Chapter 6 Investment Decision Rules

Slides:



Advertisements
Similar presentations
Investment Decision Rules
Advertisements

Capital Budgeting Decision Rules
Fin351: lecture 5 Other Investment Criteria and Free Cash Flows in Finance Capital Budgeting Decisions.
Capital Budgeting Processes And Techniques
9-0 Chapter 9: Outline Net Present Value The Payback Rule The Discounted Payback The Average Accounting Return The Internal Rate of Return The Profitability.
Hawawini & VialletChapter 7© 2007 Thomson South-Western Chapter 7 ALTERNATIVES TO THE NET PRESENT VALUE RULE.
Chapter McGraw-Hill/Irwin Copyright © 2006 by The McGraw-Hill Companies, Inc. All rights reserved. 9 Net Present Value and Other Investment Criteria.
© Prentice Hall, Chapter 8 Evaluating Investment Projects Shapiro and Balbirer: Modern Corporate Finance: A Multidisciplinary Approach to Value.
Managerial Finance Finance 6335 Lecture 5 Chapter 6 & 7 Alternative Decision Rules Fundamentals of Capital Budgeting Ronald F. Singer.
McGraw-Hill/Irwin Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. 9 Net Present Value and Other Investment Criteria.
Chapter McGraw-Hill Ryerson © 2013 McGraw-Hill Ryerson Limited 9 Prepared by Anne Inglis Net Present Value and Other Investment Criteria.
B280F Introduction to Financial Management
T9.1 Chapter Outline Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization 9.1Net Present Value 9.2The Payback Rule 9.3The Average.
Net Present Value and Other Investment Criteria (Capital Budgeting)
McGraw-Hill/Irwin Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. 9 Net Present Value and Other Investment Criteria.
Capital Budgeting Net Present Value Rule Payback Period Rule
2-1 Copyright © 2006 McGraw Hill Ryerson Limited prepared by: Sujata Madan McGill University Fundamentals of Corporate Finance Third Canadian Edition.
Chapter 9 Net Present Value and Other Investment Criteria
Net Present Value and Other Investment Criteria
0 Net Present Value and Other Investment Criteria.
P.V. VISWANATH FOR A FIRST COURSE IN FINANCE 1. 2 Decision Criteria NPV The Payback Rule Accounting Rate of Return IRR Mutually Exclusive Projects The.
Chapter 9 INVESTMENT CRITERIA Pr. Zoubida SAMLAL GF 200.
1 INVESTMENT DECISION RULES (REVIEW). 2 3 NPV and Stand-Alone Projects Consider a take-it-or-leave-it investment decision involving a single, stand-alone.
© 2003 The McGraw-Hill Companies, Inc. All rights reserved. Net Present Value and Other Investment Criteria Chapter Nine.
Chapter – 5 & 6: NPV & Other Investment Rules, Cash flows
© 2003 The McGraw-Hill Companies, Inc. All rights reserved. Net Present Value and Other Investment Criteria Chapter 9.
Ch 6 Project Analysis Under Certainty
CHAPTER 10 The Basics of Capital Budgeting Omar Al Nasser, Ph.D. FIN
T9.1 Chapter Outline Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization 9.1Net Present Value 9.2The Payback Rule 9.3The Discounted.
NPV and Other Investment Criteria P.V. Viswanath Based partly on slides from Essentials of Corporate Finance Ross, Westerfield and Jordan, 4 th ed.
FIN 40153: Advanced Corporate Finance EVALUATING AN INVESTMENT OPPORTUNITY (BASED ON RWJ CHAPTER 5)
Chapter 9 Net Present Value and Other Investment Criteria
