Module 7 Session 7.2 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.2 Scheduling and allocating resources with CPM.

Slides:



Advertisements
Similar presentations
Chapter 7 Project Management
Advertisements

CP Chapter 4 Schedule Planning.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Estimating, scheduling and budgeting
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
 Chapter 6: Activity Planning – Part 1 NET481: Project Management Afnan Albahli.
Chapter 3 Managing the Information Systems Project
© 2005 by Prentice Hall Chapter 3 Managing the Information Systems Project Modern Systems Analysis and Design Fourth Edition Jeffrey A. Hoffer Joey F.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Critical Path and Gantt
© 2008 by Prentice Hall 3-1 ITCS311 Systems Analysis and Design Dr. Taher Homeed Feb 2010 Department of Computer Science College of IT University of Bahrain.
Creating the Project Plan
Manjari Akella Pranava Nagpal B-Tech(CSE) 4 th Year.
Copyright 2008 Introduction to Project Management, Second Edition 1  Project time management involves the processes required to ensure timely completion.
BSBPMG503A Manage Project Time 6.5 Develop Schedule The process of analysing activity sequences, durations, resource requirements and schedule constraints.
PROJECT TIME CONTROL. PROJECT SCHEDULING REFERENCES PRIMARY REFERENCE IN THIS PRESENTATION IS Operations Management, Ed 6, Heizer & Render, Prentice Hall,
5/18/2015 L. K. Gaafar PROJECT MANAGEMENT Time Management* Dr. L. K. Gaafar The American University in Cairo * This Presentation is Based on information.
Importance of Project Schedules
Chapter 3 Managing the Information Systems Project
Roberta Russell & Bernard W. Taylor, III
Project Time Management
Project Time Management
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Prepared by: Michael Palazzo
Project Management Chapter 13 OPS 370. Projects Project Management Five Phases 1. Initiation 2. Planning 3. Execution 4. Control 5. Closure.
© 2006 ITT Educational Services Inc. System Analysis for Software Engineers: Unit 5 Slide 1 Chapter 3 Managing the Information Systems Project.
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
© 2005 by Prentice Hall 3-1 Chapter 3 Managing the Information Systems Project Modern Systems Analysis and Design Fourth Edition.
 Probably the most time-consuming project management activity.  Continuous activity - Plans must be regularly revised.  Various different types of.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT /
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Software Project Management
1 Teamwork Skills and Project Management 1. Teamwork Skills.
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
T.L. Martin & Associates Copyright © 2008 Chapter 1 Fundamentals of Scheduling T.L. Martin & Associates, Inc Office Park Drive Gaithersburg, Maryland.
Module 11 Session 11.1 Visual 1 Module 11 Executing and Controlling the Work Session 11.1 Managing Execution: Executing and Controlling the Work.
Managing Resources Program Evaluation and Review Technique (PERT) Production Process.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
 Delay in project implementation invariably results in cost- overrun.  Delayed project implementation means delay in getting return on investments made.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Fundamentals of Project Control Chapter 11 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
Tools to Help  Product flow Dependencies and relationships of deliverables  Work breakdown structure The parts  PERT charts Program Evaluation and.
Project Management MGT 30725
Project Management: PERT/CPM
Project Planning and Implementation
Chapter 5: Project Time Management Doddy Prayogo, Ph.D.
REQUIREMENTS Project management tools
Project Planning and Scheduling
PROJECT MANAGEMENT WITH CPM/PERT.
Project Time Management
Project Time Management
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
REQUIREMENTS Project management tools
Presentation transcript:

Module 7 Session 7.2 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.2 Scheduling and allocating resources with CPM

Module 7 Session 7.2 Visual 2 Instructional Objective Schedule activities and resources, shorten duration, and control the project by measuring progress against plan

Module 7 Session 7.2 Visual 3 Tasks for managing plans  Scheduling activities  Allocating resources  Meeting required dates  Allowing for risk  Getting management approval  Monitoring progress vs. plan (control)  Reporting  Rescheduling and updating  Detailed plan  Master summary plan

Module 7 Session 7.2 Visual 4 G 1 Early start schedule B4F2 C Weeks D 1 E 1 ::: : A 1

Module 7 Session 7.2 Visual 5 Scheduled start - Leveled resource A B4F2 1 C 1 G Weeks D 1 E 1 ::: :

Module 7 Session 7.2 Visual DAYS MAN HISTOGRAM DAYS JOB D 4 MEN FLOAT JOB A 4 MEN JOB E 3 MEN JOB A 2 MEN FLOAT JOB B 2 MEN JOB F 4 MEN FLOAT JOB C 4 MEN JOB G 2 MENJOB J 3 MENJOB K 2 MEN JOB L 6 MEN JOB M 3 MEN FLOAT MEN

