Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.

Slides:



Advertisements
Similar presentations
OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Closeout.
Advertisements

US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Office of Project Management Metrics Report Presentation
Server Virtualization: Navy Network Operations Centers
Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011.
U.S. Department of Energy Project Management: Communicating Progress – Celebrating Success Paul Bosco, PE, PMP, CFM, LEED-AP Director, Office of Procurement.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Kaname Ikeda, October Status of the ITER Project Status of the ITER Project Kaname Ikeda ITER Nominee Director-General October 2006.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Facility & Diagnostic Overview for and Beyond Masa Ono For the NSTX Team NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Hutch Neilson Princeton Plasma Physics Laboratory Stellarator Team Meeting 3 March 2011 Stellarator Program Update.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
NCSX PROJECT OVERVIEW AND MANAGEMENT James L Anderson NCSX Project Manager August 15, 2007.
OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Closeout.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
SC Project Review of NCSX, April 8-10, 2008 Ron Strykowsky - page 1 Office of Science NCSX Project Review of NCSX April 8-10, 2008 Cost and Schedule Ron.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Perspective from Princeton August 15, 2007 Stew Smith Dean for Research.
Anthony Indelicato DOE-Princeton Site Office May 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the NSTX.
PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University Plasma Physics Laboratory EVMS Certification Review.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Project Management Methodology
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Project Overview Ron Strykowsky Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 October 2-3rd, 2013 NSTX-U Supported.
National Spherical Torus Experiment Upgrade (NSTX-U) Princeton Plasma Physics Laboratory (PPPL) Joseph V. Minervini October 29, 2009 Review Committee On.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
EARNED VALUE MANAGEMENT (EVM) TUTORIALS
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Anthony Indelicato DOE-Princeton Site Office October 2013 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
Where Module 04 : Knowing Where the Project Is 1.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
Project Overview Ron Strykowsky Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 December 11-12th, 2012 NSTX-U.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
1 CD-2 ECP Preparations What is Needed. 2 Background As part of the CD-2 process, we need to establish a fully supported and documented cost and schedule.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
Anthony Indelicato DOE-Princeton Site Office December 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
TOPIC-8B- PROJECT COST CONTROL
Project Management (x470)
Project Management W. J. Foyt
ENGR 281 Engineering Scholars Program Project Management Life Cycle Overview K. F. Reinschmidt J. L. Frank / Marathon Ashland Petroleum LLC Chair in.
LSST Project EVMS Performance Overview Kevin E
External Independent Review (EIR)
Managing Project Work, Scope, Schedules, and Cost
Preliminary Project Execution Plan
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011

2 Topics Project Overview (Mission, Scope, Plans, Organization, Budget) Performance Reporting & Management Processes

3 NSTX Upgrade Project Mission Technical Mission; 1)Double magnetic field and plasma current o Toroidal magnetic field of up to 1 Tesla (presently 0.55 Tesla) o Plasma current up to 2 Mega-amp (presently 1 Mega-amp) o Upgrade centerstack 2) Double neutral beam power & more tangential injection o Beams tangent to radii 130cm, 120cm and 109.4cm o Configure NB1 and NB2 so they can operate together or separately o Increase NB heating from 5-7MW to 10-14MW o Install a second neutral beam line Major ($94M and 5 year) upgrade to an existing Operating Fusion Reactor. Classified as an MIE (Major Item of Equipment) Project. Most Project funding being carved out of a $50M/year operating program. Technical scope not new technology or first-of-a-kind.

4 National Spherical Torus Experiment – NSTX Neutral Beam #1 operating since Sept 2000 NSTX Device operating since February 1999 Center- stack Assy Vacuum Vessel Umbrella Structure CS Pedestal Plasma TF Coil PF Coil

5 Centerstack Upgrade Scope TF Bundle contains 36 identical conductors with one-layer joint design vs. two conductors types and two layers in the present design. Bolted joints located at further radius hence lower joint current density and lower magnetic field at joint

6 Second Neutral Beam Scope Present NBI Pump Duct NSTX 2 nd NBI NSTX test cell TFTR test cell An existing TFTR Neutral Beamline will be Moved to the NSTX Test Cell

7 NSTX CD-2 Baseline Base cost = $77.3M (27% complete $20.3M spent $57M to go.) Contingency (on etc)= 27% ($17 contingency) TPC =$94.3M Outage = April 2012 – September 2014 (30 months) Schedule Contingency = 12 months CD-2 Approval December 2010 (Approval of baseline) CD-3 Approval January 2012 (Start of construction) CD-4 September 2015 (Project completion)