P.V. VISWANATH FOR A FIRST COURSE IN FINANCE 1. 2 Decision Criteria NPV IRR The Payback Rule EVA Mutually Exclusive Projects The case of multiple IRRs.
Chapter 9 Net Present Value and Other Investment Criteria
© 2003 The McGraw-Hill Companies, Inc. All rights reserved. Net Present Value and Other Investment Criteria Chapter Nine.
Capital Budgeting Decision Tools 05/17/06. Introduction Capital Budgeting is the process of identifying, evaluating, and implementing a firm’s longer.
Copyright © 2011 Pearson Prentice Hall. All rights reserved. Chapter 6 Investment Decision Rules.
© 2010 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible Web site, in whole or in part.
Good Decision Criteria
AEC 422 Fall 2014 Unit 2 Financial Decision Making.
T9.1 Chapter Outline Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization 9.1Net Present Value 9.2The Payback Rule 9.3The Average.
Chapter 4 The Time Value of Money
Hawawini & VialletChapter 71 ALTERNATIVES TO THE NPV RULE.
Investment Decisions and Capital Budgeting
8- 1 McGraw Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved Chapter 8 Net Present Value and Other Investment Criteria.
Unit 4 – Capital Budgeting Decision Methods
Class 3 Investment Decisions and Capital Budgeting.
CORPORATE FINANCE I ESCP-EAP European Executive MBA
Chapter 3 Arbitrage and Financial Decision Making
Net Present Value and Other Investment Rules. Percent of CFOs who say they use the following rules to evaluate projects 2.
Conflicting NPV and IRR ranking The ranking of alternative proposal and the decision regarding selection of a proposal on the basis of NPV and IRR may.
T9.1 Chapter Outline Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization 9.1Net Present Value 9.2The Payback Rule 9.3The Discounted.
Financial management: lecture 6 NPV and other Investment Criteria Capital Budgeting Decisions.
13-1 Agenda for 30 July (Chapter 9) Assessment of various commonly used methods for deciding how capital is to be allocated. Net Present Value (NPV) The.
Investment Decision Rules
Basics of Capital Budgeting. An Overview of Capital Budgeting.
Net Present Value and Other Investment Rules
0 Corporate Finance Ross  Westerfield  Jaffe Seventh Edition 6 Chapter Six Some Alternative Investment Rules.
Chapter 6 Investment Decision Rules 6-2 Investment Decisions Leave the latte, take the chocolate (Bloomberg, Sept 15, 2009) Kraft may be ready to give.
Other Criteria for Capital Budgeting Text: Chapter 6.
Part Three: Information for decision-making Chapter Thirteen Capital investment decisions: Appraisal methods Use with Management and Cost Accounting 8e.
Chapter 6 – Multiple Cash FlowsCopyright 2008 John Wiley & Sons 1 CHAPTER 10 The Fundamentals of Capital Budgeting.
Chapter 7 Investment Decision Rules Copyright © 2009 Pearson Prentice Hall. All rights reserved. 7-1.
AcF 214 Tutorial Week 2 1. Question 1. Cost of plant: $100 million upfront Profits: $30 m. per year (at the end of every year) and are expected to last.
Investment Decision Rules. outline Decision rules for stand-alone projects – NPV, Payback, IRR, EVA Decision rules for mutually exclusive investment opportunities.
Chapter 8 Investment Decision Rules.
Investment Decision Rules
Investment Decision Rules
How do Managers Decide what Projects to Invest in? and Why?
Capital Budgeting Decision Rules
Presentation transcript:

Chapter 6 Investment Decision Rules

Chapter Outline 6.1 NPV and Stand-Alone Projects 6.2 Alternative Decision Rules 6.3 Mutually Exclusive Investment Opportunities 6.4 Project Selection with Resource Constraints

Learning Objectives Define net present value, payback period, internal rate of return, profitability index, and incremental IRR. Describe decision rules for each of the tools in objective 1, for both stand-alone and mutually exclusive projects. Given cash flows, compute the NPV, payback period, internal rate of return, profitability index, and incremental IRR for a given project. Compare each of the capital budgeting tools above, and tell why NPV always gives the correct decision. Define Economic Value Added, and describe how it can be used in capital budgeting.

6.1 NPV and Stand-Alone Projects Consider a take-it-or-leave-it investment decision involving a single, stand-alone project for Fredrick Feed and Farm (FFF). The project costs $250 million and is expected to generate cash flows of $35 million per year, starting at the end of the first year and lasting forever.

NPV Rule The NPV of the project is calculated as: The NPV is dependent on the discount rate.

Figure 6.1 NPV of FFF’s New Project If FFF’s cost of capital is 10%, the NPV is $100 million and they should undertake the investment.

Measuring Sensitivity with IRR At 14%, the NPV is equal to 0, thus the project’s IRR is 14%. For FFF, if their cost of capital estimate is more than 14%, the NPV will be negative, as illustrated on the previous slide.

Alternative Rules Versus the NPV Rule Sometimes alternative investment rules may give the same answer as the NPV rule, but at other times they may disagree. When the rules conflict, the NPV decision rule should be followed.

6.2 Alternative Decision Rules The Payback Rule The payback period is amount of time it takes to recover or pay back the initial investment. If the payback period is less than a pre-specified length of time, you accept the project. Otherwise, you reject the project. The payback rule is used by many companies because of its simplicity. However, the payback rule does not always give a reliable decision since it ignores the time value of money.

Example 6.1

Example 6.1 (cont'd)

Alternative Example 6.1 Problem A B C Cost $80 $120 $150 Cash Flow $25 Projects A, B, and C each have an expected life of 5 years. Given the initial cost and annual cash flow information below, what is the payback period for each project? A B C Cost $80 $120 $150 Cash Flow $25 $30 $35

Alternative Example 6.1 Solution Payback A Project B Project C $80 ÷ $25 = 3.2 years Project B $120 ÷ $30 = 4.0 years Project C $150 ÷ $35 = 4.29 years

The Internal Rate of Return Internal Rate of Return (IRR) Investment Rule Take any investment where the IRR exceeds the cost of capital. Turn down any investment whose IRR is less than the cost of capital.

The Internal Rate of Return (cont'd) The IRR Investment Rule will give the same answer as the NPV rule in many, but not all, situations. In general, the IRR rule works for a stand- alone project if all of the project’s negative cash flows precede its positive cash flows. In Figure 6.1, whenever the cost of capital is below the IRR of 14%, the project has a positive NPV and you should undertake the investment.

The Internal Rate of Return (cont'd) In other cases, the IRR rule may disagree with the NPV rule and thus be incorrect. Situations where the IRR rule and NPV rule may be in conflict: Delayed Investments Nonexistent IRR Multiple IRRs

The Internal Rate of Return (cont'd) Delayed Investments Assume you have just retired as the CEO of a successful company. A major publisher has offered you a book deal. The publisher will pay you $1 million upfront if you agree to write a book about your experiences. You estimate that it will take three years to write the book. The time you spend writing will cause you to give up speaking engagements amounting to $500,000 per year. You estimate your opportunity cost to be 10%.

The Internal Rate of Return (cont'd) Delayed Investments Should you accept the deal? Calculate the IRR. The IRR is greater than the cost capital. Thus, the IRR rule indicates you should accept the deal.

Financial Calculator Solution

The Internal Rate of Return (cont'd) Delayed Investments Should you accept the deal? Since the NPV is negative, the NPV rule indicates you should reject the deal.

Figure 6.2 NPV of Star’s $1 million Book Deal When the benefits of an investment occur before the costs, the NPV is an increasing function of the discount rate.

The Internal Rate of Return (cont'd) Nonexistent IRR Assume now that you are offered $1 million per year if you agree to go on a speaking tour for the next three years. If you lecture, you will not be able to write the book. Thus your net cash flows would look like:

The Internal Rate of Return (cont'd) Nonexistent IRR By setting the NPV equal to zero and solving for r, we find the IRR. In this case, however, there is no discount rate that will set the NPV equal to zero.

Figure 6.3 NPV of Lecture Contract No IRR exists because the NPV is positive for all values of the discount rate. Thus the IRR rule cannot be used.

The Internal Rate of Return (cont'd) Multiple IRRs Now assume the lecture deal fell through. You inform the publisher that it needs to increase its offer before you will accept it. The publisher then agrees to make royalty payments of $20,000 per year forever, starting once the book is published in three years. Should you accept or reject the new offer?

