Implementation of IPPC and its application to sectors in different industrial scales – Experience of Czech Republic Jan Slavík, IPPC Unit - MoE of Czech.

Slides:



Advertisements
Similar presentations
Implementation of waste management plans in Serbia 2013 workshop on Waste Policy Implementation May 2013 Copenhagen.
Advertisements

EU FORMAL REGULATION – TYPES OF STANDARDS ENVIRONMENTAL QUALITY OBJECTIVES ENVIRONMENTAL QUALITY STANDARDS.
HR 09 IB EN 02 – German Proposal, Zagreb, 10 June 2011 Page 1 April 12, Strengthening the Ministry of Nature Protection of the Republic of Armenia.
Industrial Pollution Control and Risk Management: IPPC Neil Emmott Environment Directorate-General 7 April 2006.
BULGARIAN COMPETENT AUTHORITIES IN THE FIELD OF IPPC Kalin Iliev Ministry of Environment and Water Bulgaria.
The IPPC Recast. New environmental requirements for explosives production sites.
ECENA 4 th Exchange Programme Cluj Napoca, October, 2005 National Updates in the Transposition and Implementation of IPPC directive Ministry of Environment.
SÄTEILYTURVAKESKUS STRÅLSÄKERHETSCENTRALEN RADIATION AND NUCLEAR SAFETY AUTHORITY Protection of the environment from ionising radiation - views of a regulator.
1 Inspection of LCPs: System for Inspection. ECENA Training Workshop Bristol, March 2008.
Possibilities of Business Support within the Operational Programme Enterprise and Innovation for Competitiveness May 2015.
The Sevilla process for supporting the implementation of the IPPC Directive Michael Parth Tallinn – Estonia 27 – 28 March 2008.
DEVELOPMENT OF THE NATIONAL INVENTORY SYSTEM IN THE REPUBLIC OF BELARUS Belarus has signed UNFCCC in June, 1992 Ratified in May, 2000.
Workshop, 12/3/2004 Banska Bystrica – SLOVAC REPUBLIC “INTEGRATED LICENCE PROCEDURE (Greek case)” Katerina Iakovidou-Anastasiadou Hellenic Ministry for.
Current state on Harmonisation and Implementation/Enforcement of Environmental Legislation - Industrial Pollution Control in SLOVENIA Barbara Bernard Ministry.
Report on the current legal structure and resources available to the environmental protection agencies and inspectorates in Croatia 1st BERCEN Exchange.
Croatian Report on new Environmental Protection Law Josipa Blažević-Perušić, B.Sc. Arch. State Secretary Anita Pokrovac-Patekar, B.Sc. Pharm. Senior Environmental.
Experience with an introduction of IPPC Directive in an AC IMPEL member country Czech Republic Czech Enviromental Inspectorate.
EPER reporting process in Hungary with emphasis on the experiences Edina Gampel Counsellor National Inspectorate for Environment, Nature and Water Budapest,
ECENA Exchange Programme First Plenary Meeting January, 2006 Zagreb, Croatia Update on strengthening the implementation and enforcement of EU environmental.
The IPPC Directive and its implementation Alexandre Paquot European Commission Environment Directorate-General Phare Capacity.
Ministry of Waters and Environmental Protection, ROMANIA 1 BERCEN 1 st Exchange program – November 2002 Croatia PROBLEMS AND SOLUTIONS IN COOPERATION.
EU Legislation in the field of environment – key developments in 2007 and rd ECENA Plenary Meeting 18 September 2008.
MINIMUM CRITERIA Project Manager Marianne Lindström, Bulgaria SYKE, Expert Services, Environmental Management Division.
1 Permitting of industrial facilities in Croatia.
Consultant: CMDC Joint Venture Reflections on draft Recommendations for Revision to Administrative Regulations: By Norman Sheridan, Legal & Institutional.
ECENA First Plenary Meeting January, 2006 Zagreb, Republic of Croatia Forthcoming obligation related to implementation and enforcement of EU legislation.
The Industrial Emissions Directive (IED) 2010/75/EU Gabriella Gerzsenyi & Menno Verheij European Commission, DG Environment Industrial Emissions Unit 03.
IPPC transposition and experience with its implementation in the Czech Republic ?? …!! AjPíPíSí ??
AйПиПиСи ?? IPPC implementation - experience from new EU member countries & changes brought by Industrial Emissions Directive Monika Přibylová Kiev, 10.
1 Workshop on the Directive 96/61/EC concerning (IPPC) Integrated pollution prevention and control INFRA Public participation & access to environmental.
Slovak Environmental Inspectorate Procedure of issuing the permits in the Slovak Republic.
2 nd Annual meeting Athens, January 2006 Legal Protection of Transitional Waters in Greece Dr. Petros Patronos / Dr. Vivi Roumeliotou Nomos + Physis.
