Power Transmission & Distribution Project LARSEN & TOUBRO LIMITED ECC DIVISION Front Page www.engineersportal.in.

Slides:



Advertisements
Similar presentations
Safety Absolutes Green Lake
Advertisements

Mitigation of AC Induced Voltage On Buried Metallic Pipelines
A Joint Code of Practice Objectives and Summary Presentation
Barhale Procedure for Site Establishment
TITAN Group …….Managing Site Build up for the telecom sector TICS Telecom Projects Consultancy Pvt. Ltd.
Project Planning: Assembling a Mortenson “Integrated Work Plan”
Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.
Mobile Radiographic Equipment. Introduction In-patients who could not leave their beds In-patients who could not leave their beds Surgeons who required.
POWERLINKS TRANSMISSION LIMITED a joint venture of TATA POWER &POWERGRID.
General Information Dimensions · Structure Width: ~ 197in. (16.4’), 99in. (8.2’)/car · Slope Angle: 5 degree · Structure Height (Front): 100in. + base.
Offshore Wind 2004 From Vindeby to Nysted A Manufacturer’s Experience Henrik Stiesdal Bonus Energy A/S.
The Power Grid ELEC 403 The Citadel Mark McKinney.
Skyscraper Construction
DESIGN OVERHEAD TRANSMISSION LINES Prepared by:- Er. Varinder Kaur
Protection against Lightning Overvoltages Overvoltages due to lightning strokes can be avoided or minimized in practice by (d) shielding the overhead lines.
Advantages of Lattice Towers
Successful Implementation of GIS Techniques for Route Alignment & Surveys of Power Transmission Projects of POWERGRID Power Grid Corporation Of India Ltd.
INDUSTRIAL & SYSTEMS ENGINEERING
SUPREME & CO.PVT LTD. Traditionally overhead transmission lines have been built on lattice type structures. For years, this has been found structurally.
E4014 Construction Surveying
“INSULATOR IN OVER HEAD LINE”
“Design of Water Supply and Sewer Systems” IV. Water Tank (Service Reservoir). Dimensioning and Constructing (Drawing 4) Main Procedures 1. Determination.
Increasing the life cycle of existing grids to avoid high replacement costs of new systems By S.R.Sethi Member Delhi Electricity Regulatory Commission.
Transmission and Distribution - Role of Indian Electrical Equipment in the XII Year Plan. Presentation by: Sterlite Grid Ajay Bhardwaj COO.
Detail and Assembly Drawing
RPG Vision Going for Growth
1 Oncor Electric Delivery Proposed Changes To The 2012 National Electrical Safety Code.
OUR PASSION: Earthmoving & Mining Machines Plant Maintenance Fabrication Erection.
Development and Construction of On- Shore Windfarms Andrew Aveyard Green Cat Renewables Jim Wilkinson CA Blackwells.
A SAMMINAR ON ELECTRICL TRANSMISSION LINE
Bridge Engineering (9-1) Suspension Bridges I. *Components: Anchorage (blocks or tunnel type), towers, main cables, hangers, stiffened (box) girder and.
Gandhinagar Institute of Technology
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
SAFE PRACTICES IN POWER DISTRIBUTION SYSTEM UNDER NESCO.
Mortenson Canada Corporation Proprietary and Confidential Construction and Contracting Clean Energy BC November 8, 2010.
Designing Solar PV Systems ( Utility Scale). Module 1 : Solar Technology Basics Module 2: Solar Photo Voltaic Module Technologies Module 3: Designing.
RHD Foundation Main conditions of the auction Address Kursk Region, city of Kursk, the Central district. Lease right price (initial price) (four.
WELDINGH_DK_AUTHOR_6.2_12 Barcelona May Impact of the Deregulation on the Safety H. Weldingh –DEFU I.R. Ludvigsen –The Danish Electricity.
Department of Electrical Engineering
Electrical Safety Authority
HIGHWAY DESIGN PROCESS & ROUTE LOCATION Spring 2016.
132KV GSS PIPAR CITY JODHPUR
A PRESENTATION On 400KV GSS SURPURA JODHPUR
MH...CH LECT-021 SYSTEMS CONCEPT Adopting a materials handling systems from overall optimization point of view. Adopting a materials handling systems.
Of TRANSMISSION LINE STRUCTURAL STEEL FASTENERS HARDWARE & FITTINGS 1 total Karamtara Engineering Corporate Presentation 17.
Public Tender for Comprehensive Project to award GTS Project in concession “AGUAYTÍA – PUCALLPA 138 kV ELECTRIC TRANSMISSION LINE (circuit two)” GTS: Guaranteed.
New Technologies Group Saint-Petersburg Management Company Vremya Project Management Center New Technologies Malovishersky Electrotechnical Factory.
Warmly welcomes YOU PIANO PRESITEL. Piano Presitel was established in 1960 as a Partnership company with three partners. The company has complete manufacturing.
Ch 1 Construction accidents 1. Health and safety definitions Health is the protection of the bodies and minds of people from illness resulting from the.
Estimating and Scheduling CEE 492
Mechanical Design of Transmission Lines PREPARED BY: SHAH RAHIL( ) SONAL SHRIVASTAVA( ) Guided by: DR.NILESH CHOTHANI.
Electrical Power System SMJE 2103
PRE-BID MEETING CONSTRUCTION OF MEDUPI BORUTHO 400kV TRANSMISSION LINES PRE-BID MEETING PROJECT MANAGEMENT Presented by: Theo Meveni 13 January 2015.
Electrical Power System SMJE 2103 Electrical Power Delivery System.
GUIDED BY: DR. NILESH CHOTHANI PREPARED BY: SEJAL SHAH( )
Preliminary Survey 1. The alignment of the line route is carried out by survey using a theodolite. 2. The following positions are fixed during this survey.
©Larsen & Toubro Infotech Ltd. Privileged and Confidentialwww.LnTInfotech.com Discover the Champions
UNIT-5. ELECTRICAL SAFETY, WIRING & INTRODUCTION TO POWER SYSTEM
“AGUAYTÍA – PUCALLPA 138 kV ELECTRIC TRANSMISSION LINE
Sub Station.
Topic Name: INSULATORS
Fencing.
Work experience presentation
Investment Work Package I.2 H2 to Transportation Fuels:
Installation And Estimation of Service Connection
Scientific Research and Design Republican Unitary Enterprise BELENERGOSETPROJEKT besp.by.
Govt. Polytechnic,Manesar
BRIEFING ON THE INTERCONNECTION LINES OF THE
Equilibrium of Strings
Under Ground Cables By Dr. P. Bala Chennaiah, Associate Professor,
Presentation transcript:

Power Transmission & Distribution Project LARSEN & TOUBRO LIMITED ECC DIVISION Front Page www.engineersportal.in

LARSEN & TOUBRO LIMITED L&T was founded in Bombay (Mumbai) in 1938 by two Danish engineers, Henning Holck-Larsen and Soren Kristian Toubro. L&T is a technology, engineering, construction, technology, manufacturing and financial services company. In 1944, ECC was incorporated by the partners; the company at this time was focused on construction projects (Presently, ECC is the construction division of L&T) Company Profile – ECC division www.engineersportal.in

Project Overview Generation Transmission Distribution The following 765 kv transmission lines associated with Rihand-III & Vindhyachal –IV Transmission system includes two tower packages:- Tower package- P219-TW11 150Km Gwalior- Jaipur 765 kV S/C Transmission line, Part-I Tower package- P219-TW12 150Km Gwalior- Jaipur 765 kV S/C Transmission line, Part-II www.engineersportal.in

Salient Aspects of the Project Name of the Project: - 765 kV S/C Gwalior – Jaipur (PART-II) Transmission Line Project Client: - PGCIL (Power Grid Corporation Of India Ltd., New Delhi) Contractor:- M/S LARSEN & TOUBRO Ltd., Chennai Project duration: - 24 Months Start date: - 24-03-2011 End date: - 30-03-2013 Total Cost Of Contract : - Rs 78,04,62,752/- ( Rupees Seventy Eight Crore Four Lacks Sixty Two Thousand Seven Hundred Fifty Two Only) www.engineersportal.in