The Internal Rate of Return (cont'd) Multiple IRRs The cash flows would now look like: The NPV is calculated as:

The Internal Rate of Return (cont'd) Multiple IRRs By setting the NPV equal to zero and solving for r, we find the IRR. In this case, there are two IRRs: 4.723% and 19.619%. Because there is more than one IRR, the IRR rule cannot be applied.

Figure 6.4 NPV of Star’s Book Deal with Royalties If the opportunity cost of capital is either below 4.723% or above 19.619%, you should accept the deal.

The Internal Rate of Return (cont'd) Multiple IRRs Between 4.723% and 19.619%, the book deal has a negative NPV. Since your opportunity cost of capital is 10%, you should reject the deal.

The Internal Rate of Return (cont'd) IRR Versus the IRR Rule While the IRR rule has shortcomings for making investment decisions, the IRR itself remains useful. IRR measures the average return of the investment and the sensitivity of the NPV to any estimation error in the cost of capital.

Economic Profit or EVA EVA and Economic Profit Economic Profit The difference between revenue and the opportunity cost of all resources consumed in producing that revenue, including the opportunity cost of capital

Economic Profit or EVA (cont'd) EVA and Economic Profit Economic Value Added (EVA) The cash flows of a project minus a charge for the opportunity cost of capital

Economic Profit or EVA (cont'd) EVA When Invested Capital is Constant EVA in Period n (When Capital Lasts Forever) where I is the project’s capital, Cn is the project’s cash flow in time period n, and r is the cost of capital. r × I is known as the capital charge

Economic Profit or EVA (cont'd) EVA When Invested Capital is Constant EVA Investment Rule Accept any investment in which the present value (at the project’s cost of capital) of all future EVAs is positive. When invested capital is constant, the EVA rule and the NPV rule will coincide.

Example 6.2

Example 6.2 (cont'd)

Alternative Example 6.2 Problem Ranger has an investment opportunity which requires an upfront investment of $150 million. The annual end-of-year cash flows of $14 million dollars are expected to last forever. The firm’s cost of capital is 8%. Compute the annual EVA and the present value of the project.

Alternative Example 6.2 Solution Using Eq. 6.1, the EVA each year is: The present value of the EVA perpetuity is:

Economic Profit or EVA (cont'd) EVA When Invested Capital Changes EVA in Period n (When Capital Depreciates) Where Cn is a project’s cash flow in time period n, In – 1 is the project’s capital at time period n – 1, and r is the cost of capital When invested capital changes, the EVA rule and the NPV rule coincide.

Example 6.3

Example 6.3 (cont'd)

6.3 Mutually Exclusive Investment Opportunities Mutually Exclusive Projects When you must choose only one project among several possible projects, the choice is mutually exclusive. NPV Rule Select the project with the highest NPV. IRR Rule Selecting the project with the highest IRR may lead to mistakes.

Differences in Scale If a project’s size is doubled, its NPV will double. This is not the case with IRR. Thus, the IRR rule cannot be used to compare projects of different scales.

Differences in Scale (cont'd) Identical Scale Consider two projects: Girlfriend’s Business Laundromat Initial Investment $1,000 Cash FlowYear 1 $1,100 $400 Annual Growth Rate -10% -20% Cost of Capital 12%

Differences in Scale (cont'd) Identical Scale Girlfriend’s Business

Differences in Scale (cont'd) Identical Scale Laundromat IRR = 20% Both the NPV rule and the IRR rule indicate the girlfriend’s business is the better alternative.

Figure 6.5 NPV of Investment Opportunities The NPV of the girlfriend’s business is always larger than the NPV of the single machine laundromat. The IRR of the girlfriend’s business is 100%, while the IRR for the laundromat is 20%.

Differences in Scale (cont'd) Changes in Scale What if the laundromat project was 20 times larger? The NPV would be 20 times larger, but the IRR remains the same at 20%. Give an discount rate of 12%, the NPV rule indicates you should choose the 20-machine laundromat (NPV = $5,000) over the girlfriend’s business (NPV = $4,000).

