TRANSPORT of ICARUS from LNGS to CERN Alberto Scaramelli INFN-Milano Following the meeting at LNGS on 11-12/9 118/09/2014A. Scaramelli.

Slides:



Advertisements
Similar presentations
Euratom Mechanical operation on the TPL sector E.Delmas – December 8th /13 Disassembly and reassembly of a sector of the Toroidal Pumped Limiter.
Advertisements

SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Work Zone Safety It Starts With YOU!!. 2 BOOK 7 What is NEW??? IMSA TECHNICAL EXPO October, 2014 Dave Edwards.
EA meeting, Wednesday 6 Dec 2006 TT installation, Jeroen van Tilburg 1 TT installation Installation of the TT station.
INFN-LNF / D. Orecchini – S. Tomassini – 06/24-25/2015 CLAS12 – RICH MECHANICS REVIEW SLIDE 1 RICH MODULE INTEGRATION IN CLAS_12 – LAST LAYOUT RICH MODULE.
Addendum to EDMS document “Instruction Manual for inserting the CMS ZDCs using the HXTC crane” In addition to the ZDC detectors in the TAN instrument.
TRANSPORT of ICARUS from LNGS to CERN Alberto Scaramelli INFN-Milano Following the meeting at LNGS on 11-12/9 Last News 102/10/2014A. Scaramelli.
Assembly Scenarios Draft 1 MODEL simulation based on CXUO-CRY-AP-001.
TMDB delay and production plan Augusto. TMDB Prototype Status The prototype boards almost fully assembled should be delivered this week ( May 5 th ) First.
CDF Decommissioning Status Jonathan Lewis Master Planning Meeting 9 November 2011.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Status of AMS02 Integration Area in Building 867 January 10, 2007.
WA104 Aluminum Cold Vessels A possible scenario. CAVEAT Definition of the experimental layout still under discussion within the ICARUS Collaboration (dimensions.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 12 Jul 2011 LAV construction status: a snapshot 2 A1 Arrived at CERN 29 Jun.
Summary of the WA104, T600 overhauling programme C. Montanari – INFN-PV, Italy M. Nessi – CERN, Switzerland weekly meeting, December 18,
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
Transport & Handling of Detectors TAN Workshop S. Prodon –
TOB meeting, TOB meeting 20 September 2005, Antti Onnela: TOB mechanical integration status and plans n TST-TOB-TIB integration exercise n.
Progress on Hydrogen R&D System
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Installation scenario, status on the installation tools.
Concept Design for LBNF Far detector (LAr single phase)
Installation of the T600 at Fermilab CSN2, September 22,
WA 104 : TOOLS FOR WORK ORGANIZATION IN THE CLEAN ROOM Erwan Bertrand Olga Beltramello.
Increase of the T600 maximum drift distance and preliminary considerations for larger aluminum vessels Claudio Montanari INFN-Pavia, Italy 1ICARUS Meeting.
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
ICARUS Collaboration Meeting Dec A. Scaramelli.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Duy Phan, EN-STI-RBS. Description of the hazards  An Oxygen Deficiency Hazard (ODH) exists when the concentration of O2 ≤ 19.5 % (by volume)  Cold burns.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
 Market Survey  Design, supply, delivery and installation of a Clean Room Facility  at the entrance of the LAr detector tank,  used for the storage.
HGC Cassettes Jim Freeman September 17, Director's Review -- Calorimetry – HGC Cassettes Jim Freeman, 2015 Sept 17.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
Plans for the UT Installation LHCb infrastructure workshop February Burkhard Schmidt for the UT group.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
Ideas on TPC Assembly Volker Prahl, Thomas Schörner-Sadenius Paris, 8/9 October /9 October 2015TSS: TPC Assembly1.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Kitakami Side AHCAL Assembly or anywhere in any detector.
HADES collaboration meeting XXX, Lisbon, 7-10 October, 2015,
The LBNF cryostats Marzio Nessi, CERN 16 March 2017.
Update on PANDA solenoid design
Plans for the construction of the new membrane cryostat in bldg 182
SBN Far Detector Installation & Integration
VELO-installation meeting CERN, January 17, 2006
Complementary ISTC Projects #3888, 3889p
News about the WA104 Programme
CE Status: Activities executed until 03/08 and ongoing
CATIA Design Requirements applied to Handling & Transport at CERN 26th CATIA Forum Jean-Louis GRENARD on Behalf of EN-HE design office 18-May-2017.
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
EHN1 Neutrino Installation Plans
Far Detector Activities Late 2017 – Early 2018
UK RFD Pre-Series cryomodule
Test box for ProtoDUNE SP – Integration Test
Magnet, Support and Infrastructure
UPPSALA UNIVERSITY_GERSEMI PROJECT
DS20k Integration Workshop
Presentation transcript:

TRANSPORT of ICARUS from LNGS to CERN Alberto Scaramelli INFN-Milano Following the meeting at LNGS on 11-12/9 118/09/2014A. Scaramelli

T600 Decommissioning lPlant disassembly 1.Present situation 2.Next step lTPCs transport to CERN 1.Technical solution 2.Preparation in LNGS 3.Actions and Responsabilies lTime schedule 1. Possible Scenarios Slide: 2A. Scaramelli

T600 Decommissioning: a lot of work done From July-August 2013: T600 emptying + warming ‐ up From Sept. 2013, still ongoing: Disassembling; Dismantling Many components already at CERN From Sept. 2013: Design, order, construction of the Transport Frames From Mai 2014: Removal of Opera Barrack & Warp clean room from Hall B Slide: 3A. Scaramelli

