Module 7 Session 7.2 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.2 Scheduling and allocating resources with CPM
Module 7 Session 7.2 Visual 2 Instructional Objective Schedule activities and resources, shorten duration, and control the project by measuring progress against plan
Module 7 Session 7.2 Visual 3 Tasks for managing plans Scheduling activities Allocating resources Meeting required dates Allowing for risk Getting management approval Monitoring progress vs. plan (control) Reporting Rescheduling and updating Detailed plan Master summary plan
Module 7 Session 7.2 Visual 4 G 1 Early start schedule B4F2 C Weeks D 1 E 1 ::: : A 1
Module 7 Session 7.2 Visual 5 Scheduled start - Leveled resource A B4F2 1 C 1 G Weeks D 1 E 1 ::: :
Module 7 Session 7.2 Visual DAYS MAN HISTOGRAM DAYS JOB D 4 MEN FLOAT JOB A 4 MEN JOB E 3 MEN JOB A 2 MEN FLOAT JOB B 2 MEN JOB F 4 MEN FLOAT JOB C 4 MEN JOB G 2 MENJOB J 3 MENJOB K 2 MEN JOB L 6 MEN JOB M 3 MEN FLOAT MEN
Module 7 Session 7.2 Visual 7 Resource histogram: Early start with overload DAYS Men required Men available Overload (a) Earliest start schedule MEN
Module 7 Session 7.2 Visual 8 Resource histogram: Late start schedule DAYS Men required Men available Overload (b) Latest start schedule
Module 7 Session 7.2 Visual DAYS JOB A 4 MEN JOB E 3 MEN JOB H 2 MENFLOAT JOB B 2 MEN JOB F 4 MEN FLOAT JOB C 4 MEN JOB G 2 MENJOB J 3 MENJOB K 2 MEN JOB M 3 MEN FLOAT JOB D 4 MEN FLOAT JOB A 4 MEN JOB E 3 MEN JOB H 2 MEN FLOAT JOB B 2 MEN JOB F 4 MEN FLOAT JOB C 4 MEN JOB G 2 MEN JOB J 3 MENJOB K 2 MEN JOB L 6 MEN JOB M 3 MEN FLOAT Best schedule Early start schedule JOB L 6 MEN Note: D and H now critical JOB D 4 MEN FLOAT
Module 7 Session 7.2 Visual 10 Histogram: Resource loading for best schedule MEN MAN HISTOGRAM Men required DAYS
Module 7 Session 7.2 Visual 11 Scheduling criteria 1. Resource allocation (leveling) 2. Cost and cash flow 3. Risk 4. Outside factors (weather)
Module 7 Session 7.2 Visual 12 Early versus late start schedule A B 4 F2 1 C1 G Weeks D1 E1 ::: :
Module 7 Session 7.2 Visual 13 Time compression (Crashing the schedule) What ? Why ?
Module 7 Session 7.2 Visual 14 Time compression alternatives 1. Add resources (people, money) 2. Change logic 3. Change objective 4. Change methods 5. Reduce time estimates
Module 7 Session 7.2 Visual 15 Time compression (Crashing) A B4F2 1 C1 G Weeks D1 E1 ::: :
Module 7 Session 7.2 Visual 16 Time compression alternatives 1. Add resources (people, money) 2. Change logic 3. Change objective 4. Change methods 5. Reduce time estimates
Module 7 Session 7.2 Visual 17 Change logic sequence A B A B Save 3 weeks
Module 7 Session 7.2 Visual 18 Lead-lag relationship Foundation Structural steel Foundation 30% or 2 week delay 70%
Module 7 Session 7.2 Visual 19 In sequencing do not mix logic and resources Instant coffee project Resource scheduling problem, not logical constraint Get sugar bowl Wrong Get sugar bowl Get coffee jar Right Get coffee jar
Module 7 Session 7.2 Visual 20 Risk Dealing with uncertainty Making assumptions about the future
Module 7 Session 7.2 Visual 21 Dealing with risk Longest + (4. most likely) + shortest 6 Expected time = PERT uses probability model with 3 estimates Bell shaped curve
Module 7 Session 7.2 Visual 22 Identify activities with high probability of delay Plan Risk Add extra time based on best collective judgment 4 2
Module 7 Session 7.2 Visual 23 Fast-track management decisions Normal Management approves budget of 40,000 for prototype Build 6 months Test 6 months Design Phase Prototype Phase Manufacturing Phase Start up manufact. 12 months Months Tooling Procure parts Management decisions 6 months 2 years Management approves budget of 10,000 for tooling plus 100,000 for manufacturing
Module 7 Session 7.2 Visual 24 6 months Accelerated Build 6 months Test 6 months Design Phase Prototype Phase Manufacturing Phase Months Procure parts Management decisions 1.5 years Save 6 months Fast-track management decisions Management approves budget of 40,000 for prototype plus 10,000 for tooling Start up manufact. Tooling 6 months Management approves budget of 100,000 manufacturing 12 months
Module 7 Session 7.2 Visual 25 Time compression alternatives 1. Add resources (people, money) 2. Change logic 3. Change objective 4. Change methods 5. Reduce time estimates
Module 7 Session 7.2 Visual 26 Control Measuring progress versus plan
Module 7 Session 7.2 Visual 27 Control = measuring progress versus plan A B4F2 1 C1 G Weeks D1 E1 ::: : TODAY
Module 7 Session 7.2 Visual 28 Reporting and control Monitor progress Revise schedule Pay attention to human element
Module 7 Session 7.2 Visual 29 Tasks for managing plans Scheduling activities Allocating resources Meeting required dates Allowing for risk Getting management approval Monitoring progress vs. plan (control) Reporting Rescheduling and updating Detailed plan Master summary plan