Figure 6.6 NPV of Investment Opportunities with the 20-Machine Laundromat The NPV of the 20-machine laundromat is larger than the NPV of the girlfriend’s business only for discount rates less than 13.9%.

Differences in Scale (cont'd) Percentage Return Versus Impact on Value The girlfriend’s business has an IRR of 100%, while the 20-machine laundromat has an IRR of 20%, so why not choose the girlfriend’s business? Because the 20-machine laundromat makes more money It has a higher NPV.

Differences in Scale (cont'd) Percentage Return Versus Impact on Value Would you prefer a 200% return on $1 dollar or a 10% return on $1 million? The former investment makes only $2, while the latter opportunity makes $100,000. The IRR is a measure of the average return, but NPV is a measure of the total dollar impact on value.

Timing of Cash Flows Another problem with the IRR is that it can be affected by changing the timing of the cash flows, even when that change in timing does not affect the NPV. It is possible to alter the ranking of projects’ IRRs without changing their ranking in terms of NPV. Hence you cannot use the IRR to choose between mutually exclusive investments.

Timing of Cash Flows (cont'd) Assume you are offered a maintenance contract on the laundromat machines which would cost $250 per year per machine. With this contract, you would not have to pay for maintenance and so the cash flows from the machines would not decline. The expected cash flows would then be: $400 – $250 = $150 per year per machine

Timing of Cash Flows (cont'd) The time line would now be: The NPV of the project remains $5,000 but the IRR falls to 15%.

Figure 6.7 NPV With and Without the Maintenance Contract

Timing of Cash Flows (cont'd) The NPV without the maintenance contract exceeds the NPV with the contract for discount rates that are greater than 12%. The IRR without the maintenance contract (20%) is larger than the IRR with the maintenance contract (15%). The correct decision is to agree to the contract if the cost of capital is less than 12% and to decline the contract if the cost of capital exceeds 12%. With a 12% cost of capital, you are indifferent.

The Incremental IRR Rule Incremental IRR Investment Rule Apply the IRR rule to the difference between the cash flows of the two mutually exclusive alternatives (the increment to the cash flows of one investment over the other).

The Incremental IRR Rule (cont'd) Incremental IRR Rule Application The following timeline illustrates the incremental cash flows of the maintenance contract laundromat over the laundromat without the contract.

The Incremental IRR Rule (cont'd) Incremental IRR Rule Application Setting this equation equal to zero and solving for r gives an IRR of 12%. Applying the incremental IRR rule, you should take the contract when the cost of capital is less than 12%. Because your cost of capital is 12%, you are indifferent. This finding concurs with the NPV rule.

The Incremental IRR Rule (cont'd) Shortcomings of the Incremental IRR Rule The fact that the IRR exceeds the cost of capital for both projects does not imply that both projects have a positive NPV. The incremental IRR may not exist. Multiple incremental IRRs could exist. You must ensure that the incremental cash flows are initially negative and then become positive. The incremental IRR rule assumes that the riskiness of the two projects is the same.

6.4 Project Selection with Resource Constraints Evaluation of Projects with Different Resource Constraints Consider three possible projects that require warehouse space.

Profitability Index The profitability index can be used to identify the optimal combination of projects to undertake. From Table 6.1, we can see it is better to take projects B & C together and forego project A.

Example 6.4

Example 6.4 (cont'd)

Shortcomings of the Profitability Index In some situations the profitability Index does not give an accurate answer. Suppose in Example 6.4 that NetIt has an additional small project with a NPV of only $100,000 that requires 3 engineers. The profitability index in this case is 0.1 / 3 = 0.03, so this project would appear at the bottom of the ranking. However, 3 of the 190 employees are not being used after the first four projects are selected. As a result, it would make sense to take on this project even though it would be ranked last.

Shortcomings of the Profitability Index (cont'd) With multiple resource constraints, the profitability index can break down completely.