1 Program Management Systems Committee (PMSC) Contract / Subcontract Issues Working Group 29 January 2009.

Slides:



Advertisements
Similar presentations
NDIA PMCS May 2005 Falls Church, VA Earned Value Management System Acceptance Working Group Buddy Everage Working Group Lead.
Advertisements

Contract and Project Management: A Field Perspective Moderator Michael Peek, PE CCE CFM Office of Engineering and Construction Management.
Preparing for Compliance Monitoring Reviews Understanding CMS Protocols Used by Review Organizations January 14, 2009 Presented by: Margaret deHesse, RN,
Campus Improvement Plans
1 ANSI/EIA A STANDARD Earned Value Management Systems Proposed Changes Discussion January 31, 2007 NDIA Program Management Systems Committee.
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
Contractor Code of Business Ethics and Conduct Laura K. Kennedy Senior Vice President, Ethics and Compliance SAIC.
April 25–27, 2005 Phoenix Civic Plaza/Hyatt Regency Phoenix Phoenix, AZ NCMA World Congress 2005 “Prime Time: Contract Management at the Core of the Enterprise”
1 NDIA Earned Value Management Application Guide Status Report May 3, 2005.
CENTRAL CONTRACTOR REGISTRATION (CAGE CODES) DFARS Case 2003-D040 DFARS Parts 204, 212, 213 and 252 are amended to remove policy on Central Contractor.
ANSI/EIA A EIA STANDARD Earned Value Management Systems Overview May 2, 2006 NDIA Program Management Systems Committee Walt Berkey, Lockheed.
1 EVM Policy July 2013 NAVY CEVM 2 Outline DoDI DFARS DFARS DFARS June 2012 AT&L Policy Letter.
1 Program Management Systems Committee (PMSC) Contract / Subcontract Issues Working Group 04 February 2010.
2010 National Defense Industrial Association - Program Management Systems Committee (NDIA PMSC). All rights reserved.. 1 Program Management.
Page 1 National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC). NDIA Earned Value Management Systems Intent Guide Overview.
2009 National Defense Industrial Association - Program Management Systems Committee (NDIA PMSC). All rights reserved.. Dave Roberts NDIA PMSC.
0 The Rule-Making Process How It Works and How You Can Get Involved First Annual FAR/DFARS Conference October 24, 2006.
National Aeronautics and Space Administration Jet Propulsion Laboratory California Institute of Technology Buck Crenshaw, Program Element Manager, NASA-Wide.
A SOUND INVESTMENT IN SUCCESSFUL VR OUTCOMES FINANCIAL MANAGEMENT FINANCIAL MANAGEMENT.
PCARSS: Transfers of Accountability
CONTRACTUAL FLOW DOWN OF DPAS PRIORITY RATINGS
Copyright © 2009 NDIA PMSC Robert Loop August 2009 NDIA PMSC Guides Working Group Status.
Publication of Agency Procurement Regulations Karen L. Manos Acquisition Reform & Experimental Processes Committee November 30, 2004.
Office of Management and Budget Program Management Systems Committee February 8, 2005 EVMS Actions in Process David Muzio.
1 Program Management Systems Committee (PMSC) Contractual Requirements/Issues Sub-Team Update 7 August 2007.
Earned Value Management Systems (EVMS) Defense Support Team (DST) and Report to Congress Mr. Richard Ginman OUSD(A&T)/DPAP Presentation to National Defense.
Contractor Business Systems (CBS) Rule Eric Fassett.
1 Earned Value Management (EVM) Center ‘Moving Forward’ Presented by Mr. David Kester Director, Program Integration Division April 25, 2007.
2009 National Defense Industrial Association - Program Management Systems Committee (NDIA PMSC). All rights reserved.. Gay Infanti Dave Roberts.
CERTIFICATION In the Electronics Recycling Industry © 2007 IAER Web Site - -
NDIA Small Business Division Subcommittee on Improving IP Protection for Small Businesses Mission Statement Overview Alison Brown.
Revised Department of Defense Earned Value Management Policy Deborah A. Tomsic Senior Program Analyst Office of the Under Secretary of Defense (Acquisition,
Internal Information Services Risk Management Team Gay Infanti Northrop Grumman 3 May 2006.
OSD Earned Value Management Activities Update Larry L. Axtell Senior Program Analyst Office of the Under Secretary of Defense (Acquisition, Technology.
