Installation and checkout of QBPM system Hardware to be installed –Install hardware in racks –Install CPU /SIS digitizers/VMIC 3122 analog digitizers/Digital.

Slides:



Advertisements
Similar presentations
Hardware Integration of the Prototype Wes Grammer NRAO September 24-26, 2012EOVSA Prototype Review1.
Advertisements

01/11/2002SNS Software Final Design Review1 V123S Event Link Encoder, Transmission System and PLL Receiver Thomas M. Kerner (BNL) SNS Global Controls.
NetSure™ RDB Series.
M.PEGORARO Grounding Workshop 24th Jan 08 DT GROUNDING & SHIELDING Presented by A. BENVENUTI.
MineralScan Lite Installation Guidelines Digital Control Lab, LLC NW 6 th Street, Suite F Gainesville, FL Main Unit power 90 – 240 VAC 50/60.
HPS MPS OVERVIEW Dan Sexton & the Safety Systems Group JLAB 1.
C and S band BPM system update A. Aryshev, S. T. Boogert, S. Molloy, C. Swinson 5/25/20151ATF2 Software meeting.
RPC Electronics Status Overall system TDC –Digitizing frequency issue (determine the bin size of the TDC value) Discriminator test result Trigger module.
CMS WeekDec 2002E. Hazen HF Electronics Status Report E. Hazen, J. Rohlf, E. Machado Boston University.
RPC Electronics Overall system diagram –At detector –Inside racks Current status –Discriminator board –TDC board –Remaining task.
RF Synchronisation Issues
Data Acquisition and Control Systems HYTEC ELECTRONICS LIMITED Motor Control and Power Drive Support Graham Cross.
LLRF Phase Reference System The LCLS linac is broken down into 4 separate linac sections. The LCLS injector will reside in an off axis tunnel at the end.
LCLS-II Linac LLRF Control System – L1, BC1 Zheqiao Geng Final Design Review May 7, 2012.
1PPS Timing and Reference Distribution Subsystem Wes Grammer NRAO March 15-17, 2012EOVSA Preliminary Design Review1.
TF Joint Voltage Drop Instrumentation Robert Marsala (609) Hans Schneider (609) Engineering Operations August 7, 2003 TF_JOINT_Final_Design_Review.ppt.
ATF2 Q-BPM System 19 Dec Fifth ATF2 Project Meeting J. May, D. McCormick, T. Smith (SLAC) S. Boogert (RH) B. Meller (Cornell) Y. Honda (KEK)
Low Voltage Power Requirement of TOF FEEs. Maximum tray. Low Noise:  Periodic and Random Distortion (PARD) < few mV RMS Floating.
EGSE CENTRIC PLAN FOR TWO TOWER TESTS IN ACCORDANCE WITH MEETING HELD 02 MAR 2005 REVISED 22 MAR 2005.
Status of QBPM Electronics and Magnet Movers as of June 3 rd 2008 D. McCormick, J Nelson, G White SLAC S Boogert Royal Holloway Y. Honda, Y.Inoue KEK.
Status of ATF2 Cavity BPM Project Sep 29, 2005 Project Scope: Instrument both couplers ATF2 cavity BPM’s (35) Produce prototype for December cavity test.
Design and Fabrication of a Q-BPM Calibration Tone Generator for the ATF2 Ian Bullock August 14, 2008.
Figure 1: ICD Single Channel Block Diagram Schematic PMT High Voltage Supply (see Figure 4 & 4a) LED Pulser PMT Calibration (see Figure 6) ICD Scintillator.
ATF Instrumentation Status and Planning 3 December 2007 Juan Cruz, Justin May, Doug McCormick, Janice Nelson, Tonee Smith, John Wray.
ATF2 Optics for the Commissioning Toshiyuki Okugi, KEK 2008 / 10/ 22 ATF2 commissioning meeting.
IP-BPM status Siwon Jang KNU. Contents The electronics repair status –Repair work status –Electronics RF test (by using Oscilloscope) –Electronics shipment.
1 ATF2 Q BPM electronics Specification (Y. Honda, ) Design System –Hardware layout –Software –Calibration Testing Production schedule ATF2 electronics.
© Nokia 1255_RF_Training / Jan 2006 / CFSCompany Confidential 1255 Technical Training RF Troubleshooting Presentation NMP-CDMA, San Diego Jan, 2006.
