1 Welcome to all Outline: CDR status 2012-16 planning information 2012-16 information still needed Goals of meeting and practical information.

Slides:



Advertisements
Similar presentations
Neutrinos in CHIPP Allan Clark Neuchâtel Meeting June 2004.
Advertisements

APT progress and resource discussion HS; 9 th March 2012.
Discussion on EUROTeV and ILC Nick Walker (DESY) EUROTeV Kick-off Meeting DESY 1 November 2004.
The CLIC project Brief overview of the CLIC machine and collaboration organisation Status: Feasibility studies and Conceptual Design Report (CDR) Physics.
Organization mid Initial comments The organization covers the CLIC accelerator activities but also including: ILC-CLIC WGs Detectors for CLIC-ILC.
5 th CLIC X-band collaboration meetingWalter Wuensch16 May 2011 CLIC rf structure program.
Conclusions from CLIC (IWLC 2010, Geneva) Ken Peach (JAI) Comments.
Accelerator activities Brian Foster (Uni Hamburg/DESY) 1 B. Foster - Hamburg/DESY - Orsay 11/13.
Summary of AWG4: Beam Dynamics A. Latina (CERN), N. Solyak (FNAL) LCWS13 – Nov 11-15, 2013 – The University of Tokyo, Japan.
27/3/2009EuCARD NCLinac Kick-Off Meeting 1 Summary NCLinac Kick-Off CERN, 27-Mar-2009.
J.P.Delahaye ACE CLIC A dvisory C ommitte E (ACE) Introduction to the 5 th CLIC Advisory Committee meeting (02-04/02/10) CLIC progress.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
“Linear collider studies: This heading includes the total funding for CTF3, the CLIC study and the CLIC/ILC collaboration as well as the CERN’s participation.
24-Aug-11 ILCSC -Mumbai Global Design Effort 1 ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program.
CLIC cost estimate Hans-H. Braun, CLIC-GDE meeting, February 8, 2008  Cost model goals  Methodology  Cost distribution  Future improvements.
Mats Wallin Swedish Univ. of Agricultural Sciences Dept. of Environmental Assessment Catarina Johansson Swedish Environmental Protection Agency Development.
1 Tunnel implementations (laser straight) Central Injector complex.
D. SchulteICHEP Paris, July 24, CLIC Progress and Status D. Schulte for the CLIC study team.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
Introduction to the CLIC study 6 September 2010 Mechanics meeting W. Wuensch.
J.P.Delahaye Introduction to the X Band Workshop X Band Accelerating Structure Design and Test Program Workshop WELCOME CIEMAT/Spain, CEA SACLAY/France,
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Introduction to the X-band resource estimation exercise W. Wuensch Collaboration meeting 3 November 2011.
1 Linear Colliders (LC) Outline: Why linear ? Physics at a LC (brief) ILC and CLIC – technology developments, commonality and differences Detectors at.
CLIC TDR Task Force CLIC Zero, cost & schedule considerations R. Corsini.
Considerations for the CDR and Strategy Update The current CDR planning focuses on 3 TeV and a downscaled not optimised 500 GeV machine, aiming for completion.
CLIC Overview Andrea Latina (APC/FNAL) for the CLIC/CTF3 Collaboration June 10, Low Emittance Muon Collider Workshop, FNAL.
CERN : a gateway to fundamental research Research & Discovery Training Technology Collaborating.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
F. Richard LAL/Orsay 1 ELAN in 2006 Annual Meeting.
Status and Plans for EUROnu FP7 Design Study Status and Plans for EUROnu FP7 Design Study EUROnu = A High Intensity Neutrino Oscillation Facility in Europe.
1 Future Circular Collider Study Preparatory Collaboration Board Meeting September 2014 R-D Heuer Global Future Circular Collider (FCC) Study Goals and.
University of Oslo and CLIC Short overview for first “NorduCLIC” meeting Erik Adli and Steinar Stapnes, University of Oslo May 19, 2008.
1 Tunnel implementations (laser straight) Central MDI & Interaction Region -Introduction -Feasibility Studies -CDR status -Implementation issues -Plans.
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
Various information - news News from coll. board meeting 1.2 Budget 2013 ECFA LC workshop at DESY end May ICFA and LCC meetings at Triumf European Strategy.
Introdcution to Workpackage/Activity Reflection D. Schulte.
Costing review Extract from slide of Philippe: The Panel was impressed by the quality of the presentations and degree of detail to which the value.
CLIC - CDR Status (Volume 2) Hermann Schmickler, ILCW2010.
CLIC project 2012 The Conceptual Design Report for CLIC completed – presented in SPC, ECFA and numerous meetings and conferences, also providing basis.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Context of the CLIC studies ‒ Option for a post LHC energy frontier machine CDR finalization ‒ Including input to strategy processes Some recent news ‒
The CLIC project – status and plans Outline: The CLIC machine concept Feasibility studies and CDR status Technical progress The CDR volumes Implementation.
1 The next steps – focusing points Define the scope, strategy and cost of the project implementation. Main input: The evolution of the physics findings.
CLIC/CTF3 collaboration Board J.P.Delahaye 1 CERN, October 2007 CLIC Workshop 07 CLIC'07 provides a forum to review all aspects related.
CLIC 23 rd Project Meeting: news and updates Philip Burrows John Adams Institute Oxford University 1.
CLIC 2014 goals Complete re-baselining of a staged implementation taking into account the Higgs energy scale and improved power/cost models OK … work being.
CLIC Organogram CLIC Collab. Board L.Rivkin MoU with annexes describing coll. efforts (note: in reality more complicated) CLIC SC (Stapnes) Repr. from.
1 Comments concerning DESY and TESLA Albrecht Wagner Comments for the 5th meeting of the ITRP at Caltech 28 June 2004 DESY and the LC What could DESY contribute.
Introduction to the CLIC study 24 March 2010 Tsinghua University W. Wuensch.
BRAINSTORMING ON LASER BASED SOLUTIONS FOR CLIC PRE-ALIGNMENT INTRODUCTION Hélène MAINAUD DURAND, BE/ABP/SU, 09/02/2010 Status of the study CLIC pre-alignment.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
REMIT Document – main elements (approved in March Council week) As mentioned, the remit of the ESG is to establish a proposal for an Update of the medium.
CLIC Transfer System Introduction Daniel Schulte for the CLIC team March 11, 2010.
R. Corsini CLIC work-package planning meeting 2-3 November 2011 Introduction to the session.
CERN, 27-Mar EuCARD NCLinac Task /3/2009.
for the CLIC Study team and CLIC Collaboration
CompactLight H2020 Design Study Proposal
CLIC work program and milestones
CDR The CLIC CDR is now completed. The three volumes can be found as follows:      Volume 1:       Volume 2: 
Input to Strategy currently planned
Goal of the workshop To define an international roadmap towards colliders based on advanced accelerator concepts, including intermediate milestones, and.
CTF3 Collaboration Technical Meeting January 2008
Collaboration New collaborators in 2016:
CLIC: from 380 GeV up to 3 TeV Will also study klystron based machine for initial stage.
The CLIC project IEEE LC event, October 2012 Steinar Stapnes
Presentation transcript:

