May 16, 2007Change Management Board Meeting1 Local: 850-410-5667 Toll-Free: 866-374-3368 Ext. 5667.

Slides:



Advertisements
Similar presentations
SunGuide TM Software Development Project Release 4.0 Data Fusion Follow-Up DR Jan. 8, 2008 Updated: Jan 4, 2008, 11:00 am.
Advertisements

SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.
Current Status of the FDOT SunGuide SM Software Project Robert W. Heller, Ph.D. March 16, 2005.
FDOT Central Office ITS Software Update
Using the “Cloud” in Daily Operations
Statewide Transportation Management Center Software Library System Status Meeting February 17, 2004.
02/25/11 Connected Vehicle Design Review Southwest Research Institute 1.
Connected Vehicle Design Review Southwest Research Institute
An Intelligent Transportation System Evaluation Tool in the FSUTMS Regional Demand Modeling Environment By Mohammed Hadi, Florida International University.
ITS Sketch Planning Tool Webinar 2:00 – 4:00 PM January 8, 2009.
1 ITS America Palm Springs, CA June 6, 2007 SunGuide SM Software – Florida's ITS Software ITS America Palm Springs, CA June 6, 2007 Trey Tillander, P.E.
FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.
SunGuide SM Software Development Project Status Meeting March 9, 2004.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting for SunGuide Release 4.0 August 18, 2008 August 18,
SunGuide SM Software Development Project Status Meeting (via teleconference) October 4, 2005 CDRL
Fast Forward Full Speed Ahead Presented at the Joint ITS Georgia / Tennessee Annual Meeting September 25, 2006 by Carla W. Holmes, P.E., PTOE Georgia Department.
Transpo 2012 The Future of Traffic Incident Management, October 30, 2012 Javier Rodriguez, P.E., ITS Operations Engineer Joe Snyder, TMC Manager FDOT District.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting January 11, 2005.
Outline Project Background ITS Architecture Overview GVMC ITS Architecture Deployment Plan.
January 11, 2007Map Alternatives Workshop 1 SunGuide SM Map Alternatives Workshop.
July 29, 2009 George Saylor, PE ODOT Senior ITS Engineer.
Benefit-Cost Analysis of the SMART SunGuide Operations in Fort Lauderdale, Florida June 2006 Steve Corbin District ITS Operations Manager FDOT District.
Smartphone Application for Road Rangers Tucker Brown Roger Strain Robert W. Heller, Ph.D. Southwest Research Institute San Antonio, Texas USA.
MODULE 4 Traffic Incident Management and The Road Ranger/TMC Operator
SunGuide® Software Development Project Release 4.3 Express Lanes Enhancements Design Review December 15, 2009 December 15, 20091R4.3 Design Review.
Enhanced 511: Beyond the Basics Jerry Woods Florida DOT – District 5 iFlorida - Automated Message Generation Based on Travel Times.
July 14, 2010SunGuide SMD Kickoff Meeting1 BDQ69 SunGuide Support, Maintenance and Development Enhancement Contract July 14, 2010 Kickoff Meeting.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting August 27, 2007.
Statewide Transportation Management Center Software Library System (SunGuide SM ) TIM & SunGuide SM Coordination Meeting October 21, 2004 Orlando, Florida.
SunGuide SM Software: Development Status Robert W. Heller, Ph.D. July 14, 2004.
Keeping You Moving. Work Zones Original Maintenance of Traffic.
SunGuide SM Software Development Project Release 3.0 Design Review May 8-9, 2007.
GUIDANCE FOR IMPLEMENTATION OF TIM PERFORMANCE MEASUREMENT Kelley Klaver Pecheux, PhD U.S. Department of Transportation T3 Webinar Program December 16,
SunGuide TM Software Development Project Release 4.2 FHP/CAD + AVL/RR Design Review January 8, 2009 Jan 8, 20091R4.2 Design Review.
SunGuide SM Software Development Project Status Meeting December 7, 2004.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.
Florida Traffic Incident Management Performance Measures Paul Clark – Florida DOT Traffic Incident Management and Road Ranger Program Manager.
SunGuide SM Software Development Project Status Meeting July 13, 2004.
Presented to Performance Measures Session FDOT ITS Working Group Meeting, Tampa, FL presented by Kenny Voorhies, Cambridge Systematics March 20, 2008 Florida.
Security and the National ITS Architecture ITS America 2003 Session 19: The State of the Practice: ITS and Homeland Security May 19, 2003 Minneapolis,
SunGuide SM Software Development Project Status Meeting November 9, 2004.
SunGuide SM Software Development Project Release 3.0 Design Review May 2-3, 2007.
SunGuide TM 4.0 Functionality Data Fusion: How Data is Managed June 24, 2008.
SunGuide TM Software Development Project Release 4.0 Kick-off Meeting October 15, 2007.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting October 1, 2007.
Traffic Incident Management Performance Measurement The Focus States Initiative: On the Road to Success.
Clay Packard, PE ITS GC Software Project Manager Florida Department of Transportation WAZE – FDOT Integration.
SunGuide SM Software Development Project Status Meeting April 29, 2004.
SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes GUI Design Review March 10, 2008.
1 Florida Department of Transportation ITS Performance Measures Breakout Session 2 – Elizabeth Birriel, P.E.
Florida’s Traffic Incident Management Program A Plan For Success Florida’s TIM Strategic Plan Paul Clark – Florida DOT Traffic Incident Management and.
SunGuide SM Software Development Project Status Meeting October 13, 2004.
SunGuide SM Software Development Project End of the Year ITS Working Group Meeting December 7, 2005.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting November 27, 2007.
April 29, 2004 Project Status Meeting Liang Y. Hsia, P.E. ITS Engineer Administrator Florida Department of Transportation.
1 U.S. Department of Transportation ITS Joint Program Office CASE STUDY #3 INTEGRATING THIRD PARTY CROWDSOURCED DATA Elizabeth Birriel, Florida DOT.
TMCs – The Next Generation ITS Tennessee Annual Meeting / October 8, 2009 Dr. Robert Edelstein, PE, PTOE.
SunGuide SM Incident Management Concepts Robert Heller October 21, 2004.
1 Benefits of ITS During Hurricane Evacuations Hurricane Evacuation Transportation Workshop April 5, 2003.
Smart Phone App for Road Rangers
Agenda Time Item Lead 8:30 – 8:35 Introductions Liang Hsia 8:35 – 8:50
SunGuideSM Software: Development Status Steven W. Dellenback, Ph. D
Focus State Initiative: TIM Performance Measures
Agenda Time Item Lead 10:00 – 10:05 Introductions Liang Hsia
SunGuideTM Software Development Project Release 3
SunGuideTM Software Development Project Release 3. 1
MOT Training for Incident Responders in Florida
Agenda Time Item Lead 8:30 – 8:35 Introductions Liang Hsia 8:35 – 8:45
SunGuideSM Software Development Project Status Meeting and Demonstration April 5-6, 2005 CDRL
M25 Stopped Vehicle Detection (SVD)
Presentation transcript:

