F Shot Engineering Accelerator Advisory Committee Elvin Harms Fermilab Beams Division 13 May 2002.

Slides:



Advertisements
Similar presentations
Tevatron Beam Diagnostics: Boosting Collider Performance Vladimir Shiltsev, Ron Moore, Andreas Jansson FNAL/Accelerator Division.
Advertisements

1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Run II Status and Prospects - Spalding1 Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004.
Chapter 1 and 2 Computer System and Operating System Overview
F UEC - 6 Oct 06 Recent FNAL Collider Operations Ron Moore Fermilab – Tevatron Dept.
Vaia Papadimitriou The Supertable (Introducing Supertable II) Run II meeting September 2, 2004 Timofei Bolshakov and Vaia Papadimitriou.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Proton Plans at Fermilab Robert Zwaska - Fermilab Science and Engineering at Henderson- DUSEL Capstone Workshop Stony Brook University May 5, 2006 Outline.
Antiproton Source Capabilities and Issues Keith Gollwitzer & Valeri Lebedev Accelerator Division Fermilab 1.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
INTRODUCTION  RECYCLER BPM – Original system not adequate to measure beam position precisely. It is being upgraded to meet the required physics precision.
Recycler Status and Plans Shekhar Mishra MID/Beams Division Fermilab AAC Review 2/4/03 Introduction to the Recycler Ring Recycler Improvements and status.
F Antiproton Source Apertures Steve Werkema DOE Tevatron Operations Review March 22, 2006.
Overview Run-6 - RHIC Vadim Ptitsyn C-AD, BNL. V.Ptitsyn RHIC Spin Workshop 2006 RHIC Run-6 Timeline  1 Feb – Start of the Run-6. Start of the cooldown.
Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
A Monte Carlo Model of Tevatron Operations Elliott McCrory Fermilab/Accelerator Division 13 October 2005.
F All Experimenters' Mtg - 28 Jul 03 Week in Review: 07/21/03 –07/28/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
F 19 August 2002 All Experimenters Meeting Beams Week in Review Continued to work on providing Luminosity L  N p N a /  –Stacking rate –Coalescing efficiency.
Jean Slaughter -Feb 24, 2004 Shot Data Responsible for physics analysis of shot data Oversees the development of shot data analysis tools Responsible for.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
1 Tunnel implementations (laser straight) Central Injector complex.
Dmitri Denisov D0 Weekly Summary: August 18 to August 24  Delivered Luminosity and operating efficiency u Delivered 6.9pb -1 u Recorded 6.0pb -1 (87%)
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Run II Operational Status and Plans Run II Meeting October 28, 2004 Dave McGinnis.
PIP Status Report Linac Startup plans 12/05/2012.
Jean Slaughter –April 5, 2004 – all experimenters’ meeting Purposes of SDA Store to store monitoring of performance Long term trends Analysis of specific.
Check lists to mouse clicks Automation Session : WAO The Fermi National Accelerator Laboratory is a U.S. Department of Energy (DOE) research laboratory,
All Experimenters' Mtg - Aug. 04, 2003 Week in Review: 07/28/03 –08/03/03 Doug Moehs – FNAL Stores and Operations Summary Standard Plots.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
October 2002 Jean Slaughter SDA – Shot Data Analysis Outline Description of SDA Examples Plans for 2003 SDA is a system for acquiring and analyzing data.
S. Pordes - to part of CD 09/10/031 Introduction to some Beams Division jargon in some order…see how far we get:
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
D. Still-FNAL/Tevatron HALO '03 Tevatron Collider II Halo Removal System Dean Still Fermilab Tevatron Department 5/21/2003 Motives for the Collider Run.
F All Experimenters' Mtg - 03 Mar 03 Week in Review: 02/24/03 –03/02/03 Ron Moore – FNAL Store Summary / What went wrong Tev Studies Highlights Tev Ground.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
AP2 Line & Debuncher Studies Status Keith Gollwitzer Antiproton Source January 9, 2006 Many people involved with providing the hardware and software that.
PIP Status Report Linac Startup plans 12/05/2012.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Recent Work Towards Increasing the AP2 & Debuncher Aperture – Keith Gollwitzer – May 9, Recent Work Towards Increasing the AP2 & Debuncher Aperture.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status January 2006 Pushpa Bhat.
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Status of the AP2 Optics Keith Gollwitzer Antiproton Source Department November 19, 2004.
9/2/2003Tev BPM requirements1 Tevatron BPM and BLM requirements Mike Martens.
A Monte Carlo Model of Tevatron Collider Operations Elliott McCrory, BD/(Linac & Integration) 4, 5 December 2003 A phenomenological model of Tevatron Collider.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
F A Fermilab Roadmap Dave McGinnis May 28, f Fermilab Roadmap - McGinnis Timelines  Divide the road map into three parallel paths  ILC - Energy.
All Experimenters MeetingDmitri Denisov Week of December 23 to December 30 D0 Summary  Delivered luminosity and data taking efficiency u Delivered: 5.8pb.
F Record luminosities at the Tevatron & Future potentiality Steve Werkema Fermi National Accelerator Laboratory Batavia, Illinois USA Asian Particle Accelerator.
F All Experimenters' Mtg - 24 Feb 03 Week in Review: 02/17/03 –02/23/03 Ron Moore – FNAL Store Summary Failed Tev dipole disassembly Schedule for Week.
Robert R. Wilson Prize Talk John Peoples April APS Meeting: February 14,
F HCP 2007 Performance and Future of the Tevatron Ron Moore Fermilab - Tevatron Dept. Tevatron overview and performance Antiproton source + Recycler overview.
12/16/03Tev BPM requirements1 Tevatron BPM requirements Mike Martens.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
F All Experimenters' Mtg - 6 Jan 03 Week in Review: 12/30/02 –1/05/03 Ron Moore – FNAL Store Summary – Best week! > 7 pb -1 Machine Studies/Maintenance.
Guy Crockford, BE/OP/LHC, CERN WAO 2012 Automation in the SPS and LHC and its effect on operator skills The past 20 years have seen great advances in the.
Run II Status Keith Gollwitzer Temple Review July 1, 2003.
Projects, Tools and Engineering Patricia McBride Computing Division Fermilab March 17, 2004.
Tevatron Beam Position Monitor Upgrade Stephen Wolbers (for the Tevatron BPM Upgrade Project) PAC05, Knoxville, TN May 16-20, 2005.
Cons Gattuso 2/23/10 Status/Changes to Pbar Transfer Program.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
MAC meeting (12-13 January 2010) Machine Advisory Committee participants: B.Sharkov (ITEP/FAIR) P.Belochitskii (CERN) S.Ivanov (IHEP, Protvino) M.Steck.
Friday, Feb 12, 2010 Accelerator Status1 Accelerator Week in Review Part I: Regular 9am Scheduling Meeting –Crew Chief Summary –24 hour machine summaries.
Pre-Meeting Meeting Brian Drendel Accelerator Shift Plot.
SDA- Shot Data Analysis Jean Slaughter DOE Review July 21, 2003.
Changes in delivered luminosity by varying the store length, using the luminosity projection model described in in Beams-doc-2022 Vaia Papadimitriou 30.
Turnaround time in modern hadron colliders & store-length optimization
Chapter 1 Introduction(1.1)
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Presentation transcript:

f Shot Engineering Accelerator Advisory Committee Elvin Harms Fermilab Beams Division 13 May 2002

f 13 May 02 AAC E. Harms 2 Shot Engineering Introduction Planning & Scheduling Statistics Shot Set Up Analysis/SDA Summary

f 13 May 02 AAC E. Harms 3 Introduction Integrated Luminosity –31pb -1 since last meeting Peak Luminosity –Dec 01: 7.6 E30 –Now: 19.6 E30 Store Reliability –114 stores since 12/12/01 –93 terminated intentionally: 81%

f 13 May 02 AAC E. Harms 4 Planning & Scheduling Collider Operation is our priority Up to 5 shifts per week for Collider studies –Dedicated Tevatron –Dedicated Pbar source –Studies pbars to Tevatron –Other machines as conditions permit Parasitic studies during remainder of week Recycler commissioning –Protons and Pbars MiniBooNe beam commissioning Shutdowns as jobs accumulate or component failure

f 13 May 02 AAC E. Harms 5 Operations – Scheduling Typical Schedule

f 13 May 02 AAC E. Harms 6 Operations - Planning 0900 meetings Monday, Wednesday, Friday –Review of performance –Set short-term schedule Department meetings –Topics of interest –Studies de-briefing –Studies planning Monday 1030 Studies Planning meeting –Input from systems departments –Integrate dedicated and parasitic studies –Prepare schedule for next week Thursday meeting –Run IIa topic –Shot analysis

f 13 May 02 AAC E. Harms 7 Statistics Store time Downtime Set-up time Compiled since last meeting –12 December 01 through 10 May 02

f 13 May 02 AAC E. Harms 8 Statistics – Store time On average, 71 hours in store per week, 42.5% of week Peak is 110 hours

f 13 May 02 AAC E. Harms 9 Statistics - Downtime On average, 45 hours, 26% of time each week, is accrued as downtime –On average, 8% of each week is downtime due to a failure –On average, 8% of each week is downtime identified as a scheduled shutdown –Experimenter-requested accesses are not considered shutdowns, usually ‘miscellaneous’ Convening a reliability group

f 13 May 02 AAC E. Harms 10 Statistics – Set-Up time Three hour shot set- ups are the average Two-hour set-ups recently 1-1/2 hours has been achieved and should be routine Identifying ‘slow’ steps Refining set-up technique Identify a realistic short-term goal

