1. Introduction Time is of essence in basically every construction project Yet, delays of some sort are general rule, rather than the exception Consequence:

Slides:



Advertisements
Similar presentations
A Joint Code of Practice Objectives and Summary Presentation
Advertisements

A GIA is a contract between a surety company and a contractor (or subcontractor)/principal. A GIA is a standard, typical document in the construction.
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
Contracts – important issues
Possible Loopholes in the Public Sector Contracts Anthony Hussey.
Contracts of Indemnity & Guarantee
Contract Performance, Breach and Remedies Chapter 9.
Security of Payment workshop Andrew Robertson Important Disclaimer: The material contained in this publication is comment of a general nature only and.
4/28/20151 PRESENTED BY NAKABAGO JOHN CONTRACT MANAGEMENT AND ADMINISTRATION IPPU PRESENTATION JOHN NAKABAGO.
LECTURE 7 CLAIMS RELATED TO SUB-CONTRACTORS
6 th December 2003 Luthra & Luthra Law Offices1 Impact of Force Majeure on Contracts Presentation at the Indian Council of Arbitration By Mohit Saraf Partner.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
Contracts: Third Party Rights, Discharge, Breach and Remedies Chapter 10.
Time for a new standard - AS General Conditions of Contract
Rome II Regulation Conflict rules for torts. Rome II Regulation The Regulation defines: the conflict-of-law rules applicable to non- contractual obligations.
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
Limits on Restoring Plaintiff to Rightful Position – Bargaining out of Rightful Position Default rules – rules a court applies to determine how to restore.
Vienna Convention on the Law of Treaties 1969
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
© 2010 Pearson Education, Inc., publishing as Prentice-Hall 1 REMEDIES FOR BREACH OF TRADITIONAL AND E-CONTRACTS © 2010 Pearson Education, Inc., publishing.
“Lessons Learnt” workshop on 18 th June 2015, Sofia Project Implementation Support Service Agreement (PISSA) TA BG BSF S1 – Procurement & FIDIC.
Breach of Contract and Remedy
Insurance provisions under JCT 1998 and JCT Standard Building Contract 2005 Brian Lewis – QBE CAR.
1 REMEDIES FOR BREACH OF CONTRACT. 2 When one of the parties to the contract makes a breach of the contract the following remedies are available to the.
LUMSA – International Commercial Law November 21, 2014 Prof. Avv. Roberto Pirozzi
About ACE Purpose of ACE ACE exists to represent its members’ interests to clients, both government and private sector, and stakeholder organisations,
1 Hull Claims Protocol 2007 Update. 2 Objective To establish a set of guidelines to promote the efficient handling of hull claims.
PERFORMANCE OF CONTRACT.
The Building and Construction Industry Security of Payment Act 2002 (Vic) made simple Western Suburbs Law Association Tuesday 4 June 2013 Michael Heaton.
1. Barristers’ Cost Disclosure Obligations
Kamal Farouque General Counsel Maurice Blackburn Cashman Employment & Industrial Law Section 25 July 2006 Common Law Industrial Deeds.
Project risk and control. Tender risk Programme and method – Tightness of completion LAD’s Extent of change – Construction method Temporary works Change.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Connolly – International Financial Accounting and Reporting – 4 th Edition CHAPTER 12 CONSTRUCTION CONTRACTS.
Purchasing Supplies at CERN
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
Threshold Concepts in Construction Law: Prevention & Extension in Construction Contracts Brodie McAdam University of Salford
FORMULATION & PRESENTATION OF EOT CLAIMS
Copyright © 2008 Pearson Education Canada9-1 Chapter 9: The End of the Contractual Relationship.
7 Plant, Materials and Workmanship. 7.1Manner of Execution The Contractor shall carry out the manufacture of Plant, the production and manufacture of.
PROFESSIONAL PRACTICE 544 February 16, 2015 Interpretation of Contracts Breach of Contract Remedies for Breach Michael J. Hanahan, Esq. Schiff Hardin LLP.
Chapter 12 Contract Discharge and Remedies for Breach.
Week 2 Termination for Breach Termination for Repudiation Termination for Delay.
April 19, 2001L&L/MDI1 Impact of Force Majeure On Contracts Presentation by Mohit Saraf Partner Luthra & Luthra Law Offices.
Erman Taşkın. Information security aspects of business continuity management Objective: To counteract interruptions to business activities and to protect.
Contract Performance In Traditional and E-Contracts; Breach of Contract and Remedies Chapter 18 & 19.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
By Khalil T. Hasan Construction Solutions ( Joint Operation/Administration of multiple FIDIC Forms – A Case Study.
EU-China Workshop on the Chinese Patent Law 24/25 September 2008 Topic IV: Legal Consequences of Invalidity of a Patent Prof. Dr. Christian Osterrieth.
Building Capacity of SMEs for Participation in Public Procurement Draft Presentation for Training of Trainers June 2014.
Improving Compliance with ISAs Presenters: Al Johnson & Pat Hayle.
1 Details of the Sword Contract Kick-off meeting Autonomous Province of Trento Trento, December 18-19, 2014 SWORD (School and WOrk-Related Dual learning)
Subaward - 2 CFR A formal legal agreement between your institution and another legal entity An award provided by a pass-through entity (PTE) to.
Administration of a FIDIC Contract - Project Control
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Particular Conditions of Contract & Appendix to Tender
Performance of Contract
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
What Small and Emerging Contractors Need to Know Understanding General Agreements of Indemnity © Copyright 2017 NASBP.
Particular Conditions of Contract & Appendix to Tender
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
STRUCTURE OF THE PRESENTATION
Luxembourg Workshop on Space and Satellite Communication Law,
Vienna Convention on the Law of Treaties 1969
Presentation transcript:

Delay, Disruption and Acceleration Contract Management in International Construction Delay, Disruption and Acceleration Michael J.R. Kremer Beijing, April 28, 2009

1. Introduction Time is of essence in basically every construction project Yet, delays of some sort are general rule, rather than the exception Consequence: claims for extension of time, issue of acceleration Therefore, closer look to: What are the obligations as to time in general? When and how does acceleration become relevant? Delay, Disruption and Acceleration · April 2009

2. Contractor‘s obligations as to time Modern construction contracts typically foresee three separate, but inter-related express obligations: First obligation: Contractor to complete works by certain date or within specified period; possibly with stage or sectional completion obligation Second obligation: Contractor to progress the works regularly and diligently Third obligation: Contractor to prepare and work to an accepted program (work schedule) Delay, Disruption and Acceleration · April 2009

2.1 First obligation: specific date/period In case of “period for completion”, identification of “commencement date” as well as periods crucial e.g.: x months from the “Commencement Date” clarification of “days” and “weeks” If no date or period foreseen: obligation to complete “by a reasonable time” Standard form contracts regularly provide for express obligation Delay, Disruption and Acceleration · April 2009

2.1 First obligation: specific date/period (cont’d) Effect of specific date of completion typically no qualification as of the essence clauses for extension of time or liquidated damages prevent such interpretation Specific date of completion of little assistance in management of the project Employer wants to take action early to avoid late completion stage or sectional completion obligations and liquidated damages give only limited recourse Delay, Disruption and Acceleration · April 2009

2.2 Second obligation: “progress regularly” If specific date for completion agreed, no “implied” second obligation Contractor has right to plan, execute and progress the works severe evidential difficulties for Employer Therefore: express obligation (regularly included in standard form contracts) Delay, Disruption and Acceleration · April 2009

2.2 Second obligation: “progress regularly” (cont’d) Effect of express obligation to proceed regularly and diligently “Proceed continuously, industriously and efficiently with appropriate resources so as to progress steadily towards completion substantially in accordance with the contract.” Contractor may not slow down even if ahead in time schedule Employer may have remedy of damages, even if completed in time, if Employer can show “loss” Delay, Disruption and Acceleration · April 2009

2.3 Third obligation: program “program/work schedule” no legal term Requires basic information of activities or operation with a list of dates for commencement and completion of respective activities Types of programs: Bar Chart Network Program Line of Balance Delay, Disruption and Acceleration · April 2009

2.3 Third obligation: program (cont’d) Potential roles of the program: Monitor role: milestone program progress program prediction program Dynamic role management program compensation program Delay, Disruption and Acceleration · April 2009