Hall-B was an extremely crowded area Slide: 4 You must pass through this leftover space ! A. Scaramelli

Next steps lThermal insulation & cooling screen will be dismantled lSome mechanical obstacle in front of the vessels will be removed the two cold vessels can be opened lIn Tir Gallery some obstacles will be removed Slide: 5A. Scaramelli

Hall B Virtual Top View 6 A. Scaramelli

Results of the Survey 7 lAccording to the measurements made in the past and confirmed in the recent survey, the occupancy and the present layout of the Hall B permit to handle the following max. dimensions and weight : Dimensions 3.90m x 4m x 20m - Weight 40 t lSuch dimensions are fully compatible with the designed Transport Frame. In particular the max. required weight is compatible with the hall B crane capacity. Unfortunately they are presently incompatible with the dimensions of the original cold vessels, which must be therefore dismantled and reconstructed elsewhere. A. Scaramelli

The Transport Frame 19.9m Long 3.815m Large 4m High Total Weight 40t TPC included 8 18/09/2014 A. Scaramelli

TPC Extraction & Transport 9 A. Scaramelli

Object to be transported 4 lifting points (must be dismounted) reducing the height of the box Length of the lifting sling 7m 10 18/09/2014 A. Scaramelli

Present situation in Hall B 11 Restriction of passage 4.7m in front of the XENON tank Transport Frame Exit route from the salle B 18/09/2014 A. Scaramelli

The trailer used for the transport lTransport company : ALIANI lLow bed truck /09/2014 A. Scaramelli

The trailer used for the transport 13 18/09/2014 A. Scaramelli

Methodologies for the loading lSee 3D simulation 14 18/09/2014 A. Scaramelli

Exit route 15 18/09/2014 A. Scaramelli

To be removed in Tir Gallery 16 18/09/2014 A. Scaramelli

Some actions, dates and responsibilities 1 lFrom now on Chiara V. blows clean air inside the cryostat to remove all Argon. The Lab has to find a technical solution. lBy 7 October, Chiara V. opens the welds and unscrew some bolts protecting with plastic the front face. l9 October the box arrives from Spain and by the 10 th it will be pre-positioned in front of the TPC (J.L.Grenard) during the night 9-10 Oct). l13 th October the door (towards ICARUS) of the box will be removed (F.Noto procedure) and the box opening is protected with plastic to avoid dust. l13 th October Claudio M. put in place the plastic tunnel between the cryostat and the box. All electrical services enter there. l14 th Oct – 7 th November: Pavia group will install extraction tools and insert TPC into the box. Slide: 17A. Scaramelli

Some actions & dates 2 l7 th November the Transport Frame will be closed, ready for moving. l10 Th November the Transport Frame will be out of the GS Lab., traveling to CERN: the truck enters into the tunnel in the early morning and is assembled inside the Hall B, leaving GS in the afternoon. l13 th November in the night, the second TF arrives and is positioned in front of the cryostat. Then we have to decide what next, because it is very difficult to be ready for a second transport to CERN for the 10 th of December. Slide: 18A. Scaramelli

Second Transport Frame: scenario 1 lWe give priority to insert the first TPC into the clean room at CERN lWe have to move the insertion tools from GS to CERN together with the Pavia Tecs lInsertion week of 24 th November l4 th December tools and Tecs back in GS and insertion work into the 2 TF can restart lTransport to CERN probably at the end of January or February Slide: 19A. Scaramelli

Second Transport Frame: scenario 2 lWe give priority to insert the second TPC into the TF in GS lAll insertion operation between 17 th Nov and 9 th December lTransport leaves GS to CERN the 10 th. Last possible date. Or leaves end of January lFirst TPC insertion into the clean room at CERN in the week of the 15 th December or in January. Slide: 20A. Scaramelli

Actions & Responsible Persons lLNGS to organize the argon flushing of the ICARUS detector before any operation in October lCERN to confirm with the IRMA-GRU the transport dates lCERN to confirm the transport with the firm Allieni lJ.L. Grenard to provide to GS Lab the list of tools and people he will bring, with all necessary certificates lF. Noto to provide a written procedure for the removal of the box doors lC. Montanari to to provide a written procedure for the extraction and insertion procedure, with all the tools lM.Nessi to order the missing support lCh.Zarra to start the procedure to remove all material for the entrance and exit of the trucks from the bypass towards L’Aquila (2 dewars, guardian barrack, various small material, several lights and signs) lCh. Zarra to organize the removal of the Lab signs inside the freeway tunnel lCh. Zarra to write a letter to the freeway authorities informing of the need for such special transports and agree on the dates and operations lC. Montanari to inform C.h Zarra of the electrical power needs during operation Slide: 21A. Scaramelli

At CERN m 10m 7m Clean room for TPC assembly lA bldg. (185) is being adapted and dedicated to assemble the TPCs in the new cold vessels. A. Scaramelli

Conclusions Slide: 23 lDisassembly of a complex plant as ICARUS and the removal of the main components in such a difficult environment represented very hard work, demanding appropriate procedures/organisation, and care for safety. lWe have experienced some significant delays, essentially due both to the administrative procedures and to the dense crowding of hall B.  A lot of work has already been completed.  But still lots of work remain to be done…. lHowever the transport of the TPCs out of the LNGS will be performed without major interferences on the critical path of the future overhauling program. A. Scaramelli