8 NSTX - Progress to Date  CD-0 Approved - February 2009  Conceptual Design & CD-1 Readiness Review - October 2009  EVMS Implemented - January 2010  CD-1 Approved - April 2010  Preliminary Design Review & CD-2 Readiness Review - June 2010  CD-2 Lehman Review – August 2010  DOE approval of Critical procurements & limited fabr. – August Inner TF conductor -TF Conductor machining, lead extension,& friction stir welding -Other Critical Procurements -Refurbishment of 2 nd neutral beam  CD-2 Approved - December 2010  PARS-II reporting initiated - January 2011  Initiated EVMS Certification preparations – February 2011  Final Design and CD-3 readiness review – June 2011  TF Fault review and validation of upgrade TF design – September 2011  DOE Authorize start of outage machine removals – September 2011  EVMS Certification Review- October 4-6  SC-OPA (Lehman review) - October 26 & 27  Request CD-3 Approval - November  CD-3 Approval - January Since CD-0 the design and project management have been vetted by 23 individual reviews composed of 57 external people from 19 institutions.

We plan to complete the Project at least six months earlier than our CD-2 baseline plan 9 Recent Machine Operational failure has placed the project on a fast track ! Our CA plans have not changed but we’re working ahead of schedule.

10 NSTX Upgrade Project Team Excellent, experienced and talented team assembled. Most important part of the management process.

11 NSTX Upgrade Project Responsibility Assignment Matrix ( excerpt shown ) CAM’s chosen for their technical expertise and specialty. (many CAM’s but this works for us) CAM’s have ownership

12 NSTX Budget cross-cut >75% of the Project is PPPL labor. Many small procurements (parts, off the shelf hardware, materials) may be augmented with in house fabrication. All procurements fixed priced contracts.

Project Performance metrics Cost – CPI=1.02 CV=+ $427K Schedule – SPI= 0.96, Total float = 6 months PLUS 12 months schedule contingency BAC =$77.3 EAC= $80.7 TPC =94.3M Summary status; – Design = 93% complete – Procurement = 2% complete – Fabrication & Assy = 7% complete Free balance contingency 31% on remaining work (27% at CD-2) Risk: $2,000k retired since CD-2 Currently $3,744 remain 13

Performance to date is good 14 Performance is good to date Transitioning from design in FY09-11 to fabrication/assembly in FY Accelerated schedule being iterated but will call for significant ramp-up in spending, re-assignment of labor and increased procurement work load.

Milestones on Track for early finish 15

Excellent people getting the work done 16 Resource loaded schedules, CPR’s, meetings don’t actually accomplish work, people do! Must track needs and get (negotiate) assignments with other projects.

FY2011 FY2012 FY2013 FY2014 Contingency remains above target and available to mitigate uncertainties and risk % (through end August)

Risk monitored at monthly status meeting 18 Risk registry populated from WAF’s prepared by CAM’s Changes discussed monthly

Cost Performance, Variance analysis & Estimate to Complete 19 Bottoms-up performed every 6 months. Last one performed in June for the PDR. CAM’s marked –up their WAF’s and input to a scratch P3 file. DOES NOT CHANGE BAC. To date no cost ECP’s processed but the ETC provides advanced warning of what issues need to be mitigated. Monthly less formal ETC input from CAM’s discussed at the monthly status meetings.

Project Summary report 20 Communicate overall project performance at director’s meeting, internal and DOE meetings

Project Management – Analysis & reporting 21 Monthly status meeting ‒ Associate Director, Project Management, Project Controls, CAM’s ‒ Schedule progress, Earned value, Risk registry review, ETC assessment ‒ Variances, issues, impacts, resolutions, direction provided Monthly reporting including ‒ (see CAM notebook and Management Instrument panel) ‒ Updated risk register, VAR’s, PARS-II, Schedules, CPR’s, Special Reports Weekly Technical meetings (Design/analysis, value engineering and 4 week look-ahead) Weekly DOE video meeting (PPPL, PU & PSO Management with OFES) IPT meetings coordinated by DOE with all stakeholders Weekly (Daily) Meeting with PSO Federal Project Director Weekly Director’s meeting Work control center daily meetings for outage tasks Data collection, disciplined processes, and good communication fosters quick problem resolution and no surprises

Summary PPPL is a small lab which facilitates good communications and quick problem resolution. External project oversight, both technical and management, have provided valuable input and improved our operations and product. Astute planning by DOE and PPPL have positioned the project to take advantage of recent adversity. Excellent communication amongst stake holders. Management systems in place. Continuously enhanced in recent years. CAM’s have ownership of their CA plans. The project is >75% PPPL labor with relatively small procurements. The largest and most critical procurement contract has been placed. The project is 27% complete Risks assessed and being retired. Contingency free balance tracking to plan. All Project Execution Plan (PEP) milestones ahead of plan. The project is on schedule, below budget, and forecasting early completion.