March 17, 2015.
West Contra Costa USD General Obligation Bond Update Presentation to the Facilities Subcommittee September 9, 2014.
West Contra Costa USD Tax Rate Setting Process, November 2012 Bond Election, and Current Topics Presentation to the Facilities Subcommittee August.
Annual Meeting Budget Hearing Budget Process Overview Revenue Limit Calculation and Estimation of Other Revenues December Revenue Limit Calculation.
Preparing for Successful Bond Elections – Twin Rivers Unified Case Study Kim Barnett Executive Director, General Services Twin Rivers Unified School District.
Pinole Valley High School (PVHS) Project Status 1 Facilities Subcommittee Meeting February 10, 2015.
West Contra Costa USD Presentation to the Facilities Subcommittee November 13, 2012.
Portola Middle School and Gompers/Leadership Public Schools OPSC Funding Status Update.
West Contra Costa USD Proposed Refunding Plan Presentation to the Facilities Subcommittee January 11, 2012.
West Contra Costa Unified School District Facilities Subcommittee Meeting December 2, 2014 State School Facility Program Seismic Funding Update.
Presented By: Lisa LeBlanc, Associate Superintendent Recommendation on Valley View ES Facilities Subcommittee – January 6, 2014.
1 West Contra Costa Unified School District December 7, First Interim Financial Report.
1 Capital Financing Options Jane A. Russo, Superintendent Michael P. Bishop, Associate Superintendent, Business Services Joe Dixon, Assistant Superintendent,
West Contra Costa USD Presentation to the Facilities Subcommittee Bond Budget Update March 17, 2012.
Memorial Northwest HOA 2014 Budget. Budget Process Review & Evaluate prior year Budget & Actual Identify new requirements Map the spending to the GL accounts.
1 West Contra Costa Unified School District January 4, Budget Update.
West Contra Costa Unified School District Long-Range Facilities Master Plan West Contra Costa Unified School District Long-Range Facilities Master Plan.
West Contra Costa Unified School District Long-Range Facilities Master Plan West Contra Costa Unified School District Long-Range Facilities Master Plan.
FY17 BUDGET BASICS Minneapolis Public Schools Finance Office.
Presented to the Board of Education April 26, 2016.
West Contra Costa Unified School District Long-Range Facilities Master Plan WCCUSD.net/FMP Facilities Subcommittee Option Recommendation April 19, 2016.
Proposed Budget Fiscal Year 2017 Presentation to the County Commission May 4, 2016 FY16 Proposed Budget Presentation.
SMITHVILLE R-II SCHOOL DISTRICT Tradition of Excellence The Power of One … One Community … One Future! November 4, 2014 SMITHVILLE R-II SCHOOL DISTRICT.
West Contra Costa Unified School District Facilities Subcommittee Meeting April 9, 2013 School Facility Program State Funding Update.
Texas Higher Education Coordinating Board November 4, 2011 Ben Ferrell, Jr., Executive Vice President, Finance & Administration Austin Community College.
PRESENTED BY: REBECCA ALLARD INTERIM ASSISTANT SUPERINTENDENT FINANCE, FACILITIES AND OPERATIONS MARCH 17, 2016 Illinois School Finance.
BUDGET HEARING II Presented to the Board of Education MAY 10, 2016.
West Contra Costa USD General Obligation Bond Program Status Presentation to the Facilities Subcommittee June 11, 2013.
LOCAL OPTION SALES TAX FOR EDUCATION APPROVED BY THE BOARD OF TRUSTEES SEPTEMBER 29, 2015.
West Contra Costa Unified School District Long-Range Facilities Master Plan WCCUSD.net/FMP Board of Education Workshop February 27,
CFW Caldwell Flores Winters, Inc. Facilities Planning, Public Finance, Program Administration Calistoga Joint Unified School District Financing Options.
Board of Education Option Recommendation April 27, 2016
Trimble County Public Schools
Budget Overview Review of Last Years Budget
Davenport School Board Meeting
ELECTRIC REVENUE REFUNDING BONDS SERIES 2016A
West Contra Costa USD 2015 General Obligation Bond
Capital Improvement Plans
Attendance Boundary Development & Revisions
West Contra Costa USD 2015 General Obligation Bond
Presentation transcript:

Presented By: Lisa LeBlanc, Associate Superintendent Framing the Next Steps – Bond Program Facilities Subcommittee – 2/26/15 DRAFT

There is currently $457M in bond authority remaining under Measures D (2010), Measure E (2012) and Measure J (2005) Bond program currently has approximately 14 major construction projects underway The buildings on Pinole Valley HS will be under construction this year Planning and sequencing of the remaining projects is needed Overview 2

Bond Measure Background BondsDateAmountIssuedAuthority Remaining Measure E1988$40M $0 Measure M2000$150M $0 Measure D2002$300M $0 Measure J2005$400M$323M$77M Measure D2010$380M$190M Measure E2012$360M$170M$190M $457M Remaining Authority Note: The BOE approved the sale of $135M on February 11, 2015 (Measure D (2010) $50M and Measure E (2012) $85M

Bond Authority Targeted Issuance Schedule YearMeasure DMeasure EMeasure JTotal 2016/17$60M$65M$125M 2018/19$65M$60M$125M 2020/21$45M$57M$102M$352M 2035/36$77M 2045$20M$8M$28M$105M $457M Note: assumes $48 tax rate per $100,000 of assessed value, 40-year maturity structure and 4% AV growth

Estimated Revenue and Current Project Expenditures REVENUE: AMOUNT: Cash balance as of 7/1/2014 $104M Recently Issued D/E Bonds $135M Available bond authority thru 2021 $352M$591M EXPENDITURES: Expenditures and estimated expenditures for current projects $347M Estimated bond funds available for upcoming projects to be planned $244M Note: available authority assumes $48 tax rate per $100,000 of assessed value, 40-year maturity structure and 4% AV growth (Includes Valley View Temp/Dover Field/Does not include PVHS estimate reconciliation)

Coronado DeAnza Downer El Cerrito HS S. Greenwood/LPS Helms Swim Korematsu Nystrom Ohlone Pinole Valley HS Pinole MS Montalvin Technology Major Projects Currently Underway

Factors that Affect Cash Flow Availability of State Funding Factors affecting amount of issuances (AV, tax rate) Escalation rates (construction cost increases and market conditions/bid climate) Unforeseen conditions Project schedules and related cash needs Maintaining defined budgets Cost efficiencies without compromising program or quality Project scale (i.e. modernization vs. new construction) Timing of passing new General Obligation Bonds

Major Upcoming Projects to be Sequenced Valley View ES - replacementDSA approved Fairmont ES - replacementDSA Approval Stege ES - replacementDSA Approval pending Ohlone ES – Multipurpose/KinderDesign changes needed Richmond HS – Buildings A/BDSA Approval mid 2015 Wilson ES - replacementDSA Approval late Cameron ESMaster Plan - Complete Lake ESMaster Plan-Spring 2015 Highland ESMaster Plan- Complete Olinda ESMaster Plan- Complete Shannon ESMaster Plan- Spring 2015 Hercules Middle/HSMaster Plan-Complete

Planning Process for Consideration Develop and recommend prioritization criteria Consider cost savings efficiencies recommended by CBOC and staff Recommend construction and construction drawing timelines based upon availability of funding and project costs Discuss actions and communications needed for community support if future bond measures considered 9 CBOC to review district construction standards for cost efficiencies that might be applied to upcoming projects Work with staff to understand and verify current expenditures and future project estimates Discuss actions and communications needed for community support if future bond measures considered FACILITIES SUBCOMMITTEE CBOC

Prioritization Criteria for Consideration 10 Cost of Project Condition of buildings (maintenance/operating expenses) Age of buildings Number of students affected Community considerations Educational suitability (special programs, etc.) Status of planning and/or construction drawings Availability of State Funding Geographic distribution of upcoming projects taking into consideration projects already completed in each high school family Capacity / utilization of schools Safety and Security