Energy Efficiency in IPPC Installations, Wienna Oct/2004 Petr Honskus (SPF Group) Chairman of EE TWG CR Vladimíra Henelová, Monika Přibylová Members.
1 st Program of Experience Exchange INSPECTION – PLANNING AND REPORTING (CURRENT SITUATION IN THE REPUBLIC OF CROATIA IN CORRELATION WITH IPPC) Brijuni,
SEVESO II transposition and implementation – possible approaches and lessons learned from MS/NMS SEVESO II transposition and implementation – possible.
The conception of Information System on Integrated Pollution Prevention and Control (IS IPPC) Ing. Blanka Kapustová, PhD. Slovak Environmental Agency Centre.
Workshop on the Application of Environmental Indicators and Indicator based Environmental Reporting Donetsk 31 October – 2 November 2006 Draft Guidelines.
Environmental Impact Assessment in the Slovak republic.
FEAD ANNUAL CONFERENCE 2008 Future Challenges for the Waste Management Industry Paris, 19 September 2008.
Air Quality Governance in the ENPI East Countries Capacity building for decision makers for small businesses regulation Monika P ř ibylová.
The legal background for implementing the IPPC, EPER, and PRTR Protocol Requirements Orsolya Adamovics Department for Conservation of Environment Ministry.
Strengths and weaknesses of the permitting system and enforcement process in RIEW – Veliko Turnovo Regional Inspectorate of Environment and Water - Veliko.
SEA in the Czech Republic Prague, 24 September 2008.
Iuliana CHIDU European integration counsellor Ministry of Environment and Water Management Prague - CZECH REPUBLIC April 2005 DIRECTIVE 96/61/EC.
How to start with the implementation of IPPC Directive Czech Republic Czech Environmetal Inspectorate.
Developing PRTR Systems in Europe : EPER, E-PRTR and the PRTR Protocol Magda Tóth Nagy Public Participation Programme October 15, 2007.
UN ECE CEP Working Group on Environmental Monitoring and Assessment 7th Session Geneva 27 – 29 November 2006 Item 5(a) Draft Guidelines on Indicator based.
1 Short overview of the implementation of IPPC, LCP, Seveso II, Waste Landfill and Incineration directives Short overview of the implementation of IPPC,
CROATIA Country Report IPPC Directive: implementation, problems, constraints, open questions,… Anita Pokrovac Patekar, B. Sc. Pharm. Ministry of Environmental.
Consultant: CMDC Joint Venture Czech experience - Use of BREFs and national BAT notes, role of IPPC Agency, Czech TWG Multi-Country Workshop June 8th,
Achievements in IPPC Directive Implementation: problems and constraints Albania Ministry of Environment 3 rd BERCEN Exchange Programme for the Environmental.
The current legal situation
The EU and Access to Environmental Information Unit D4 European Commission, Directorate General for the Environment 1.
Pilot Project on implementation of SEA for regional planning in Ukraine Prof. Dr. Michael Schmidt Dmitry Palekhov Brandenburg University of Technology.
1 Review of the IPPC Directive and related legislation Second Meeting Of Working Group E On Priority Substances 17 October 2007 Filip FRANCOIS – DG ENV.
Peter Lukáč Ministry of Environment of the Slovak Republic Department of Environmental Assessment.
New approach in EU Accession Negotiations: Rule of Law Brussels, May 2013 Sandra Pernar Government of the Republic of Croatia Office for Cooperation.
Lithuanian Water Suppliers Association LEGAL REGULATION OF WASTEWATER DISPOSAL AND TREATMENT IN LITHUANIA.
Integrated and Planned Enforcement of Environmental Law Phare Twinning Project CZ03/IB/EN/01 1 The IPPC Directive Introduction to the philosophy Rob Kramers.
IPPC A general overview Nigel Barraclough Policy Adviser Industrial Pollution Control Branch Air and Environment Quality Division. Taiwanese Environmental.
TAIEX-REGIO Workshop on Applying the Partnership Principle in the European Structural and Investment Funds Bratislava, 20/05/2016 Involvement of Partners.
M O N T E N E G R O Negotiating Team for the Accession of Montenegro to the European Union Working Group for Chapter 27 – Environment Bilateral screening:
BAT - BREF Their scope Rob Kramers Senior advisor InfoMil.
PRESENTATION OF MONTENEGRO
INTEGRATED PERMITTING PROCEDURE IN THE CZECH REPUBLIC
Overview of public participation in strategic decision-making in the UNECE area David Aspinwall.
Mr. Nepimach Czech Ecological Institute
Czech Republic Mining Association (Těžební unie)
Aleksandra Antonowicz Green Federation GAJA/CCB
Industrial Emissions Directive Targeted stakeholder survey
Presentation transcript:

Implementation of IPPC and its application to sectors in different industrial scales – Experience of Czech Republic Jan Slavík, IPPC Unit - MoE of Czech Republic Workshop on the Directive 96/61/EC (2008/1/EC) concerning Integrated Pollution Prevention and Control (IPPC) Ankara, November 2009

Content 1. IPPC implementation in Czech Republic 1.1. Elementary principles 1.2. Situation of industry before implementation 1.3. New legislation 1.4. Institutional set-up 1.5. Permitting 2. Cooperation with industry 2.1. Cooperation in implementation 2.2. Industry in system of information exchange and preparation of legislation 2.3. Subsidies for application of BAT and emerging techniques 3. Impact on Industry 3.1. Administrative impacts 3.2. Economical and Environmental Impacts 4. Conclusion

1. IPPC implementation in Czech Republic

1.1. Elementary principles Integration an IPPC Permit replaced several permits in the field of air, water protection and waste. New permitEvery existing IPPC Installation had to obtain the new permit and went throught full scale permitting process. SubsidiarityPermitting itself is done on regional level, regional authorities are supported on central level by MoE and CENIA (expert agency). Individual approachEvery permit is a result of individual permitting and its binding conditions are unique (taking into account the scale of production, technical characteristics of technology and local situation). However, minimal requirements have to be respected. Dialogue with operatorPermit conditions are the result of dialogue among operator, state institutions and general public. Access to informationAll permits and relevant documents from permitting as well as BREF documents (in Czech) are available on the Internet without any restriction Application of BAT The permit should ensure that operation of installation is in line with relevant BAT requirements.

1.2. Situation of industry before implementation The Czech Republic is highly industrialized country About 1500 IPPC Permits represents most of our important industry (almost all Annex I activities) The most of permits is granted to small and medium sized enterprises. Industry generates about 30 % of GDP. Industry gives about 40% jobs within national economy Structure of industry covered by IPPCD (according to Annex I)

1.2. Situation of industry before implementation

1.3. New legislation IPPCD was implemented by the new legal act (IPPC Act) – in force from 1 January 2003 Old legislation (separate acts on waste, air protection, water protection) is still valid –They are used as minimum requirement for setting binding conditions according to the IPPC Act. –Separate permits (for waste, air and water) are replaced by the IPPC permit. For new installations IPPC Permit is given after Environmental Impact Assasment (EIA) and before Building Permit. EIA -› IPPC -› Building Permit Same procedure for all activities, all industial scales and new and existing installations. Same and binding form of application for all activities, all operators and new and existing installations. Industrial scale is reflected in permitting itself – every installation is permitted individually, extend of requirements reflects: industrial scale of operator, economical situation and impacts on Environment. Length of the procedure is from 117 – 185 days.

1.3. New legislation Act No. 76/ 2002 Coll. on integrated pollution prevention and control, on the integrated pollution register and on amendment to some laws (the Act on integrated prevention) Transposition of IPPCD, institutional set-up, process set-up, relationship to other acts in the field of environmental protection. Act includes: Definitions Procedure of permitting Content of application and permit Obligations of the Operator Execution of the Public Administration (role of authorities) Fines etc. Decree No. 554/2002 Coll. establishing the specimen of the application for integrated permit, the scope and method of filling in of the application. Decree includes:Detailed and binding rules on structure of application Guidance and examples for operator One structure for all kind of activities. Decree No. 63/2003 Coll. the concept and range of exchanging the best available techniques information Establishing on a national level rules for the exchange of information on Best Available Techniques (including the role of industry in this process).

1.4. Institutional set-up REGION – permitting authority Region is the highest-level administrative unit. There are thirteen regions and one capital city of Prague with regional status Average region: about inhabitants about 120 IPPC Permits about officers responsible for the IPPC agenda very often strong representation of one branch of industry (chemistry, production of metals, intensive rearing)

1.4. Institutional set-up REGIONS- permitting authority - inspection of IPPC installations CZECH ENVIRONMENTAL INSPECTORATE - statement on application in permitting process - inspection of IPPC installations in relation with environment REGIONAL PUBLIC HEALTH AUTHORITIES - statement on application in permitting process - inspection of IPPC installations in relation with public heath CENIA - Czech Environmental Information Agency - expert support of permitting authority (technical experts) - statement on application in permitting process (BAT) MINISTRY OF ENVIRONMENT - supreme state supervision and the central body of state in IPPC - appealing authority - expert support of permitting authority (legal experts) MINISTRIES OF INDUSTRY AND TRADE, AGRICULTURE AND HEALH - organisation of information exchange of BAT - statement on appeal