Module 7 Session 7.2 Visual 7 Resource histogram: Early start with overload DAYS Men required Men available Overload (a) Earliest start schedule MEN

Module 7 Session 7.2 Visual 8 Resource histogram: Late start schedule DAYS Men required Men available Overload (b) Latest start schedule

Module 7 Session 7.2 Visual DAYS JOB A 4 MEN JOB E 3 MEN JOB H 2 MENFLOAT JOB B 2 MEN JOB F 4 MEN FLOAT JOB C 4 MEN JOB G 2 MENJOB J 3 MENJOB K 2 MEN JOB M 3 MEN FLOAT JOB D 4 MEN FLOAT JOB A 4 MEN JOB E 3 MEN JOB H 2 MEN FLOAT JOB B 2 MEN JOB F 4 MEN FLOAT JOB C 4 MEN JOB G 2 MEN JOB J 3 MENJOB K 2 MEN JOB L 6 MEN JOB M 3 MEN FLOAT Best schedule Early start schedule JOB L 6 MEN Note: D and H now critical JOB D 4 MEN FLOAT

Module 7 Session 7.2 Visual 10 Histogram: Resource loading for best schedule MEN MAN HISTOGRAM Men required DAYS

Module 7 Session 7.2 Visual 11 Scheduling criteria 1. Resource allocation (leveling) 2. Cost and cash flow 3. Risk 4. Outside factors (weather)

Module 7 Session 7.2 Visual 12 Early versus late start schedule A B 4 F2 1 C1 G Weeks D1 E1 ::: :

Module 7 Session 7.2 Visual 13 Time compression (Crashing the schedule)  What ?  Why ?

Module 7 Session 7.2 Visual 14 Time compression alternatives 1. Add resources (people, money) 2. Change logic 3. Change objective 4. Change methods 5. Reduce time estimates

Module 7 Session 7.2 Visual 15 Time compression (Crashing) A B4F2 1 C1 G Weeks D1 E1 ::: :

Module 7 Session 7.2 Visual 16 Time compression alternatives 1. Add resources (people, money) 2. Change logic 3. Change objective 4. Change methods 5. Reduce time estimates

Module 7 Session 7.2 Visual 17 Change logic sequence A B A B Save 3 weeks

Module 7 Session 7.2 Visual 18 Lead-lag relationship Foundation Structural steel Foundation 30% or 2 week delay 70%

Module 7 Session 7.2 Visual 19 In sequencing do not mix logic and resources Instant coffee project Resource scheduling problem, not logical constraint Get sugar bowl Wrong Get sugar bowl Get coffee jar Right Get coffee jar

Module 7 Session 7.2 Visual 20 Risk  Dealing with uncertainty  Making assumptions about the future

Module 7 Session 7.2 Visual 21 Dealing with risk Longest + (4. most likely) + shortest 6 Expected time = PERT uses probability model with 3 estimates Bell shaped curve

Module 7 Session 7.2 Visual 22 Identify activities with high probability of delay Plan Risk Add extra time based on best collective judgment 4 2

Module 7 Session 7.2 Visual 23 Fast-track management decisions Normal Management approves budget of 40,000 for prototype Build 6 months Test 6 months Design Phase Prototype Phase Manufacturing Phase Start up manufact. 12 months Months Tooling Procure parts Management decisions 6 months 2 years Management approves budget of 10,000 for tooling plus 100,000 for manufacturing

Module 7 Session 7.2 Visual 24 6 months Accelerated Build 6 months Test 6 months Design Phase Prototype Phase Manufacturing Phase Months Procure parts Management decisions 1.5 years Save 6 months Fast-track management decisions Management approves budget of 40,000 for prototype plus 10,000 for tooling Start up manufact. Tooling 6 months Management approves budget of 100,000 manufacturing 12 months

Module 7 Session 7.2 Visual 25 Time compression alternatives 1. Add resources (people, money) 2. Change logic 3. Change objective 4. Change methods 5. Reduce time estimates

Module 7 Session 7.2 Visual 26 Control  Measuring progress versus plan

Module 7 Session 7.2 Visual 27 Control = measuring progress versus plan A B4F2 1 C1 G Weeks D1 E1 ::: : TODAY

Module 7 Session 7.2 Visual 28 Reporting and control  Monitor progress  Revise schedule  Pay attention to human element

Module 7 Session 7.2 Visual 29 Tasks for managing plans  Scheduling activities  Allocating resources  Meeting required dates  Allowing for risk  Getting management approval  Monitoring progress vs. plan (control)  Reporting  Rescheduling and updating  Detailed plan  Master summary plan