May 16, 2007Change Management Board Meeting1 Local: Toll-Free: Ext. 5667

May 16, 2007Change Management Board Meeting2 Welcome and Introductions Steve Corbin, CMB Chairman

May 16, 2007Change Management Board Meeting 3 Change Management Board TimeItem LeadSupporting Materials 10:30 – 10:35Welcome and IntroductionsCorbin 10:35 – 10:45Previous Meeting Recap and Action Item ReviewCorbin April 5, 2007 Meeting Notes 10:45 – 11:10 SunGuide SM Software Release 3 Statewide Performance Measures Reporting Requirements (Vote) BondsBallot FHP CAD Interface Tillander Concept of Operations Draft V1.1 11:10 – 11:30 SunGuide SM Software Release 4 ATIS Data Fusion Subsystem Requirements (Vote) Glotzbach Functional Specification v3.2, Requirements Tracking Log v1.1, 3/3/07 Cost Estimate 11:30 – 11:55 SunGuide SM Map Alternatives Tillander SunGuide Alternative Map Approaches v1.01, Responses to Map Questionnaire 11:55 – 12:00Closing and Action Item ReviewCorbin

May 16, 2007Change Management Board Meeting 4 Change Management Board Previous Meeting Recap and Action Item Review Steve Corbin

May 16, 2007Change Management Board Meeting 5 Change Management Board Action Items – 1/2 1. Gene Glotzbach, Trey Tillander, and Steve Corbin will have a teleconference to decide on the edits to the CMB charter and then send the revised version to CMB members for review. 2. Trey Tillander will look into Safety Program’s software which can provide the mapping of FHP roadway. 3. Trey Tillander will update/modify the FHP CAD ConOps documents, including: –Flowchart –RCC coverage map 4. Jennifer Heller will check with FHP regarding the information of disable vehicle (DAV) and abandoned vehicle.

May 16, 2007Change Management Board Meeting 6 Change Management Board Action Items - 2/2 5. Steve Corbin will provide the Red tag information (based on event type, duration) in SunGuide R Districts will provide comments of FHP CAD ConOps document by 4/26/ Districts will provide comments of AMBER Alert ConOps document by 4/26/ Trey Tillander and Steve Corbin will review and circulate the document of Using SunGuide Software at Multiple TMCs Currently before next CMB meeting. The next CMB meeting will be scheduled at late May in video-conference format.

May 16, 2007Change Management Board Meeting 7 Change Management Board SunGuide SM Software Release 3.0 Statewide Performance Measures Reporting Requirements John Bonds

May 16, 2007Change Management Board Meeting 8 Performance Measures Reporting Requirements p 1/4 TM007D15 SunGuide shall calculate and store a notification time performance measure for each event by taking the time that the TMC was notified and subtracting from it the time the FHP or FDOT is notified. TM007D16 SunGuide shall calculate and store a verification time performance measure for each event by subtracting the time when an incident is confirmed from the time when the TMC was notified. TM009D3SunGuide shall calculate the Response Time for each confirmed incident by subtracting the date/time of initial SunGuide incident confirmation from the date/time that law enforcement or road ranger is dispatched. Response Timeincident ID = tLE/RR Dispatched - tconfirmed. TM010D2 SunGuide shall calculate the Incident Clearance Time (ICT) by subtracting the date/time that law enforcement or road ranger vehicle arrive on scene from the time that the lanes are cleared. ICT = tlanescleared - tLE/RR Arrives. TM010D4SunGuide shall calculate the total incident duration time defined as the difference in time from when FDOT or FHP is notified until the travel lanes are cleared. and associate it with the incident. Y / N CMB Vote

May 16, 2007Change Management Board Meeting 9 Performance Measures Reporting Requirements p 2/4 TM017DSunGuide shall calculate the rate that secondary incidents occur over a date-time period specified by the SunGuide operator for specified roadway segments or for the entire District. TM017D1The reduction in rate of secondary crashes performance measure shall be: Rate of Secondary Crashes = (Number of Secondary Crashes for a Date-Time period X 1,000,000) / (Total Vehicle Volume for a Date-Time period X Road Segment Length in miles). TM018DSunGuide shall track the primary way in which an incident was detected and associate that information with the incident for performance measure reporting. TM018D1Detection methods to be recorded by SunGuide are: by surveillance camera (CCTV), speed detector (by type), Road Ranger stop, FHP notification. TM018D2SunGuide shall be able to generate a report listing the number of incident detections by device type over a SunGuide operator specified date-time period. Y / N CMB Vote

May 16, 2007Change Management Board Meeting 10 Performance Measures Reporting Requirements p 3/4 TM018D3SunGuide shall be able to sort the incidents by level of incident severity. TM019DFor performance measures purposes, SunGuide shall calculate Vehicle Miles Traveled (VMT) expressed as million vehicle miles for any date-time period specified by the person requesting a performance measures report from SunGuide that deals with VMT. TM019D1For the volumes needed to calculate vehicle miles traveled (VMT) for presenting crash statistics, SunGuide shall use either TSO data provided in tabular form to calculate VMT or VMT shall be calculated by SunGuide off-line using the volume from detectors multiplied by the segment length. Y / N CMB Vote

May 16, 2007Change Management Board Meeting 11 Performance Measures Reporting Requirements p 4/4 The Requirements will be covered at Reporting Subsystem The Requirements will be covered at Reporting Subsystem No additional cost needed. No additional cost needed. CMB Vote

May 16, 2007Change Management Board Meeting 12 Questions?

May 16, 2007Change Management Board Meeting 13 Change Management Board FHP CAD Interface Trey Tillander

May 16, 2007Change Management Board Meeting 14 FHP CAD - ConOps

May 16, 2007Change Management Board Meeting 15 Questions and Next Steps?

May 16, 2007Change Management Board Meeting 16 Change Management Board SunGuide SM Software Release 4.0 ATIS Data fusion Subsystem Requirements Gene Glotzbach

May 16, 2007Change Management Board Meeting 17 Change Management Board SunGuide SM Software Release 4.0 ATIS Requirements Discussion and Vote Gene Glotzbach

May 16, 2007Change Management Board Meeting 18 Statewide 511 ATIS Block Diagram

May 16, 2007Change Management Board Meeting 19 Statewide 511 ATIS DFS Block Diagram 4 functional components 4 functional components

May 16, 2007Change Management Board Meeting 20 Statewide 511 ATIS Data Fusion Requirements 137 Data Fusion Subsystem Requirements Contained is a separate database –Florida 511 Requirements database Requirements specified in: –ITN #: ITN-DOT-06/ JP, –Title: Statewide Advanced Traveler Information System (ATIS) Cost Basis Documented in: – SunGuideSM ATIS Budgetary Estimate - March 3, 2007 Cost Estimate in two parts –SunGuide Changes (modifications to exiting) –Data Fusion Subsystem (new)

May 16, 2007Change Management Board Meeting 21 SunGuide Changes DFS GUI Requirements and Cost Pg 1/4 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 22 DFS GUI Requirements and Cost Pg 2/4 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 23 DFS GUI Requirements and Cost Pg 3/4 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 24 SunGuide Changes SwRI Cost Estimate GUI Pg 4/4 GUI Operator Map $22, DF026G CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 25 SunGuide Changes Admin Editor Pg 1/3 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 26 Admin Editor Pg 2/3 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 27 SunGuide Changes SwRI Cost Estimate Admin Editor Pg. 3/3 Admin Editor $23, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 28 SunGuide Changes Traffic Sensor Subsystem (TSS) Pg 1/2 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 29 SunGuide Changes SwRI Cost Estimate TSS Pg 2/2 TSS $17, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 30 SunGuide Changes Reporting Subsystem Pg 1/2 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 31 SunGuide Changes SwRI Cost Estimate Reporting Subsystem Pg 2/2 Reporting Subsystem $55, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 32 C2C Plug-in Pg 1/2 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 33 SunGuide Changes SwRI Cost Estimate C2C Plug-in Pg 2/2 C2C Plug-in $26, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 34 SwRI Cost Estimate for SunGuide Changes Integration Testing$24, Documentation Updates$12,829.08

May 16, 2007Change Management Board Meeting 35 Data Fusion Subsystem Pg 1/3 General Requirements PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 36 Data Fusion Subsystem Pg 2/3 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 37 SwRI Cost Estimate DFS General Pg 3/3 General DFS $167, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 38 Data Fusion Engine Tasks Pg 1/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 39 Data Fusion Engine Tasks Pg 2/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 40 Data Fusion Engine Tasks Pg 3/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 41 Data Fusion Engine Tasks Pg 4/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 42 Data Fusion Engine Tasks Pg 5/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 43 Data Fusion Engine Tasks Pg 6/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 44 Data Fusion Engine Tasks Pg 7/8 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 45 SwRI Cost Estimate Data Fusion Engine Pg 8/8 Data Fusion Engine $153, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 46 GUI Tasks Pg 1/6 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 47 GUI Tasks Pg 2/6 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 48 GUI Tasks Pg 3/6 1 = Critical PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 49 GUI Tasks Pg 4/6 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 50 GUI Tasks Pg 5/6 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 51 SwRI Cost Estimate GUI Tasks Pg 6/6 GUI Tasks $91, CMB Approval Yes ______ No ______ DF004G/1/2/3, DF006G,

May 16, 2007Change Management Board Meeting 52 C2C Plug-in Tasks Pg 1/2 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 53 SwRI Cost Estimate C2C Plug-in Tasks Pg 2/2 C2C Plug-in Tasks $71, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 54 Data Base Tasks Pg 1/ PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 55 SwRI Cost Estimate Database Tasks Pg 2/2 Database Tasks $36, DF003D, DF004D, DF003D, DF021F, DF021F1, DF016F1 CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 56 Reporting tasks Pg 1/2 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 57 Reporting tasks Pg 2/2 DF014, DF029, DF007F, DF012F, DF012F1, DF015F Reporting Tasks $25, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 58 Integration Testing Pg 1/2 PriorityReqID Requirement Text

May 16, 2007Change Management Board Meeting 59 SwRI Cost Estimate Integration Testing Pg 2/2 DF002, DF009, DF018, DF001R, DF005D Performance Testing (Integration Testing) $76, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 60 Other Costs DFS Documentation$22, FAT (Optional)$36, Deployment Support$24, Data Management$21, ATIS Contractor Coord.$69, Grand Total (incl. option) $981, CMB Approval Yes ______ No ______

May 16, 2007Change Management Board Meeting 61 DFS Requirements Not Priced HW HW HW HW N/C N/C ? Identified which requirement was grouped in what cost by SwRI in the requirements database.

May 16, 2007Change Management Board Meeting 62 Change Management Board SunGuide SM Map Alternatives Trey Tillander

May 16, 2007Change Management Board Meeting 63 Change Management Board Closing and Action Item Review Steve Corbin, CMB Chairman