f 13 May 02 AAC E. Harms 11 Shot Set-Up Description Tools Recent Progress and Improvements

f 13 May 02 AAC E. Harms 12 Shot Set-Up – Description Tevatron Proton source Main Injector Recycler Antiproton source

f 13 May 02 AAC E. Harms 13 Shot Set-Up – Description TevatronMain InjectorPbar source Terminate store & Return to 150 GeV Check/correct closed orbitCool Pbars into core & maintain stability Verify/correct A150 line tune Set tunes & chromaticities Check/correct extraction positions Optimize protons Accept reverse protons, maximize transmission from MI, minimize injection oscillations Load protonsProvide protons for tuneup of beam lines Orient Accumulator for unstacking

f 13 May 02 AAC E. Harms 14 Shot Set-Up – Description Tevatron Proton source Main Injector Recycler Antiproton source AP3 P2 P1 AP1 A1 MI-8

f 13 May 02 AAC E. Harms 15 Shot Set-Up – Tools Manpower –MCR crews are fully integrated –Cross-training continues –Machine experts present much of the time for dedicated tasks and monitoring Software –Sequencers –State devices –Specialized applications

f 13 May 02 AAC E. Harms 16 Shot Set-Up – Recent Progress Improved Accumulator to MI beam lines lattice match Revised Unstacking Scheme Pbar transfers to both Tevatron and Recycler in same shot set-up Tevatron tunes and chromaticity setting at 150 GeV MI coalescing improvements

f 13 May 02 AAC E. Harms 17 Shot Set-Up – Improvements Decrease turn-around time –Track length of setup steps –Identify steps of concern –Apply fixes –Ongoing exercise Beam line tuning reproducibility Tevatron octupole tune-up Proton pulse to pulse stability Pbars requested vs. unstacked Optimization of input parameters –MCR specification sheet Close the loop –Use previous stores to improve on future ones –SDA

f 13 May 02 AAC E. Harms 18 Shot Analysis/SDA Introduction Data Status

f 13 May 02 AAC E. Harms 19 Shot Analysis/SDA - Introduction SDA – The Shot Data Analysis (SDA) products are a set of complementary tools and application libraries intended for off-line studies of the Tevatron complex performance during RunII. Beam Physicists and Engineers can access the shot data from their workstations, using either a collection of Java-Based or Web based applications to plot and export flat data table (ASCII text) to other packages for further studies. We believe that this remote access and analysis of the beam data will be essential optimize and fine-tune our accelerators for RunII. This can only be accomplished via extensive studies of post-mortem dumps of the data, trending over significant periods, selection of particularly successful stores and so forth.

f 13 May 02 AAC E. Harms 20 Shot Analysis/SDA - Introduction SDA Main Tools –SDA Editor to add, edit, delete input devices Devices can be sampled over time to generate time plot data Devices can be sampled on single ‘event’ to generate scalar data –SDA Viewer to view scalar data information Given most attention to date –Plot Viewer to view plottable data Needs more attention Off-line Analysis tools –data saved into ‘Shots’ and Tevatron electronic log books –true off-line tools under development

f 13 May 02 AAC E. Harms 21 Shot Analysis/SDA – Scalar Data Sample Scalar data view for Pbars

f 13 May 02 AAC E. Harms 22 Shot Analysis/SDA – Summary Report Shot Summary, store 1303, Wed May 08 21:22:02 CDT 2002, Initial Stack Size = E10 Proton Intensity E9 Step Efficiency % Cumulative Efficiency % Pbar Intensity E9 Step Efficiency % Cumulative Efficiency % Accumulator AP AP P P MI Inj MI 8Gev MI 150Gev Coalescing Inject Protons Pbar Injection porch Inject Pbars Before Ramp Flattop Squeeze Initiate Collisions Remove Halo HEP Initial Luminosity20.24CDF18.61DZero Shot Setup Time135.22min

f 13 May 02 AAC E. Harms 23 Shot Analysis/SDA – Plots Shot Summary, store 1303, Wed May 08 21:22:02 CDT 2002, Initial Stack Size = E10 Protons – 10 recent storesPbars – 10 recent stores

f 13 May 02 AAC E. Harms 24 Shot Analysis/SDA - Status Recent influx of manpower Bi-weekly infrastructure meetings/action list Generating useful data, but not complete Software platform stabilizing Hardware fairly stable Analysis in progress/just beginning Instrumentation needs work in some areas Need to build a larger user base

f 13 May 02 AAC E. Harms 25 Shot Engineering - Summary Luminosity performance is improving Planning/scheduling –Mature –Flexibility is needed Reliability –Good –Needs proactive attention Shot Set-Up –Technique is mature –Evolving as necessary –Needs to go faster Shot analysis –Toddler stage –Tools maturing –Getting serious about analysis