QBPM System Installation Systems –Rack mount chassis –LO and CAL RF cable plant ( need 714Mhz from eels bedroom) –Down mix boxes –DC power cable plant.
The ATF Damping Ring BPM Upgrade Nathan Eddy, Eliana Gianfelice-Wendt Fermilab for the ATF Damping Ring BPM Team.
FONT Hardware Processing electronics and current beam tests Stephen Molloy Queen Mary, University of London.
Beam Line BPM Filter Module Nathan Eddy May 31, 2005.
1 ATF Instrumentation Status and Planning Justin May, Juan Cruz, Doug McCormick, Janice Nelson, Tonee Smith, John Wray 1.
Director’s Review of RunIIb Dzero Upgrade Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage u High.
18 December 2007 ATF Damping Ring BPM System Upgrade Joe Frisch, Justin May, Doug McCormick, Janice Nelson, Tonee Smith, Mark Woodley (SLAC) Charlie Briegel,
Commissioning Hardware and IP Configuration of ATF / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)
Tests of STO IF Components S. Weinreb April 15, 2009 Two 1-2 GHz IF amplifier plates and one 5 GHz converter plate for the Texas test flight have been.
LIGO-G9900XX-00-M LIGO II1 Why are we here and what are we trying to accomplish? The existing system of cross connects based on terminal blocks and discrete.
ATF DR BPM Upgrade Janice Nelson, Doug McCormick, Justin May, Andrei Seryi, Tonee Smith, Mark Woodley.
NLC - The Next Linear Collider Project Nano beams in the ATF extraction line Marc Ross Linear collider challenges: Energy Emittance source Stability ATF.
N. BlaskovicFONT Meeting1 ATF November 2013 shift plan N. Blaskovic.
Prototype Sensor Status and Measurements u Sensor Response Measurements u Mechanical Response u Noise Expectations u DAQ Status.
05/12/2014 Gerrit Jan Focker, BE/BI/PM 1 PSB-Injection H - and H 0 Dump detectors and Stripping Foil current measurement.
1 ATF2 Q-BPM Magnet Movers & 1 st Pulse Calibration Progress from May 7-11 J. May, D. McCormick, T.Smith (SLAC) S. Boogert (RH)
S. Smith LCLS Facility Advisory October 12, Beam Position Monitors Facility Advisory Committee October 12, 2006.
LEReC BPM Status P. Cernigla, R. Hulsart, R. Michnoff, Z. Sorrell June 2, 2016.
S-band processing electronics R. Ainsworth (summer student), S. Boogert, G. Boorman (Royal Holloway) A. Lyapine (University College London) Weekly ATF2.
Current Status of QBPM Electronics and Magnet Movers D. McCormick, J Nelson, G White SLAC S Boogert Royal Holloway Y. Honda, Y.Inoue KEK.
HF ROBOX PRR3 Apr 2003E. Hazen HF Front-End Electronics ● System Description – Overview – PMT Board, ROBOX, Patch Panel – Signal Cable, Front-end boards.
1 FONT IP FB Philip Burrows Robert Apsimon, Doug Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Colin Perry John Adams Institute Oxford University.
Cosmic Microwave Technology, Inc.
Solid State Amplifier Development at PSI
ATF/TTF Instrumentation Nov. 27, 2006 Last report: Oct. 2
Injectors BLM system: PS Ring installation at EYETS
Christian Veelken last updated 11/09/06
The ELENA BPM System. Status and Plans.
WP02 PRR: Master Oscillator and RF Reference Distribution
RF cables calibration Matteo Volpi Thomas Geoffry Lucas
LCLS Cavity BPM Electronics Undulator Week January 22, 2008
NI Data Acquisition (DAQ) Wiring and Connections
BESIII EMC electronics
CH-6 CABLE TV.
LO BOX and LO/CLK DISTRIBUTION Arash Kaftoosian ESS Bilbao, May 2018.
AM-7026 Down Converter-Receiver
Status of TTF HOM Project Aug 9, 2005
Report on ATF2 Third Project Meeting ATF2 Magnet Movers ATF2 Q-BPM Electronics Is SLAC ILC Instrumentation Group a good name?
CECOM LAR Operation Course
RPC Electronics Overall system diagram Current status At detector
Building a 2 KW SSPA for 23cm
Presentation transcript:

Installation and checkout of QBPM system Hardware to be installed –Install hardware in racks –Install CPU /SIS digitizers/VMIC 3122 analog digitizers/Digital I/O module –DC power cables –IF cables –Downmix boxes/standoffs –Analog read back cables –LO/CAL cables Hardware checkout to be done –Confirm 8V DC at all downmix boxes –Set LO power at all downmix boxes to be 3dbm –Adjust all LO phases to be equal for single pulse calibration system. –Adjust CAL power to -10dbm for all downmix boxes. Software checkout to be done. –Load CPU operating system/ digitizer software etc….. –Test single pulse calibration software –Test DDC library codes for QBPM data acquisition. –EPICS interface with DDC library code –Digitize CAL tone signal and record system gains for each channel –Digitize analog read back signals……

Install Chassis in Racks Load rack with chassis as shown (ATF) DC power distribution DC power supply BPM signal patch panel Nanobpm or Ring BPM VME crate Analog signal interface Cable Feed through RF amplifier pwr supply Cal Tone Generator Cable Feed through SLAC supplied SLAC supplied still to ship SLAC supplied Cable Feed through 6446 MHz LO Locking box Existing unit 5 Units 2 Units 4 Units 2 Units 3 Units 9 Units 2 Units 4 Units 1 Unit Still to be designed Need 15V at 5 amps Could use existing Nanobpm or Ring BPM VME crate Maybe use Ring BPM M550 CPU

DC power SLAC to ship 16 gauge single pair cable connectors and pins to ATF Cable installation. (ATF) –Make all lengths the same. –Connect drain wire to return DIN rail in rack –Connect drain wire to spade lug on tunnel end for possible connection to downmix box. Build 15V 5amp LO amp power supply chassis (ATF/SLAC)

Put a connector on the drain wire as shown for grounding the connector shell if needed DC Power Distribution Attach drain wire with DC return wire to return blocks

IF Cables SLAC to ship 40 pairs of IF cables, patch panel and jumpers for ATF personnel to install. –Cables are pre-terminated with SMA connectors on tunnel end and BNC cables on the other. –ATF personnel to install one pair per downmix box and connect to patch panel. –Do not cut cables to length. Store extra cable in the trays.

… Beam direction xyxy xyx y QD10X Y QD10X X QF11X Y QF11X X QD12X Y QD12X X QD16X Y QD16X X etc

SIS QBPM channel assignments SIS1SIS1 QD10X Y QD10X X QF11X Y QF11X X QD12X Y QD12X X QD16X Y QD16X X SIS2SIS2 QF17X Y QF17X X QD18X Y QD18X X QF19X Y QF19X X QD20X Y QD20X X SIS3SIS3 QM16FF Y QM16FF X QM15FF Y QM15FF X QM14FF Y QM14FF X QM13FF Y QM13FF X SIS4SIS4 QM12FF Y QM12FF X QM11FF Y QM11FF X QD10AFF Y QD10BFF X QF9AFF Y QF9BFF X SIS5SIS5 SF6FF Y SF6FF X QF9AFF Y QF9AFF X FDBKbpmFF Y FDBKbpmFF X QD21X Y QD21X X

SIS6SIS6 QD6FF Y QD6FF X QF5BFF Y QF5BFF X SF5FF Y SF5FF X QF5AFF Y QF5AFF X SIS7SIS7 QD4BFF Y QD4BFF X SD4FF Y SD4FF X QD4AFF Y QD4AFF X QF3FF Y QF3FF X SIS8SIS8 QD2BFF Y QD2BFF X QD2AFF Y QD2AFF X SF1FF Y SF1FF X QF1FF Y QF1FF X SIS9SIS9 RC1FF RC1X RC3FF RC2FF SISSIS SIS QBPM channel assignments SD0FF Y SD0FF X QD0FF Y QD0FF X QD8FF Y QD8FF X QF7FF Y QF7FF X

Downmix boxes/standoffs ATF personnel to install one downmix box per quad and reference cavity. –Standoffs to be sent by SLAC to ATF ATF personnel to install 2 jumpers (SLAC provided) from downmix box to hybrid outputs Hybrid Downmix box standoffs Jumpers

Analog read back cables ATF personnel to purchase and install 3 pair 20 or 22 gauge wire with individual shields and drain wire around each pair. ATF personnel to: –Wire to run from each downmix box to analog input chassis already at ATF –Lug drain wire in the tunnel for attaching to metal shell of DB9 connector –Connect drain wire to ground connection of terminal block Connect ribbon cables from interface panel to the VMIC 3122 modules.

Metal shell DB9 male connector Drain wire Attach to shell and terminal block as shown

LO/CAL Cables ATF to purchase: –RF BPM LO and CAL cable plant 500 ft of Andrews LDF4-50 or equivalent LO from source to splitters. With a loss/meter at 6400MHz of 6.5 db/30m. $2.50/FT $ L4NM-C type N male connectors for both ends. $27.00 each-- $ ft of Andrews LDF2-50 or equivalent for LO from splitters to electronics. With a loss/meter at 6400MHz of 10.2 db/30m. $2.00/ft $ L2PNM-HC type N male connectors. $27.00 each $ – Two 2 way 3db splitters with type N female connectors that will work at 33dbm power levels. Pulsar Microwave PS /3N or equivalent –Two 6 way splitters with Type N female connectors. Pulsar Microwave PS /1N or equivalent –Conformal cable and connectors for LO and CAL jumpers. The length of these cables have to be adjusted for the single pulse calibration setup. 30 meters of conformal cable or equivalent. $6.90/m -----$ female N connectors $2.67 each $ male SMA connectors. $1.90 each $152.00

LO/CAL Cables (cont) Cable purchase details LDF4-50A Andrews Heliax website 44 L4NM-C male type N connectors for LDF4-50 cable. ATF to purchase 1000ft of LDF2-50 Andrews Heliax or equivalent. ATF to purchase 160 L2PNM-HC male type N connectors for LDF2-50 cable

LO/CAL Cable Installation Install cable as shown in the following sketches. –Install Male type N connectors on ½” and 3/8” heliax. (ATF) –Keep cable paths as short as possible. Mount couplers and splitters securely, and out of foot traffic. Attach 3/8” cable to the downmix box standoffs as shown. (ATF) –SLAC to provide LO tunnel amp and splitter LO cable mounted to standoffs. CAL cable mounted on opposite side

LO power budget/ cable plant 33 dbm max amp output 29.5dbm after splitter 7m of LDF4-50 cable = 1.4 db plus 0.25 db per connector=1.9db loss 27.6dbm 26.88dbm 13.5m of LDF4-50 cable = 2.71 db plus 0.25 db per connector=3.25db loss 23.63dbm 20.13dbm after splitter 20m of LDF4-50 cable = 4 db plus 0.25 db per connector=4.5db loss dbm 1db loss in these cables 17.6dbm 26.88dbm 16.6dbm 27.6dbm 16.6dbm 10m of LDF4-50 cable = 2db plus 0.25 db per connector=2.5db loss 24.3dbm All 8 way splitters have 10db loss All cables from 8 way to down mix boxes should have no more than 2db loss These cables should be made from LDF db/meter

Some where in this location is an ideal location for QBPM electronics 42 db gain 33dbm amp with 2way splitter 8 way splitters 10db directional couplers 2 way 3 db splitter LDF4-50 cable or equivalent LDF2-50 cable

8 way splitter LDF4-50 cable or equivalent 6 way splitter LDF2-50 cable

8 way splitters LDF4-50 cable or equivalent LDF2-50 cable Some where in this location is an ideal location for QBPM electronics

Hardware Checkout DC power –Confirm voltage at the downmix box is between 8 and 9V. (SLAC) LO Power –Set Locking Box output power so that there is -10dbm at the input to high power amp in the tunnel. (SLAC) –Set power level at the downmix box end of the 3/8” cable, to between 3 to 4dbm. (SLAC)

Hardware Checkout (cont) –Adjust all LO phases to be the same for single pulse operation. (SLAC with ATF help) CAL Power –Use RF source to produce CAL tone and inject it into CAL cable system. Adjust CAL tone power level at downmix boxes to be about -10dbm. (SLAC) –Design CAL tone generator locked to 714MHz (SLAC)

Software Work Software work to be done. –Load CPU operating system VXWorks/Artems digitizer software etc….. –Before beam stop in May of 08, use Test Bed QBPM with nanobpm VME crate, CPU and digitizers to: Test Matlab code for single pulse calibration data acquisition. Test DDC library codes for QBPM data acquisition. Create EPICS panels to interface with data taking software Write analog digitization software for monitoring LO levels, downmix box temperatures, etc. Write CAL tone digitization software to track system gains for each channel Work to be done by SLAC and RH personnel. Software is THE critical path item for successful QBPM operation in October.