© MCR, LLC MCR Proprietary - Distribution Limited Earned Value Management Application, Guidance, and Education Neil F. Albert President/CEO MCR, LLC
1 The Voice of the Industrial Base 1 IBR Guide NDIA PMSC Working Group NDIA PMSC Meeting January 31, 2007 Updated Feb 4, 2007 Prepared by; Joe Houser KM.
Generic GFE Implementation Toolset for Prime Contractors -IUID Guidance- –Initial population of Government Furnished Equipment Data into the IUID Registry.
Page 1 National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC). NDIA Surveillance Guide Overview May
Earned Value Management Update Nancy L. Spruill Director, Acquisition Resources and Analysis Office of the Under Secretary of Defense (Acquisition, Technology.
Presented to: NDIA By: Keith Kratzert Date: August 16, 2006 Federal Aviation Administration Improving Program Performance at FAA.
0 Office of Performance Assessments and Root Cause Analyses (PARCA) PARCA EVM Update Presenter: Phone:
Office of Management and Budget NDIA Program Management Systems Committee May 3, 2005 EVMS Compliance Requirements David Muzio.
Strength through Industry & Technology Program Management Systems Committee Procurement Division Educational Seminar 31 March 2008 Sarasota, Florida Current.
Earned Value Management Presented By: Steve Krivokopich May , 2006.
1 NDIA Earned Value Management Application Guide Status Report August 16-17, 2005 Wayne Abba Walt Berkey David Muzio David Treacy NDIA EVM Application.
Earned Value Management Update Nancy L. Spruill Director, Acquisition Resources and Analysis Office of the Under Secretary of Defense (Acquisition, Technology.
1 Felisha Hitt, Senior Procurement Analyst March 18, 2008 Defense Acquisition Regulations System
Internal Information Services Risk Management Working Group Gay Infanti Northrop Grumman 15 August 2006.
1 Program Management Systems Committee (PMSC) Contract / Subcontract Issues Working Group Industry Issues and Position Summary 13 August 2008.
Brookhaven Science Associates U.S. Department of Energy Facility Managers Meeting DOE-OECM Certification of Earned Value Management Systems April 27-28,
1 Program Management Systems Committee (PMSC) Contract / Subcontract Issues Working Group 27 August 2009.
Internal Information Services Risk Management Team Gay Infanti/John Driessnack Northrop Grumman 3 May 2005.
Alpha Contracting Sole Source Negotiations between Government and Industry (13 CFR (c)(2))
Project Management Project Integration Management Minder Chen, Ph.D. CSU Channel Islands
NDIA PMCS May Rosslyn, VA Earned Value Management System Acceptance Working Group Buddy Everage Working Group Lead.
Defense Cost and Resource Center Contractor Cost and Software Data Reporting: An Update Ron Lile May 2006.
Strength through Industry & Technology How is the Government Managing for Value? Program Management Systems Committee March 11, 2007 The Voice of the Industrial.
Small Business Programs Tatia Evelyn-Bellamy Director Small Business Division Small Business Center February 2016.
1 The Voice of the Industrial Base 1 IBR Guide NDIA PMSC Working Group NDIA PMSC Meeting August 7, 2007 Prepared by; NDIA IBR Working Group August 2007.
1 The Voice of the Industrial Base 1 IBR Guide NDIA PMSC Working Group NDIA PMSC Meeting April 24, 2007 Prepared by; NDIA IBR Working Group April 15, 2007.
Small Business and Subcontracting. Subcontracting for Small Business 6 steps to successful subcontracting 6. Report Contractor performance 1. Consider.
1 Changes to Regulations Governing Personal Conflicts of Interest and Organizational Conflicts of Interest Breakout Session # C08 Name: Barbara S. Kinosky,
Commercial Item Acquisitions: A Brief Update
EVM 202—Lesson 5 EVMS Surveillance
EVM 202—Lesson 3 EVMS Guidelines and Compliance
NDIA Earned Value Management Application Guide
EVM Policy NAVY CEVM July 2013
NDIA Intent Guide Update for EVMIG.
CMO DPAS RESPONSIBILITIES
Program Management Systems Committee (PMSC)
Presentation transcript:

1 Program Management Systems Committee (PMSC) Contract / Subcontract Issues Working Group 29 January 2009

2 Team  Members Mike Martin - P&W Rocketdyne (Lead) Gay Infanti - Northrop Grumman Eleanor Haupt - Consultant to the Institute for Defense Analyses Dave Muzio - MCR Peter Schwarz - MDA Jeff Poulson - Raytheon Mike Pelkey – OSD Randy Steeno – Boeing Debbie Tomsic – OSD Larry Axtell – OSD Fred Meyer – DCMA EV Center John Pakiz – Boeing (Retired) Dan Feeney – Lockheed Martin Kathryn Flannigan – General Dynamics

3 Issues List  The following issues have been addressed by the Contracts Working Group and consensus has been reached, on all but the last, among industry and government participants concerning next steps: –Contract vs. EVM system order of precedence. –Subcontractor compliance, validation and surveillance –Knowledge gap between EVM and contracting communities –Integrated and virtual team (badgeless) subcontracting teaming arrangements –DCMA EV Standard Surveillance Operating Manual (SSOM) –Under what circumstances can a supplier apply an existing validation from one site to another? New –DCMA EV Center is preparing a position paper on each of these issues. After a review by other DOD segments, the position paper, which will represent a consolidated DOD position, will be published.  The actions contained herein will be executed through a collaborative industry / government effort  OSD has requested that these issues be worked and closed out.

4  In addition to including FAR or DFARS EVMS clauses on contracts, contracting officers frequently include other provisions that often require suppliers to modify or depart from their standard, validated EVM Systems to manage their contracts and meet the requirements of their contracts. These provisions may be found in sections of the contract that take precedence over Section I, where the EVMS clauses are contained, e.g., –Section H – Special Provisions –Section C – Statement of Work requirements  DCMA’s stated policy is to issue Corrective Action Request (s) against the contractor for following contract direction. Issue Order of Precedence Team Position  Contractors are obligated to follow the contracts.  In the sprit of cooperation the Contractor and the cognizant CMO should notify the PCO of the conflicting requirements  The DCMA CMO and the PCO should reach a solution with the government PM which precludes noncompliance with either the ANSI or the contractor’s validated EVMS  Previous DCMA Director has instructed the EV Center not to initiate CARs when an inconsistency exists  DCMA must issue a communication regarding this position to all CMOs and EV Center personnel. Action: DCMA EV Center Director will readdress this issue with new DCMA Director..

5 Issue  Previously a subcontractor had the ability to request one of three options when required to have a validated EVMS; the EVMIG and other guidance documents vested primary responsibility in the prime contractor. 1)Prime Contractor Review Only 2)DCMA Review Only (at sub’s request) 3)DCMA and Prime Contractor Review  October 2006, DCMA revised the EVMIG to assign DCMA sole responsibility for subcontractor validation.  The EVMIG may conflict with NDIA EVMS System Acceptance Guide since it appears to categorically eliminate the consideration of other agencies’ acceptance.  Inconsistencies will result in dual industry processes for subcontractor validation and the potential for the same at a single contractor facility. Subcontractor Compliance, Validation and Surveillance Team Position  Validation / Compliance Reviews: DCMA has taken over responsibility for subcontractor validation and surveillance, however prime contractors will be encouraged to participate in subcontractor validation and/or compliance reviews since they retain responsibility for –Subcontractor performance –Accuracy and fidelity of CPRs, including reported subcontractor data  Suppliers with DoD contracts must review their system descriptions to ensure they comply with recent change.  Who is responsible for notifying the government of the need for a subcontractor validation review?  Surveillance: – Program- Prime’s DCMA prime will issue a LOD to the Subcontractor’s DCMA for program surveillance – System – DCMA will conduct joint surveillance of sub’s EVMS; Prime will participate  General : EVMIG update is necessary for clarification

