Module 2 (part 1) Improving Diversion Works John Ratsey

Slides:



Advertisements
Similar presentations
6.5 River Stability and Bank Protection John Ratsey
Advertisements

Flood Profile Modeling with Split Flows and Weirs
6.3 Sediment management options
Change of the flow state
Spillways Abdüsselam ALTUNKAYNAK, PhD Associate Professor,
6.6 Canals and Command Area Structures. (1) Canals in Spate Schemes  traditional systems are diverted to short, steep canals in the upstream areas (with.
1.3Economic Costs and Benefits. Spate irrigated areas are often among the poorest areas in a country and therefore require special attention.
Managing Flooding Hard and Soft Engineering. HARD ENGINEERING This uses technology, large amounts of money to try and control the river. It can prevent.
Floods Hard and Soft Engineering. Hard Engineering This uses technology, large amounts of money to try and control the river. It can prevent floods in.
Challenge of runoff regulation to supply paddy terraces in Subak irrigation schemes.
Why is soil moisture conservation and management vital in spate irrigation?
CASE STUDY OF WADI LABA AND WADI MAI ULE (ELWDP – ERITREA) Lesson 5
Assessment of gravel transport characteristics of the upper Santa Ana River Scott Wright and Toby Minear USGS California Water Science Center Sacramento,
Module 1 : Understanding the Wadis John Ratsey
Sept 4, 2008CVEN 4838/5838Slide #1 Lecture 4 Spillways and Outlet Works.
Long Term Storage Long term storage means to store water during high inflows years for the benefit of low inflows years. Long term storage means to store.
6.4 Improving Diversion Works
SPATE ENGINEERING GASH RIVER - SUDAN Lesson 4
Sediment transport in wadi systems
1 I. Water Supply Networks and Facilities Topic I.4. River Water Intakes: Kinds and Structures Water Intake Kinds General classification: I. According.
CASE STUDY: SHEEB FARMERS ASSOCIATION, ERITREA 2.3.
HOSHIKAWA Keisuke Center for Integrated Area Studies Kyoto University, Japan PNC 2011 Annual Conference and Joint Meetings Thamnop Irrigation and Natural.
. Introduction Rice crop is sensitive to water stress causing reduction in quality and quantity of yield. Therefore management of irrigation is of uttermost.
Sediment Transport in Wadi Systems Part 1: Overview
Sediment transport in wadi systems Part 3 - Sediment management structures and canal design
CASE: HADRAMAWT IMPROVED TRADITIONAL ENGINEERING 6.6.
6.10 SHARC Software usage for Spate irrigation John Paul van der Ham.
1.6 Experience and challenges of spate irrigation projects in Tigray (By Demisew Abate)
Chapter 33 Dam Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Give reasons why.
Diversion of Flood Water from Ganga at Kanpur.  Introduction  Study Area  Flow Pattern of Ganga at Kanpur  Quantification of Divertible Flood  Downstream.
Head works.
SOIL MANAGEMENT AND MOISTURE CONSERVATION
6.7 Improved Traditional Systems
CASE: GASH SUSTAINABLE LIVELIHOODS PROJECT (SUDAN)
Penny Coombes Sarah Wharton Gary Davies Simon White River Bee, Desing FLOOD ALLEVIATION FEASIBILITY.
2.2 Spate water rights and distribution rules. This is Anambar Weir, Balochistan (Pakistan) What happened here?
3.1 Participatory Design. WHY PARTICIPATORY DESIGN?  To understand and agree priorities and make the best design for the system accordingly  To tap.
6.11 Case: Wadi Labka – What to Do When Traditional System Becomes Unsustainable.
6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT Presented by Eyob Yehayis.
4.3 Groundwater management in Spate Irrigation Systems.
Floods Hard and Soft Engineering Lo; to understand the sustainability of differing flood protection methods.
1 Spillway Weirs and its Role in Dam Protection Husam Khaled Al Mubark Abdel Aziz Al Mesnd Roume Al Roume Abdullah Al Qashami Civil and Environmental Engineering.
Bartolome, Mark John Faustino, Frank Lipaopao, John Rei
Presentation - Streams
Assoc. Prof. Dr. Tarkan Erdik
6.9 Case: Hadramawt Improved Traditional Engineering
1.2 Typology of spate irrigation systems
6.12b Belilo Spate Irrigation System
FUSIBILITY STUDY OF GAMBELLA IRRIGATION PROJECTS NOVEMBER 2017.
Spate Irrigation.
Improving Diversion Works
CASE STUDY: SHEEB FARMERS ASSOCIATION دراسة حالة: جمعية مزارعي شيب
6.2 Sedimentation Issues: Overview
6.1 BASIC ENGINEERING New ‘modernised’ diversion structures have promoted larger inequity in the distribution of irrigation water between upstream and.
Middle east [southwest asia] geographic vocabulary
UNIT 8 CANAL HEAD WORKS SANDEEP LECTURER IN CIVIL ENGG. GP MEHAM.
The shapes of stream channels
REGULATION WORK UNIT – 10 LECTURER IN CIVIL ENGG. GP MEHAM SANDEEP.
ECONOMIC COST AND BENEFITS
3.1 PARTICIPATORY DESIGN.
Part 4 - Sediment management options + exercise
6.8 Case - ‘River Engineering Approach’ Wadi Labka – Gabion/ Soil Diversion Spurs.
2.2 Spate water rights and distribution rules
GROUNDWATER MANAGEMENT IN SPATE IRRIGATION SYSTEMS
IMPROVED TRADITIONAL SYSTEMS
Module 3 Irrigation Engineering Principles Version 2 CE IIT, Kharagpur.
3.2.2 Design Considerations
SPATE WATER RIGHTS AND DISTRIBUTION RULES
Field water distribution
FIELD WATER DISTRIBUTION
Presentation transcript:

Module 2 (part 1) Improving Diversion Works John Ratsey

Traditional diversions

Modern diversion structure Concrete weir Gated canal intake Sluiceway Sediment basins Outlet for flushing basins Main canal Flow

Optimum layout of intake

Key components A control structure to limit / stop flow into canal A spillway to reject excess flows back to the wadi A sluiceway to remove sediment / maintain low flow channel Works to divert water to intake (bed bar / gravel embankment / weir)

Typical layout of improved intake

Questions for farmers Do they want protection against floods damaging their canal system? Do they want to be able to stop the flow of water into their canals? Do they want to divert the whole of the wadi flow, or only a part of the flow? What are their priorities?

Design Options Ungated head regulator for existing offtake Ungated head regulator for existing offtake with spillway Gated head regulator for existing offtake Gated head regulator for existing offtake with spillway Optional sluiceway for ejecting sediment and maintaining low flow channel

Design considerations Best location to be determined by comparison of wadi level, field levels (with allowance for rising) and canal slope Intake structure to occupy less than 20% of wadi width Orifice head regulator limits maximum flow into the canal Side spillway enables rejection of excess flow approaching canal intake Gravel embankments will breach to enable passing of big floods

Location selection Intakes are best located at the outside of a bend where the low flow channel will be However, outsides of bends are most vulnerable to erosion

Al Zoran Intake Intake is here Canal is also in outside of bend and needs protection The original intake was probably further downstream and has moved upstream to maintain command

Command and field level rise The water level at the intake needs to be enough to supply water to the first fields during a small flood Otherwise the first farmers on the canal will block the flow to other farmers until they have irrigated their land The design has to consider the likely rise in field levels within the life of the structure

Layer of sediment from one flood Sediment thickness about 5cm from one flood

Rates of field level rise Scheme Annual rise rate, mm/year Wadi Laba Eritrea Upstream fields 8–32 (Measured 1998/99) Middle fields 6–18 Downstream fields 5–9 Wadi Laba Eritrea (Long term estimate) 30 Eastern Sudan 139 Baluchistan mountain systems > 50 Wadi Zabid Upstream fields 20–50 30mm per year x 30 years is 90cm

Edge of Zabid irrigation area Fields are several metres above the desert

Design for the big flood Before designing anything to be built in the wadis, try to visualise the big floods Make provision for the floods to pass with the minimum of damage Allow for the energy head (v²/2g) in the designs

Typical wadi rating curve

Options Gates to only be provided if required by the farmers. A large orifice may be sufficient Sluiceways are more appropriate in the upstream part of wadis where more water is available for flushing Strength / cost of structure will decrease upstream to downstream, but the benefits will also decrease

Wadi Zabid weir 5 Canal 50% of flow Concrete bed bar Masonry wall Gravel embankments will breach in major flood to pass water downstream

Divide wall at Zabid weir 5 Concrete bed bar Masonry divide wall Weir 5 Gravel embankments

Gerhazy canal intake - plan Intake Canal Wadi Gravel embankment Concrete bed bar

Gerhazi canal intake

Intake for Gerhazy canal Farmers use a gravel embankment to close the intake Breastwall with three orifices

Space for the big flood

Bagr canal intake Designed as one orifice but modified to two gates, but blockage by trash is a problem Gravel embankment to divert water