June 25-26, 2002D&D Lessons Learned Workshop1 Overview of the TFTR D&D Project Erik D. Perry D&D Lessons Learned Workshop June 25-26, 2002 PPPL.

Slides:



Advertisements
Similar presentations
East Hampton High School July 2013 – July 2014 Design Phases.
Advertisements

1 EM Update and Perspective David Huizenga Senior Advisor for Environmental Management 2012 DOE Project Management Workshop April 3, 2012.
School for drafting regulations Nuclear Safety Decommissioning Vienna, 2-7 December 2012 Tea Bilic Zabric.
KY Dept. for Environmental Protection 2013 – 2017 Five Year Update KY Division of Waste Management Statewide Solid Waste Planning and Recycling Workshop.
Lock-Out/Tag-out.  What is lock-out/tag-out (LOTO)?  The proper procedure for installing locks and tags.  The proper procedure for removing locks and.
TRU Waste Processing Center Culture and Successful Implementation of an ISO Certified Environmental Management System Presented at the DOE ISM Conference.
Standard Operating Procedures.  To understand: › The purpose of having SOP’s and how they affect the daily workings of laboratories.  To discuss: ›
Capital Asset Management CATS Presentation December 12, 2007 Today’s Presenter: Anna Jensen, Director of Auxiliary Accounting, Capital Asset Management,
MODULE “STRATEGY DEVELOPMENT”
NCSX NCSX DCT Project Meeting Raki Slide 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PROJECT MANAGEMENT.
Capabilities & Competencies An Introduction to EnergySolutions September 19, 2007 Scott Baskett Erik Vogeley.
Engineering Standards Working Group Annual Meeting June 24-25, 2002 DOE Nevada Support Facility June 2002 Joe B Stringer, PE Framatome ANP DE&S.
- Site Summary Revised Format for EM QPRs and MPRs Site Generated Slides May
1 29 CFR THE CONTROL OF HAZARDOUS ENERGY.
Authorization and Inspection of Cyclotron Facilities Inspections.
Authorization and Inspection of Cyclotron Facilities Authorization for the Decommissioning of the Facility.
1/18/2005Module 41 How the NCSX Project Does Business Work Planning & Design Review Processes.
Construction Work Packaging
1 DOE IMPLEMENTATION WORKSHOP ASSESSING MY EMS Steven R. Woodbury
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Cultivating a Safety Culture within a Creative Environment Frances Alston Manager, Environmental, Safety & Waste Management.
Work Control Center Thomas Meighan D&D Lessons Learned Workshop June 25-26, 2002 PPPL.
OSU-CHS ALARA Statement The OSU-CHS radiation safety program will be conducted in such a manner so that exposure to faculty, staff, students, the public,
MODULE “PROJECT MANAGEMENT AND CONTROL” SAFETY ASSESSMENT DURING DECOMMISSIONING SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
Office of Acquisition and Property Management Proposed Changes to Attachment G FY 2011 – FY 2015 Five Year Plan.
Overview of TFTR D&D Hazards Jerry Levine Head, Environment, Safety & Health.
Using ISMS Principles and Functions in Developing an ARRA Readiness Review Process Presented by Linda K. Rogers Assessments & Readiness Programs Manager.
June 25-26, 2002D&D Lessons Learned Workshop1 Summary of Lessons Learned James H. Chrzanowski D&D Lessons Learned Workshop June 25-26, 2002 PPPL.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
J. Levine5/21/02 NCSX ENVIRONMENT, SAFETY & HEALTH (ES&H) NCSX Conceptual Design Review (CDR) May 21, 2002.
June 25-26, 2002D&D Lessons Learned Workshop1 D&D Health Physics Issues George Ascione / Carl Tilson D&D Lessons Learned Workshop June 25-26, 2002 PPPL.
Do Work Safely DOE Hanford Site Recovery Act Support to New Workers Ted Giltz Hanford Site Recovery Act Project Manager
Work Control Center Overview. 2 Purpose of Work Control Center Allow engineering to concentrate on developing procedures and technologies Allow field.
NSTX-U Construction Erik Perry Princeton Plasma Physics Laboratory NSTX Upgrade Readiness to Operate Review LSB B318 December 9-11, 2014 NSTX-U Supported.
Specific Safety Requirements on Safety Assessment and Safety Cases for Predisposal Management of Radioactive Waste – GSR Part 5.
ISM at the Savannah River Site
HSS Inspection of Environment, Safety, and Health Programs at BNL Accelerator Safety Workshop E. Lessard Collider-Accelerator Department August 12-14,
Nuclear Research and consultancy Group European Radiation Survey Site Execution Manual Leo van Velzen ENVIRONET Kick-off meeting Vienna 23 – 26 November.
Think safe. Act safe. Be safe. LEHR Site Annual Soil Management Plan Training Sue Fields, Environmental Health & Safety Sept,
1 EM Update Presented to the National Governors Association Federal Facilities Task Force Dr. Inés Triay Principal Deputy Assistant Secretary for Environmental.
Qualification & Training of Work Planners Steven K. Little Work Control Department Manager.
Research and Test Reactor Decommissioning Inspections Gerald A. Schlapper, PhD, PE, CHP Health Physicist Division of Nuclear Materials Safety Region I.
Office of Pipeline Safety Remedial Action Review Protocol Integrity Management Workshop July 23-24, 2002.
DECOMMISSIONING OF NUCLEAR POWER PLANTS IN THE CZECH REPUBLIC Peter Lietava Division of Radioactive Waste and Spent Fuel Management State Office for Nuclear.
Expert Review of the Licensing Documentation of the Centralized Facility for Long-Term Storage of Disused Sealed Radiation Sources Oleksii Tokarevskyi.
Laboratory Decommissioning : Essential Tools and Lessons Learned Jim Carscadden Division of Environmental Protection Office of Research Facilities.
Project Delivery Working Group FY2016 EFCOG Annual Meeting Robert P. Miklos Idaho National Laboratory Battelle Energy Alliance Working Group Chair June.
Federal Aviation Administration Oklahoma Airport Operator’s Association Reimbursable Process Planning & Requirements Group National Airspace System Planning.
Environmental Management Division 1 NASA Headquarters Environmental Management System (EMS) Michael J. Green, PE NASA EMS Lead NASA Headquarters Washington,
7/24/011 TFTR D&D Status July 24, /24/012 Project Status The TFTR D&D Project will be completed on time and within budget.
FY 2012 Budget Press Briefing February 14, NRC FY 2012 Budget NRC Mission: License and regulate the Nation’s civilian use of byproduct, source,
Construction Work Packaging
Large Synoptic Survey Telescope
WASTE MANAGEMENT at COMMUNITY LEVEL Rwanda experience
NNSA Project Reviews NNSA Office of Project Analysis, Oversight, and Review (NA-APM-1.1) June 7, 2017 Dwight Henderson, Director
John Christian President, Logistics, Processing and Disposal
SESSION 3 Policy Framework
Vermont Yankee Decommissioning Update
Janet R. Schlueter Senior Director, Radiation and Materials Safety
Research Reactor Decommissioning Demonstration Project (R2D2)
“Prepare, Prevent, Respond”
Project Update - Accomplishments March 28, 2018
Research and Test Reactor Decommissioning Inspections
Understanding the Space Park Requirements
INDOT Storm Water Management
Controlling Project Cost and Schedule
Course Structure.
DOE Review of the LCLS Project October 2006
Research and Test Reactor Decommissioning Inspections
Presentation transcript:

June 25-26, 2002D&D Lessons Learned Workshop1 Overview of the TFTR D&D Project Erik D. Perry D&D Lessons Learned Workshop June 25-26, 2002 PPPL

June 25-26, 2002D&D Lessons Learned Workshop2 Overview of TFTR D&D Schedule: October 1999 through September 2002 Original Estimated Project Cost: $40.3M Projected Project Cost at Completion: $36.8M Objectives: –Remove activated and/or contaminated components from the TFTR Test Cell, Test Cell Basement and Tritium Area. (Tritium Area later changed to mothball) –Provide data for the decommissioning of future fusion projects.

June 25-26, 2002D&D Lessons Learned Workshop3 TFTR D&D Summary Schedule

June 25-26, 2002D&D Lessons Learned Workshop4 TFTR Before D&D

June 25-26, 2002D&D Lessons Learned Workshop5 Overview of TFTR D&D cont Not a typical decontamination and decommissioning (D&D) project Will not be returned to “green field” conditions Facility will not be released for unrestricted use Not a capital project - funded with operating money

June 25-26, 2002D&D Lessons Learned Workshop6 TFTR D&D Organization

June 25-26, 2002D&D Lessons Learned Workshop7 Management of TFTR D&D Project Used existing PPPL Project Control Systems (PCS) Cost - Performance Measurement System employed utilizing earned value techniques Schedule - PC based “Primavera” System Management Meetings / Project Reports

June 25-26, 2002D&D Lessons Learned Workshop8 Work Breakdown Structure 1.0Engineering 1.1Oversight & Planning 1.2Area Preparations 1.3Non-Tokamak Removals 1.4Tokamak Removal Engineering 2.0Field Operations 2.1Oversight & Support (Field Ops) 2.2Area Preparations (Field Ops) 2.3Non-Tokamak Removals (Field Ops) 2.4Tokamak Removals (Field Ops)

June 25-26, 2002D&D Lessons Learned Workshop9 Work Breakdown Structure cont 3.0Project Management 3.1Project Office 3.2Work Control Center 3.3Configuration and Document Control 4.0Health Physics and Safety 4.1HP Oversight 4.2Safety Oversight

June 25-26, 2002D&D Lessons Learned Workshop10 Work Breakdown Structure cont 5.0Radwaste Operations 5.1 Radwaste Management 5.2Containers and Supplies 5.3Transportation and Disposal 5.4Mixed Waste

June 25-26, 2002D&D Lessons Learned Workshop11 Conduct of Operations Worker safety highest priority Protecting environment from tritium release Different set of hazards than TFTR operations Centralized control of work activities Procedure compliance mandatory Clear responsibility and accountability

June 25-26, 2002D&D Lessons Learned Workshop12 Work Package Process Engineering »Define work scope »Conduct Peer Reviews and Design Reviews »Prepare installation/removal procedure »Define prerequisites for field work »Update or void drawings after removal is complete

June 25-26, 2002D&D Lessons Learned Workshop13 Work Package Process cont Work Control Center »Review Engineering Package for completeness »Ensure prerequisites are completed prior to issuing package for work »Arrange for all permits »Release work package to field per schedule »Arrange for resolution of field problems »Return completed work package to Engineering for drawing update/voiding

June 25-26, 2002D&D Lessons Learned Workshop14 Work Package Process cont Construction »Verify and/or perform safing / lockout/tagout per PPPL procedures as required »Perform field work per procedure »Return completed work package to Work Control Center

June 25-26, 2002D&D Lessons Learned Workshop15 Summary The TFTR D&D Project has been performed safely, on time and within budget