Project Route Gwalior Gangapur Lalsot Kothun Phagi www.engineersportal.in

Towers The transmission towers are self –supporting hot dip galvanized lattice steel. Type designed to carry the line conductors with necessary insulators, earth wires and all fittings under all loading conditions. The tower should be fully galvanized using mild steel or high tensile steel sections as specified. Bolts and nuts with spring washer are to be used for connection. Galvanisation-Galvanization (or galvanisation) is the process of applying a protective zinc coating to steel or iron, in order to prevent rusting. www.engineersportal.in

Different Tower Sections www.engineersportal.in

Height Of A Transmission Tower 1. Minimum permissible ground clearance (H1) 2. Maximum sag of the conductor (H2) 3. Vertical spacing between top and bottom conductors (H3) 4. Vertical clearance between ground wire and top conductor (H4) www.engineersportal.in

Classification of Towers Type Of Tower Deviation Limit Typical Use A 0 deg. To be used as suspension tower B 0 deg.-15 deg. Tension tower for Earth wire. C 15 deg.-30 deg. To be used as section tower & for transposition of transmission lines. D 30 deg.-60 deg. Anchor tower for river crossing www.engineersportal.in

Purpose Of Using Different Tower 1. Tangent Suspension tower and it is generally A – type tower. 2. Angle tower or tension tower or sometime it is called section tower. All B, C and D types of transmission towers come under this category. www.engineersportal.in

Parts Of Transmission Tower www.engineersportal.in

Work Methods www.engineersportal.in Route alignment & Survey Soil Investigation Foundation Tower Erection Stringing Testing and commissioning www.engineersportal.in

Role Of Route Alignment & Survey The routing of the transmission line is most economical from the point of view of construction and maintaince. Thus optimal route should be used. Routing of transmission line through protected/reserved forest area should be avoided. The route should have minimum crossings of Major river, Railway lines, National/State highways. The number of angle points should be minimum. It is preferable to utilize level ground for the alignment. Crossing of power lines should be minimum. www.engineersportal.in

Role Of Soil For The Foundation Normal Dry Sandy Dry Soil Wet Nd-To be used for locations where normal dry cohesive or non-cohesive soils are met. Sd-To be used for locations where cohesion less pure sand or sand with clay content less than 10% met in dry condition Wt-Where sub-soil water is met between 1.5 meters and the depth of foundation below the ground level www.engineersportal.in

Role Of Stringing www.engineersportal.in 1.The machine is suitable to string one rope or one conductor. 2.The bull-wheel grooves are made up of high resistance interchangeable nylon sectors. 3.The machine is completely electronically controlled. www.engineersportal.in

Types Of Insurance Required Automobile Third Party Liability Liability Workmen’s Compensation Marine insurance for supply Employer’s Liability Installation www.engineersportal.in

Safety Systems And Safety Indices Objectives Establish and define chain of command for resolution of all hazards prevention issues Define individual hazards prevention and safety promotion responsibilities at each level of the construction team. Identifying highly hazardous operations within the scope of work and specify integrated preventive measures to mitigate the same. www.engineersportal.in

Safety Statistics of June 2013 S.NO DESCRIPTION NUMBER MAN-HOUR OT PERFORMED TOTAL 1 Company Staff 17 6052 Not Applicable 2 Departmental Workmen (including regular supply) 71 15336 9940 25276 3 Subcontractor's Workmen (including security personnel) 165 35640 23100 58740 Ot-Occupational therapy is skilled treatment that helps people become ... Goals  use of treatments to develop, recover, or maintain the daily ..... Performance skills GRAND TOTAL OF MANHOURS WORKED DURING THE MONTH 90068 www.engineersportal.in

MPCS and Reporting Systems Schedule of Construction program Schedule of Invoice Schedule of Milestone events Schedule of Plant & Machinery Schedule of Staff Schedule of labour Schedule of Material requirements Mpcs-Under MPCS, various reports are maintained like Cp-month wise target for each activity till completion and subsequently updating the actual accomplishments are listed Inv- Listing of activities for Planned vs. Actual Billing done as per the volume of work Executed Mil-critical activities comparing the planned vs. actual achievement. www.engineersportal.in

Major Constraints For The Transmission Line Project ROW Problems Tree Cutting Shut Downs Row-right of way Sd- railway crossings www.engineersportal.in

Thank u www.engineersportal.in