Earned Value JOEL VIRAY TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
Copyright , Dennis J. Frailey CSE7315 – Software Project Management CSE7315 M30 - Version 9.01 SMU CSE 7315 Planning and Managing a Software Project.
These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 6/e and are provided with permission by.
Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, :20 AM to 12:50.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
 Galorath Incorporated Parametric Performance Monitoring and Control (PPMC) Presented by: Karen McRitchie Galorath Incorporated 100 North Sepulveda.
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Earned Value Project Management: a powerful tool for software projects
Using Earned Value Management System (EVMS) Briefing for ATC Engineering & Test Division (ACT-200) Managers and Leads.
Earned Value Management
Advanced Project Management Project Cost Management Ghazala Amin.
Chapter 10 Project Monitoring and Control
CPM-400: xxx Lesson B: EV Data Analysis I Instructor Ellen Udell
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
© SYBEX Inc All Rights Reserved. Session 10 Project Control.
Monitoring and Information Systems
Software Project Management Lecture # 7. What are we studying today? Chapter 24 - Project Scheduling  Effort distribution  Defining task set for the.
Microsoft Project Association Building an EV System using MS Project (and Excel) Kirsty C. McLean, MBA, PMP Project Controller, Photonics Division General.
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Earned Value management This presentation is just a short introduction to a few terms and concepts. I am sure there will be training sessions in the next.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Project Scheduling 1. Why Are Projects Late? An unrealistic deadline established by someone outside the software development group Changing customer requirements.
Stage III: Project Execution and Control Earned Value Analysis B: Chapter 8: pages B: Chapter 12: the entire chapter.
Team7 Team Assignment 2 Software Measurement and Analysis.
Mohawk Vehicle - MEGA HERZ ELEC & VEN - MOH-2 F C-0050 J:\CS40\Data Analysis\- Standard Analysis Package/Sample Standard Analysis Package.
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
EARNED VALUE MANAGEMENT (EVM) TUTORIALS
Ev3 1 In House Software Development:… Verner, etal IEEE Software, Jan?feb 2005.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
What Is It ? Why Do I Need It ? How Do I Do It? Earned Value Analysis.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Performance Measurement Baseline Contract Price (Project Price)
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Management
Work Packages / Deliverables Completed
Progress and Performance Measurement and Evaluation
Earned Value - What is it
An Introduction to Earned Value Performance Measurement
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
Earned Value Management
Presentation transcript:

Earned Value JOEL VIRAY

TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned Value System

What is Earned Value? Earned Value is an objective measurement of how much work has been accomplished on a project and at what cost Provide early alerts to performance slippage Earned Value indicates how much of the budget should have been spent in view of the amount of work done so far A Manager’s Tool for Integrated Cost, Schedule and Technical Performance Management Technical Schedule Cost Earned Value CSSR CPR Other Information

Why use EVM? Accurate picture of project status –cost, schedule, AND technical Early and accurate identification of trends and problems Basis for corrective action Supports mutual goals of contractor and customer –bring project in on schedule and cost

How Does Earned Value Work? Successful EVM management requires several key practices: –Identify each project deliverable –Develop a schedule for the completion of each deliverable –Assign a value to each deliverable

Terminology ACWP = Actual Cost of Work Performed BCWP = Budgeted Cost of Work Performed BCWS = Budgeted Cost of Work Scheduled SPI = Schedule Performance Index –(EV/Planned Value) or (BCWP/BCWS) CPI = Cost Performance Index –(EV/Actual Cost) or (BCWP/ACWP) EAC = Estimate at Completion BAC = Budget at Completion

WHY DO I NEED IT? Your project: –total budget of $100,000 –12 month effort –produce 20 units How are you doing? Is everything going to plan? How far along are you? (64%, 50%, >40%) –Is this where you expected to be or do you need to take action? EVM - A Simple Example EVM - A Simple Example Status: –spent to date: $64,000 –time elapsed: 6 months –units produced: 8 complete or 40% Complete

Earned Value – the Math Your project: –total budget of $100,000 –12 month effort –produce 20 units The Basics BAC = Budget at Completion = $100,000 BCWS = Plan =$50,000 ACWP = Actuals = $64,000 BCWP = Performance = $5,000/unit = $40,000 Status: –spent to date: $64,000 –time elapsed: 6 months –units produced: 8 complete or 40% Complete EVM - A Simple Example

Your project: –total budget of $100,000 –12 month effort –produce 20 units Earned Value –BAC = $100,000 ACWP = $64,000 –BCWS = $50,000 BCWP = $40,000 The Variance Measures CV= Cost Variance =BCWP-ACWP= -$24,000 SV =Schedule variance = BCWP-BCWS= -$10,000 CV% = CV/BAC = -20% SV % = SV/BAC = -10% CPI = BCWP/ACWP = 40,000/100,000 = 0.4 SPI = BCWP/BCWS = 40,000/50,000 = 0.8 Status: –spent to date: $64,000 –time elapsed: 6 months –units produced: 8 complete or 40% Complete EVM - A Simple Example

0 10K 25K 50K 75K 100K 125K JFMAMJJASONDMJJASONDJF Earned Value Trend Graph TIME FRAME Cost TIME NOW BAC $100K EAC $120K Schedule Variance $10K Cost Variance $20K BCWS $50K ACWP $64K Earned Value (Work Completed) $40K

Sample Project: Second Story Deck Stands 10 feet off the ground Measures 12 x 12 feet Set of stairs will lead to the ground Will be supported with 4 posts resting on concrete footings Footings must extend below frost line (4 feet) Homeowner (and friends) will construct with standard materials

Planned Values for Deck Replacement Project

Measuring Performance End of Day 5 –Planned: 34 hours of work –Expended: 36 hours –Earned: 26 hours

Measuring Performance

CPI (EV/Actual Cost) 26/36 = 0.72 –We are realizing 7.2 hours of result for every 10 hours of actual effort expended SPI (EV/Planned Value) 26/34 = 0.76 –We are realizing 7.6 hours of result for every 10 hours of planned effort

Corrective Action Stakeholder PriorityGeneral ApproachPossible Approaches Maintain project scheduleSacrifice product Reduce scope of other part of project (hand railings) Stop digging and hope building inspector doesn’t notice Sacrifice cost Work overtime Have a friend help (more pizza and beer) Rent a back-hoe

Re-Baseline Plan

Why do we need Early Warning? Course corrections are easier when you have time to make adjustments It’s too late when you’re this close to the iceberg!

STATING THE OBVIOUS EVM will not solve your problems - only you can do that! A good tool is POINTLESS if you don’t TAKE ACTION based on the information it gives you!!!

Line of Business Applications WAWDIFMS SOS SLDCADA More… EPM Solution Architecture Internal/ExternalDatabases