6  Evidence that EVM and Contracting experts are not collaborating, via IPTs, on the contractual application and use of EVMS during acquisition planning.  Evidence of this is as follows: – Incorrect flow down and/or omission of EVM contractual requirements. – Improper contract direction forcing the contractor or subcontractor to violate their approved system. – Over application of EVM requirements – Improper application of requirements for follow on options – Improper use of Management Reserve (MR) – Integrated Baseline Review (IBR) timing  Knowledge gap is perceived cause IssueTeam Position EVM Knowledge Gap  NDIA PMSC should establish an Industry / Government team to generate a training package which can be delivered to all federal agencies and contractor organizations. Action: D. Tomsic developed/delivered this training on 7/29/08 through NCMA audio seminar. Industry will review material to ensure it is acceptable to a broader audience.  Issue correspondence “EVM Contract Requirements Checklist” under OUSD signature to all commands. Action: DPAP correspondence “EVM Requirements and Reporting” issued 8/27/08 Memo addresses this item and references checklist with link to web site to obtain current version.  DOD is considering the establishment of a common Procurement Initiation Document (PID) process to review contract requirements prior to solicitation. Action: TBD

7  The use of a single EVMS by all program participants to manage large programs involving major subcontractors is viewed as non-compliant to the DFARS EVMS clause by DCMA. – This approach also referred to as badgeless, virtual, or gray badge. – Characterized by adoption of a single validated system to manage the effort (typically the prime’s EVMS), use of a common tool set, integrated schedules and performance reporting. Issue Integrated Subcontract EVMS Implementations Team Position  Team will review matrix and establish general guidance for various types of integrated solutions.  Establish Matrix of Variable Implementations – Complete.  Update Matrix to Establish Validation, Compliance and System Surveillance Responsibilities - Open.  Completed guidance will be communicated through NDIA PMSC and agreed to via letter correspondence - Open.  Published in the EVMIG - Open. Transfer Issue to Joint DoD / Industry Working Group

8 Issue Standard Surveillance Operating Manual  DCMA EV Standard Surveillance Plan (SSP) will be implemented throughout the agency without being distributed for comment.  Issues include but are not limited to: –Existing AA provisions allowing system description change after ACO notification. –Review and adjudication of all CARs by the EV Center. –Risk Based Surveillance approach appears to eliminate contractor input. –Level of detail and amount of data requests to support surveillance have increased. –Training and Implementation - Demonstrated DCMA response time for final reports and system description changes must be improved. –Relationship of NDIA Intent Guide to the surveillance. Team Position  NDIA PMSC will work with DCMA to achieve a timely review and closure on any areas of concern.  DCMA has agreed to break out separate small group of Industry and Government participants to review the process and make recommendations.  Industry Representatives –Boeing : Randy Steeno –Lockheed Martin: Pete Wynne –Northrop Grumman: Gay Infanti –Raytheon: Jeff Poulson –Pratt & Whitney: Mike Martin –DCMA EV Center: Donna Holden, Kelli Coon  Schedule –Industry Comments to DCMA: 01/09 –Team Meeting: 1/30 –Additional Team Meeting: Feb –Adjudication of Issues: 2/16 – 3/27 –Final Industry Input : 3/31 Issue to be Closed 3/31

9 Issue Application of Existing Validation to Another Company Site  Under what circumstance is it can the validation (and system) from one company site apply to another ? Team Position  Not Discussed NEW

10 Summary  The following issues are still working toward closure: –Contract vs. EVM system order of precedence. –Subcontractor compliance, validation and surveillance.  The following issue is still open: –Knowledge gap between EVM and contracting communities.  Training Delivered and Correspondence Issued  Open Item - PID Process  The team requests that the following issue be transferred to the Joint OSD/Industry Working Group: –Integrated and virtual team subcontracting teaming arrangements  The following issue is new: –Application of existing process and validation from one company site to another.  The following issue is being worked separately and is targeted for closure by 3/31/08: –DCMA EV Standard Surveillance Operating Manual (SSOM).