3. Employer‘s obligations as to time Completion of obligations specified in the contract e.g. supply information, provide material, execution of certain pre-condition works, permits, appointment of engineer etc. at times specified in program or reasonable times with regard to execution of works Typically no obligation to comply with approved program, rather obligation not to hinder Contractor implied obligation not to hinder implied obligation to cooperate Delay, Disruption and Acceleration · April 2009

4. Acceleration What does the term mean? What is the benchmark? Basically, tow situations relating to the overall works: Contractor is required to finish earlier than the contractual date variation of the contract, i.e. constructive order/change order constructive acceleration Contractor is likely to complete later than the contractual completion date acceleration to reduce delays Delay, Disruption and Acceleration · April 2009

4.1 Constructive acceleration typical example for constructive acceleration claim: Equipment procured by Employer from a third-party is delivered late. Contractor’s words are delayed. Contractor applies for Extension of Time (EOT). Interim assessment of the Engineer denies EOT; final review still pending. Employer presses Contractor to increase resources to make up for the delay. Delay, Disruption and Acceleration · April 2009

4.1 Constructive acceleration (cont’d) Contractor‘s stark choice: Continue in hope to prove EOT or “accept” to be in default temporarily and take steps to mitigate Nature of problem: contract’s EOT procedures and contractor’s “temporary default” Conclusion: Constructive acceleration claim presents significant legal difficulties; claim for disruption may be possible with fewer legal difficulties Delay, Disruption and Acceleration · April 2009

4.2 Acceleration to reduce delays The issue of right or obligation to reduce the effect of qualifying delays may arise in three ways: Contractor’s may have right to choose how to deal with a qualifying delay and whether to accelerate or not and to recovery on the basis of this right; Contractor may be entitled to EOT and any associated loss only to the extent that he has mitigated the effect of the delays; Contractor may be under an obligation to progress the works including an express obligation to mitigate delays and the failure to do so prevents remedies of EOT/associated losses. Delay, Disruption and Acceleration · April 2009

4.2 Acceleration to reduce delays (cont’d) Mitigation of delay by acceleration? Contractor reacts to the qualifying delay most contracts provide for EOT provisions and express terms for agreement for acceleration generally no right of contractor to accelerate and recover costs (except if “constructive order”) “reasonabless”-argument Contractor does not react to the qualifying delay Generally no obligation where EOT provisions apply Mitigation by managing delay? obligation to re-plan recourses and activities obligation to progress “regularly & diligently” includes managing of effects of delay Delay, Disruption and Acceleration · April 2009

4.3 Obligation to accelerate? Differentiation by reason for delay: Delay not caused by Contractor, i.e. entitled to EOT no obligation; only by means of separate agreement Delay caused by Contractor: in principle no obligation (discretion of contractor in regard of his own culpable delay) contract may provide power to order Contractor to adopt acceleration measures “Indirect” obligation Contractor must weigh costs of acceleration, chance of recovery against liquidated damages potentially levied against him Delay, Disruption and Acceleration · April 2009

4.4 Entitlement to acceleration Contractor may perceive commercial advantage to accelerate; generally only bound by completion date Generally no obligation of the Employer to co-operate Exception: entitlement of acceleration provided in the contract and bound to program Delay, Disruption and Acceleration · April 2009

5. Conclusion Time is of the essence in construction projects The effort of planning, negotiating and drafting does not end at providing sophisticated terms for the event of delays by finding a realistic completion date, incorporating EOT provisions and delay related liquidated damages Instead, the same though and sophistication should be put in addressing delays in terms of acceleration, rather than only dealing with them in terms of EOT and liquidated damages. Delay, Disruption and Acceleration · April 2009

Delay, Disruption and Acceleration Contract Management in International Construction Beijing, April 28, 2009 Delay, Disruption and Acceleration www.cliffordchance.com Clifford Chance, Königsallee 59, 40215 Düsseldorf, Germany © Clifford Chance 2009 Clifford Chance Partnerschaftsgesellschaft von Rechtsanwälten, Wirtschaftsprüfern, Steuerberatern und Solicitors · Sitz: Frankfurt am Main · AG Frankfurt am Main PR 1000 #960898