Operator of Installation Application for Integrated Permits Regional Authority For 30 days in 8 days Forwarding the ApplicationDisclosure of brief summary CENIA (BAT assasment) Relevant Administrative Authorities General Public Sign in of other Participants Participants in Procedure in days Affected State in 45 days for CENIA, otherwise 30 days in 45 days from receiving statemens Statements Regional Authority Disclosure of Statement of CENIA (BAT) Oral Discussion of Application Decision on Application Disclosure of Decision Appeal against the Decision 1.5. Permitting

2. Cooperation with industry

2.1. Cooperation in implementation  In period 1999 – 2007 IPPC and BAT issues were systematically consulted with representants of industry.  Proposals of the industry were very often useful but not always acceptable – They were not compatible with requirements of IPPCD and other EU legislations.  Series of workshops and consultations – IPPC principles (permitting) and BAT implementations –Workshops based on regional approach (organized by Regions) –Workshops for particular industrial activity (organized by ministry of agriculture, industry and trade, environment, CENIA) –Workshops organized by specialized industrial associations (Association of Chemical Industry, Association for the District Heating, Czech Cement Association…)  Special attention was given to smaller scale activities (e.g. intensive rearing): due to economical situation operators has limited possibility use assistance of expert companies. Ministry of agriculture organized workshops on regional level, printed manuals on application especially in particular activity. Manuals on BAT in intensive rearing.

2.1. Cooperation in implementation  Communication between industries concerns and state administration Activities of relevant ministries during industrial and agricultural exhibitions and convention, advertising in relevant magazines Publications on IPPC Articles in technical and agricultural magazines

2.1. Cooperation in implementation  IPPC on Internet The internet is used as the most accessible source of information on IPPC and BAT for operators, general publics and state administration. Web page on permitting and administration –Information on legislation and administrative procedures –Fulfill requirements on accessibility of certain documents from permitting to general public –Operator can use the page to check progress in permitting –Complete database of permits and their changes –Source of data for reporting to EU institutions Web page on BAT –BREFs in English and Czech –Other publications on BAT (more specific – focused on BAT applicable in CZ) –Internet forum for national technical working group –Other relevant news and information

2.2. Industry in system of information exchange and preparation of legislation  Activities of national technical working groups Active national technical working group significantly support successful implementation of BATs in relevant industry. –Organized and financed by relevant ministry. –Information on BAT in particular branch of industry. –Translation of BREF into Czech language. –BAT and IPPC manuals for particular activity. –Cooperation on preparation of preparation of BREF on EU level.  Testing round of permitting procedures During process of drafting of national IPPC legislation Cooperation of: –industry concerned (food production, chemistry, intensive rearing), –research institution (BAT application), –state administration (regions, ministries).  Twinning projects on IPPC with participation of Germany, United Kingdom and Netherlands included also participation of industry.

2.3. Subsidies for application of BAT and emerging techniques Operators of IPPC installations has possibility to obtain subsidies and grants on application of advanced techniques for environmental protection Operational Programme Environment Available 4,92 mld. € from European Union + 0,87 mld. € from public resources. Sources: Cohesion Fund (85%) and European Regional Development Fund (15%). Relevant period 2007 – supported projects so far (in all areas of environmental protection). One of the priorities is reduction of industrial emissions (mainly by application of advanced BATs in IPPC installations) and applied research in BAT: –The renovation or installation of technologies for reduction of industrial pollution. –Advanced monitoring systems. –BAT centres – research units focused on testing of BAT and emerging techniques with emphasis on their applicability in national conditions, validation of their parameters and on informing operators on BAT (usually as part of technical university or research institution).

2.3. Subsidies for application of BAT and emerging techniques Extend of support The maximum level of subsidies is 90% of relevant expenses. Subsidies must not interfere with economic competition. Subsidies can be granted only in „assisted areas“. For standard enterprise is subsidy limited to 30 – 40 % of relevant expenses. The limit of subsidy can be further increase for: -small enterprise (employ fewer than 50 persons and which have an annual turnover not exceeding EUR 10 million) to additional 20%. -medium size enterprise (employ fewer than 250 persons and which have an annual turnover not exceeding EUR 50 million) to additional 10%. „De minimis“exception Certain enterprises can apply for „de minimis“exception – 90 % of relevant expendes (smaller projects limited by EUR). Applicable till 2010.

