Pippa Wells25 October 20051 Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
SCT Power Supply Installation Schedule Jan Bohm, Prague AS, 4 th November 2005 The SCT Power Supply System will be installed in 22 LV&HV racks situated.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
31 January 2006A.Ciocio - SCTSG1 Type IV cables and PP3 Installation Type IV installation Connector in situ work Status of PP3 Testing.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
14 February 2006A.Ciocio - ID Week1 SCT Services Procurement & Installation Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing MTF Workpackage.
P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
ID week - 26 September 2006 A. Ciocio1 SCT Services Installation SCT Cables Web page
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB Fabio Montecassiano INFN PH/CMM.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
8 June 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Testing & Installation Plan Workpackage
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Technical Support Activities in PH-ADO-PO
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
14 December 2005A.Ciocio - SCTSG1 Services and Patchpanels Installation Type IV installation Connector in situ work Status of PP3 Type II/III Testing.
ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)
7 March 2006A.Ciocio - SCTSG1 SCT Services and Patch Panels Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing Workpackage
9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage
AMS-02 tracker mechanics status of construction, assembly, integration Ladder assembly Ladder installation on planes Integration details, cooling loop,
13 September 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Delivery Installation Connector work Testing Summary.
Gas System production for LHC detectors Stefan Haider EP / TA1 - Gas.
Pending mechanics issues for electronics/services (updated 18/08/05 by Ana) Fixation/shielding for 2 LV PS (no fingers):  - Clermont worked out a proposal.
SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
25 October 2005A. Ciocio - SCTSG1 Type II/III Cables and PP1 Status & Plan.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
1 G. Aielli for the RPC community. General information  BOE to be delivered in September  Detector design is over  Production facility reviewd and.
31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
August 04 Jason Tarrant CCLRC1 SCE EC Design & Manufacture l Progress of SCT EC »Support Structure (Required for Disc Assembly 2004) »Services (Required.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Comments on Engineering talk by A. Catinaccio at Inner Tracker Engineering Meeting CERN ) Fixed length barrel layout drawing by C. Bault (Strawman.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
LV-HV cable reuse for the Si Tracker Being worked out with S. Wenig.
Cables Ian Crotty 8 May 2012 Cables for the RE4 Upscope in CMS News. The HV cables are in the Integration DB (INB/904) The Hv order is confirmed. Need.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
ATLAS Plenary, Feb. 18th, 05Commissioning1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Cables for the RE4 Upscope in CMS
Service channels between Tracker and PP1
Services – First Considerations Sigi Wenig / Nicolas Massol ATLAS Tracker Upgrade Workshop Valencia December 2007 Existing services (in cryostat.
CMS Area Working Group Meeting
Installation plans from mid 2005
ATL-IC-ES new version available - approval starts
Presentation transcript:

Pippa Wells25 October Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates PS installation plan Readout installation plan – covered by Janet PS and ROD mapping

Pippa Wells25 October Where to find information? Installation WP document Tuesday mornings, CRM (control room management) meetings (Pamela Ferrari, Sandra Ciocio attend for ID). Any installation in racks in US(A)15 should be discussed here Wednesday mornings ID/TC installation meeting Numerous ID representatives Focussing on services installation so far. New schedule v.7.09 – talks by Miikka Kotamaki in the last TMB Schedule is now under scrutiny Safety course Level 4 course mentioned in the bulletin is for LHC machine experts only – not for work in ATLAS Safety course in English is now available every day in Building 55

Pippa Wells25 October Timescales for services - NEW Type IV installation complete on US side. USA just starting. Will drop to lower priority when type II/II cable installation begins. 2 November – barrel calorimeter moves to z=0 (this is an additional delay since the last TMB) Sequence in a sector is: Tubes, fibres, heater cables, SCT cables, (Muon chambers), TRT cables, pixel cables 7.09 sequenceStart dateDurationComments 5 (top)22 November5 daysOnly 2x6 DCS cables 315 December15 daysWill start with fibres (bottom) 1 15,11

Pippa Wells25 October Organisation for type II/III services New organisational effort to work out detailed installation strategy Management team being established Nicolas Massol (TC - coordinator), Sigi Wenig Marek Stodulski (leaving), Jack Fowler (part time), Stefan Valker, Hans Danielsson Technical follow up from Marco Olcese (based in Genova and commuting to CERN from Nov 05) Installation teams Cables at PPB/F1: Need experienced people from the subsystems to make connections at PPB/F1 Cables over cryostat flange: 8 people from Prague Cables from tile gaps outwards: TC installation team of Russians (already in place) Tubes on flange: current installation team Design work on flange should not be the bottleneck: plan to finish by end of the year

Pippa Wells25 October List of SCT cables in sector 3 To be extracted from services inventory by Sigi Wenig…

Pippa Wells25 October Planning for type II/III power cables Type II/III service installation is supposed to start on 15 th December in sector 3 Company are at present making double length harnesses with type II cable and connectors on both ends. Saverio will work on QA. We need cable trays to be in place to measure lengths of type II/III harnesses with trial cables Company will then take 2-3 weeks to make harnesses We must supply tables of lengths, connectors (not yet delivered to CERN), labels (final scheme being worked out) Include a few spares for instant replacements (and maybe even try to install a few?????)

Pippa Wells25 October (dummy) PPB1 and PPF1 PPB1 mechanics and dPPB1 boards seem to be under control Test of dPPB1 prototype was made in the pit A few pieces (clamps) need to be remade PPF1 mechanics - needs some attention Agreed in Engineering meeting in NIKHEF to redesign the cable clamp to avoid deforming cables The clamp is supported from the cryostat and is sufficient to locate the type II cable in the correct position The mechanics to support the dPPF1 PCBs is NOT available (either not yet made or in use at Liverpool/NIKHEF) dPPF1 boards should be fabricated on time – need to find a way to support them

Pippa Wells25 October Fibres First fibres to be installed 15 December Boxes of data fibres should have been delivered yesterday to Bat Space there to sort out all boxes, get fibres in sequence for installation, do inventory… Tony strongly resists any testing to avoid spoiling the heavy duty rigging we paid for Need to verify that we understand connectivity/labels in enough detail. FSI fibre drums are still in Bat 226. Urgently need a person to take charge of planning Where to cut them to length? Are all the steps for pulling/stripping/splicing sufficiently understood Make labels

Pippa Wells25 October Mapping A lot of discussion recently about power supply mapping DCS and other experts are fully informed of the results of the mapping – some implications for interlock complexity. Barrel crates not mixed with end cap crates Some end cap crates mix EC-A and EC-C – but cooling circuits (quadrants) collected in the same crate

Pippa Wells25 October Cables between racks in US(A)15 We are collecting a list of services needed between racks in US and USA15 These must be put into the cable DB and given to Sergei Malyukov to book slots in cable trays and find out lengths Marco Olcese does not want to add them to the ID services inventory

Pippa Wells25 October Conclusions Dates for installation of first type II/III cables are known Urgent need to identify skilled people to do connections at PP1 without depleting SR1 team Logistics of type II/III power cables will be “interesting” Need to improve plans for dPPF1 for power cables Planning for fibres (especially FSI) needs to be improved Have to go through the list of other cables and verify that all is going to be “in time”