1 Welcome to all Outline: CDR status planning information information still needed Goals of meeting and practical information

2 Goal CDR and feasibility issues Drive beam scheme Detector (experimental conditions) Luminosity Operation and Machine Protection System (robustness) Main linac gradient – Accelerating structure – Drive beam generation – PETS – Two beam module – Drive beam deceleration – Main beam emittance generation and preservation, focusing – Alignment and stabilisation

3 CDRs: Vol 1: The CLIC accelerator and site facilities (H.Schmickler) CLIC concept with exploration over multi-TeV energy range up to 3 TeV Feasibility study of CLIC parameters optimized at 3 TeV (most demanding) Consider also 500 GeV, and intermediate energy ranges Vol 2: The CLIC physics and detectors (L.Linssen) Vol 3: CLIC study summary (S.Stapnes) Summary and available for the European Strategy process, including possible implementation stages for a CLIC machine as well as costing and cost-drives Proposing objectives and work plan of post CDR phase ( ) Timescales: By end 2011: aim to have Vol 1 and 2 completed Spring/mid 2012: Vol 3 ready for the European Strategy Open Meeting The CDR(s) Main information page: Accelerator About 90% of the contributions received Good progress Physics and Detectors Very good progress and status – complete draft available and have been reviewed A link providing the opportunity to subscribe as a signatory for the CLIC CDR can be found on the main information page Main information page: Accelerator About 90% of the contributions received Good progress Physics and Detectors Very good progress and status – complete draft available and have been reviewed A link providing the opportunity to subscribe as a signatory for the CLIC CDR can be found on the main information page

4 Accelerator CDR status – snapshot The linked documents (in blue) are all the drafts Still un-submitted parts Help needed on the editorial side

5 Physics and Detector CDR

6 nferenceDisplay.py?con fId=136364

7 The project meetings are open and on EVO, stay involved and informed:

– Goal: Develop a project implementation plan for a Linear Collider : Addressing the key physics goals as emerging from the LHC data With a well-defined scope (i.e. technical implementation and operation model, energy and luminosity), cost and schedule With a solid technical basis for the key elements of the machine and detector Including the necessary preparation for siting the machine at CERN Within a project governance structure as defined with international partners After 2016 – Project Implementation phase: Including an initial project to lay the grounds for full construction (CLIC 0 – a significant part of the drive beam facility: prototypes of hardware components at real frequency, final validation of drive beam quality/main beam emittance preservation, facility for reception tests – and part of the final project) Finalization of the CLIC technical design, taking into accoun the results of technical studies done in the previous phase, and final energy staging scenario based on the LHC Physics results, which should be fully available by the time Further industrialization and pre-series production of large series components with validation facilities The real focus of this meeting - CLIC Final CLIC CDR and feasibility established European Strategy for Particle CERN Council

9 The next steps – focusing points Define the scope, strategy and cost of the project implementation. Main input: The evolution of the physics findings at LHC and other relevant data Findings from the CDR and further studies, in particular concerning minimization of the technical risks, cost, power as well as the site implementation. A Governance Model as developed with partners. In order to achieve the overall goal for 2016 the follow four primary objectives for 2011—16 can defined: These are to be addressed by activities (studies, working groups, task forces) or work-packages (technical developments, prototyping and tests of single components or larger systems at various places) Define and keep an up-to-date optimized overall baseline design that can achieve the scope within a reasonable schedule, budget and risk. Beyond beam line design, the energy and luminosity of the machine, key studies will address stability and alignment, timing and phasing, stray fields and dynamic vacuum including collective effects. Other studies will address failure modes and operation issues. Indentify and carry out system tests and programs to address the key performance and operation goals and mitigate risks associated to the project implementation. The priorities are the measurements in: CTF3+, ATF and related to the CLIC Zero Injector addressing the issues of drivebeam stability, RF power generation and two beam acceleration, as we as the beam delivery system. (other system tests to be specified) (technical work-packages and studies addressing system performance parameters) Develop the technical design basis. i.e. move toward a technical design for crucial items of the machine and detectors, the MD interface, and the site. Priorities are the modulators/klystrons, module/structure development including testing facilities, and site studies. (technical work-packages providing input and interacting with all points above)

10 Work-packages and responsibilities

11 Example of WP

Initial resource planning versus availability in CERN MTP Total integrated: 140 MCHF (still being re-fined) In CERN MTP: 86 MCHF s Total integrated: 140 MCHF (still being re-fined) In CERN MTP: 86 MCHF s R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 Problem for personnel worse, as CERN planning is essentially flat

13 Available information - summary Overview of work-packages and responsibilities (shown) Description of work-packages (5 EXCEL tables, corresponding to the 5 activity areas, in the INDICO page with one sheet per work- package (example of a single WP shown) Includes estimates of resources needed Adding up give total resources needed for CERN MTP plan for available for comparison Conclusion: We need to find substantial resources outside CERN and will rely on the collaboration

14 CLIC multi-lateral collaboration - 41 institutes from 21 countries ACAS (Australia) Aarhus University (Denmark) Ankara University (Turkey) Argonne National Laboratory (USA) Athens University (Greece) BINP (Russia) CERN CIEMAT (Spain) Cockcroft Institute (UK) ETHZurich (Switzerland) FNAL (USA) Gazi Universities (Turkey) Helsinki Institute of Physics (Finland) IAP (Russia) IAP NASU (Ukraine) IHEP (China) INFN / LNF (Italy) Instituto de Fisica Corpuscular (Spain) IRFU / Saclay (France) Jefferson Lab (USA) John Adams Institute/Oxford (UK) John Adams Institute/RHUL (UK) JINR (Russia) Karlsruhe University (Germany) KEK (Japan) LAL / Orsay (France) LAPP / ESIA (France) NIKHEF/Amsterdam (Netherland) NCP (Pakistan) North-West. Univ. Illinois (USA) Patras University (Greece) Polytech. Univ. of Catalonia (Spain) PSI (Switzerland) RAL (UK) RRCAT / Indore (India) SLAC (USA) Thrace University (Greece) Tsinghua University (China) University of Oslo (Norway) Uppsala University (Sweden) UCSC SCIPP (USA) The CLIC International Collaboration

15 Information needed We have received ~40 such tables, indicating that there will be substantial help on the personnel side, while the material contributions will be more limited: 1.7 MCHF estimated in 2012 – going down with time, 48 FTE in institutes and 24 at CERN from inst. – also going down with time Plus: Still more input expected, and we observe that the collaborators are careful promising beyond their current funding horizon Minus: We also need to analyze carefully how the resources are matched to our needs

16 Collaboration The primary goal of this exercise is to identify the work-capability (WP-task-actual work) and resources (personnel and material) available in the collaboration for the various WPs The secondary goal is to understand the formal status (annexes to MoU or similar) of your link to CLIC and make sure we update and improve wherever needed for next period The third objective is to create direct links between people responsible for activities and work - packages and collaborators taking on responsibilities

17 onfId=156004

18 Inside CERN more is needed: EXCEL sheets for each task in each work-package: need about 200 tables like below sounds scaring, but this is only about 4 per work-package holder

19 Roadmap to APT implementation at CERN Start organizing a sequence of meetings between resource holders (mainly GLs)- CLIC work-package leaders – and (if needed) Hermann. Target: Get refined and ‘feasible’ work-packages definitions by the end of the year. Need a matrix of CLIC work-packages versus all concerned CERN groups. 3 rd /4 th November: Present/discuss and plan work-packages with collaborators. Significant participation is crucial for the success of the overall programme. January 2012: Prioritization by the CLIC study team February 2012: Implementation into APT at CERN in time for the MTP to Council

20 Summary Please sign up for the CDR: Activity and WP leaders: Update WP info – there are still things to fix Help collaborators to specify their contributions so it can be accounted for and define clear personal links Work on CERN group matrix Collaborators: Study WPs to understand possibilities and seek contact We need input from all collaborators, if at all possible by the end of the meeting, and latest by Create well-defined links to WPs and Activities Provide also input about formal collaborations documents needed (new, updates, adaptions.. )

21 onfId=156004

22

23

24