3. Impact on Industry

3.1. Administrative Impacts Permitting Preparation of application for a permit. –Mandatory form. –Can be done by operator or expert company. –Including proposal for binding operating conditions (BAT based). Administrative Fee - Granting a permit. Change in operation Planned changes are announced to permitting authority. If the change is not find substantial permitting authority just change the permit to be in line with new situation. If the change is find substantial the procedure is in general same as in permiting (its extent can be limited). Operation –Evaluation of compliance with the conditions of the integrated permit (report) –Keeping records of information on compliance –Notification of all unusual situations, accidents at the installation and accidental releases of pollutants

3.1. Administrative Impacts PermittingChangeOperation or Overview of administrative requirements – expenses (EUR)

3.1. Administrative Impacts PermittingChangeOperation Overview of administrative requirements – working hours

3.1. Administrative Impacts Advantages of IPPC for operators One permit instead of several single-media permits and documents Improved transparency of requirements and binding conditions. Integrated permit replaced the following: -Air protection permit (emission limits) including binding operating regulations -Water protection permit including accident rules (water protection) -Waste handling permit -Permit for extracting of groundwater -Permit for discharching of wastewater -Noise requirements -Energy efficiency requirements (Energy audit conclusions) One contact point instead of several institutions Better communication with state administration. Regional authority (IPPC Unit) replaced the following: –Water basin authority –Municipality –Czech Environmental Inspection –Regional Hygiene Authority –Various departments and units of Regional authority

3.1. Administrative Impacts Advantages of IPPC for operators Individual Permitting –Operator can proposed its operating conditions –Individual conditions taking account operators history, its technical characteristics, economical aspects, scale of production and impact on environment (Minimum requirements have to be always respected) Significant reduction of administrative burden – change of permit If the announced change is find not heaving significant negative effects on human beings or the environment the authority just change the permit to be in line with new situation. Disadvantages of IPPC permitting (from point of view of operators) -Administrative burden (new permitting) -Possibility of new requirements (investments) beyond „minimum requirements“. This requirements can be based on: a)Problems with environmental quality standard. b)Insufficient compliance with BAT (without proper justification). -Uncertainties related to public participation of process (NGOs)

3.2. Economical and Environmental Impacts Bigger scale industry (e.g. Energy, metal and chemical industry) BAT requirements Problem to identify investments to BAT and standard modernisation –Most of modern technologies has BAT parameters. –BAT in existing installation is set on individual basis (technical and local characteristics) In case of serious and unjustified incompliance with BAT –Mandatory schedule for modernisation is part of the permit (transition from mercury cell technology in chlorine-alkali industry). –The schedule takes, among other things, into account economical situation of an operator. Communication with operators shows that BAT requirements don't represent significant economical burden Environmental quality standards In case that an IPPC installation significantly decrease local environmental quality standards below legal requirements permitting authority may set binding conditions far beyond BAT and minimum requirements (e.g. Emission ceilings for certain pollutants). It may represent significant economical burden or reduction of production.

3.2. Economical and Environmental Impacts Smaller and medium scale industry (e.g. intensive rearing) Expenses in relationship with administration of permitting were reduced by workshops and manuals prepared by state administration (Operators could prepare application by themselves and not use expert companies). Although Application and permitting procedure was the same as for the bigger scale industry, scale of activity and its impact on Environment was taken into account. In BAT requirements was taken into account if they allows implementation under economically and technically viable conditions and if they are applicable in local conditions of the Czech Republic. From changes related to IPPC was beneficial especially for small and medium size enterprises: a)improved transparency of legal requirements, b)simplification of communication with state administration, c)reduction of administrative burden related to change of permits.

4. Conclusion Same rules for all industrial scales and all activities proved viable and successful. Individual permitting takes into account all relevant aspect of production, including industrial scale. However, minimum requirements and impact on Environment have to be respected. For successful implementation operators have to be informed in advance on new requirements and BATs. IPPC improved transparency binding requirements for operator (one permit instead of several documents) and communication with state administration (one contact point – Region). IPPC legislation did not significantly increase administrative burden on operators. Economic impacts with relation to BAT requirements are extremely hard to identify – from series of consultations with operators seems acceptable. Intensive communication with industry and permitting authorities is necessary for identification of possible problems in particular sector. Identified problems can be solved mostly by other then legal changes (assistance to problematic group of operators – workshops, manuals, subsidies).

Thank you for your attention! ContactJan Slavik Ministry of Environment of Czech Republic IPPC Unit Vršovická Praha 10 Phone: Fax: