THE IDT’S ROLE IN DELIVERY OF SCHOOL INFRASTRUCTURE PRESENTATION TO SELECT COMMITTEE ON PUBLIC SERVICES 25 February 2014 by The Independent Development.

Slides:



Advertisements
Similar presentations
1 Presentation to the Portfolio Committee on Water Affairs and Forestry and Select Committee on Land and Environmental Affairs 2005 Department of Water.
Advertisements

BUCKET ERADICATION PROGRESS SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS 22 & 23 February 2007 Presented by Ms. T. Mpotulo Department of.
ERADICATION OF MUD AND OTHER INAPPROPRIATE SCHOOL STRUCTURES PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICES 24 APRIL 2012 by The Independent Development.
SIP 18 WATER AND SANITATION MASTER PLAN Water and Sanitation Master Plan NDHS and DWA Water & Sanitation Master Plan.
Presentation to Select Committee on Public Services Briefing on Unproclaimed Roads and Road Maintenance Budgets 14 th August
Important considerations & contributions of flourishing shipbuilding industries in Bangladesh Khairul Hassan Doctoral student Maritime Engineering, Kyushu.
1 DEPARTMENT OF SOCIAL DEVELOPMENT PRESENTATION TO THE SELECT COMMITTEE ON FINANCE ON THE PROVINCIAL BUDGETS & EXPENDITURE REVIEW 14 NOVEMBER 2006.
BRIEFING ON NATIONAL SCHOOL NUTRITION PROGRAMME PORTFOLIO COMMITTEE ON EDUCATION 15 MAY 2007.
The Portfolio Committee on Sport & Recreation Briefing by the NLC on status of distributing activities 11 August 2015.
FET Colleges Finances and Financial Aid Scheme 20 February 2007.
ECONOMIC GROWTH & ENHANCED LOCAL PARTICIPATION THROUGH INFRASTRUCTURE DEVELOPMENT INTEGRATING INFRASTRUCTURE DELIVERY TOWARDS 2030 CJ Venter 05 October.
EPWP 31 October 2013 Vic van Vuuren. ILO ILO Started 1919 First specialised unit of the UN in 1946 Only tripartite UN agency  Role of the trade unions.
Department of Arts and Culture Presentation to the Select Committee on Appropriations: 08 May 2013 Community Library Services Grant Mr Sibusiso Xaba Director.
Province of the EASTERN CAPE Department of Roads & Transport “Quality Service Delivery through Transportation Excellence” Report on Conditional Grants.
ERADICATION OF MUD AND OTHER INAPPROPRIATE SCHOOL STRUCTURES PRESENTATION TO PUBLIC WORKS PORTFOLIO COMMITTEE 14 JUNE 2011 by The Independent Development.
Eradication of Mud Schools and other Inappropriate Structures Presentation to Portfolio Committee 22 September 2008.
Technical Secondary Schools Recapitalisation Grant Framework – 2011/12 Interim Report - 31 March 2012 Conditional Grant, Division of Revenue Act, 2011,
1 2009/10 DIVISION OF REVENUE BILL Presentation to Select Committee on Finance 24 February 2009.
Department of Arts and Culture Presentation to the Select Committee on Appropriations: 05 June 2012 Community Library Services Grant Mr Sibusiso Xaba Director.
Trends in Intergovernmental Finances: 2000/01 – 2006/07 Agriculture & Land Aditi Maheshwari National Treasury 06 October 2004.
20 FEBRUARY 2013 STANDING COMMITTEE ON APPROPRIATIONS (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)) 1.
MASIBAMBANE CO-ORDINATING COMMITTEE MEETING PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 22 nd JUNE 2012 MASIBAMBANE CO-ORDINATING.
Programme 4: Housing Development Finance Purpose: Fund national housing and human settlement development programmes in terms of the Housing Act (1997),
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE OVERVIEW OF THE NDPW PRESENTED BY THE TOP MANAGEMENT COMMITTEE 26 MAY 2004.
1. PRESENTATION TO SELECT COMMITTEE ON ECONOMIC DEVELOPMENT OF DMR 2010 / 11 ANNUAL REPORT 15 NOVEMBER 2011 Programme 4: Mineral Policy & Promotion 2.
RECAPITALIZATION AND DEVELOPMENT PROGRAMME (RADP): PRESENTATION TO THE SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS 22 MAY 2013.
Themba Wakashe Director - General Department of Arts and Culture 2009 / 10 DIVISION OF REVENUE BILL PRESENTATION TO SELECT COMMITTEE ON FINANCE NCOP 3.
EPWP INFRASTRUCTURE PERFORMANCE INCENTIVE GRANTS TO PROVINCES AND MUNICIPALITIES Standing Committee on Appropriations and Portfolio Committee on Public.
DEPARTMENT OF EDUCATION EDUCATION INFRASTRUCTURE PROGRAMME OF ACTION Portfolio Committee Presentation Cape Town 15 February 2005.
SCHOOL SPORT PRESENTATION TO PORTFOLIO COMMITTEE 27 JULY 2010.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
Integrated National Electrification Programme (INEP): Overall Performance (End of January 2012) Dr Wolsey Barnard.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
Hospital Revitalisation Joint Budget Committee 23 May 2005.
1 Financing Tourism Development Owen Willcox | Chief Director: Economic Services, National Treasury 31 March 2015.
1 Local Government Budgets and Expenditure Review 2001/02 – 2007/08.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
EDUCATION CONDITIONAL GRANTS Quarter One: 2010/11.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
Presentation to the Portfolio Committee on Provincial & Local Government Branch: Free Basic Services and Infrastructure Mr Yusuf Patel 19 ~ 20 February.
1 Overview The Expanded Public Works Programme (EPWP) 17 Aug 2010 EPWP incentive update for Select Committee on Public Services.
1 Select Committee on Economic Development Progress relating to the implementation of Integrated National Electrification Programme (INEP)
Green Concrete 1 1.
1 Reporting on Conditional Grants Presentation to Portfolio Committee 19 February 2007.
Expanded Public Works Programme Current Status PORTFOLIO COMMITTEE ON PUBLIC WORKS SEPT 2009 Period (1 April 2009 – 30 June 2009)
Presentation to the Health Portfolio Committee Presentation to Health Portfolio Committee Free State Department of Health 15 APRIL 2003.
Financial and Fiscal Commission
Coceko BJ Pakade, CEO: IDT; and Joe Odhiambo, CEO: ASA
Presentation to the Portfolio Committee on Energy
BUDGET OVERVIEW Total budget for 2014/15 is R33,9 billion growing at an average of 9,3% to R39,4 billion over the MTEF; Of this R30,1 billion or 88,7%
TRANSPORT PORTFOLIO COMMITTEE: BRIEFING ON THE ROAD MAINTENANCE FUNDING PLAN 02 November 2010.
15 April 2016 Public works sector focus areas audit outcomes Presentation to the Standing Committee on Appropriations 15 April 2016.
SELECT COMMITTEE ON PUBLIC SERVICE: REPORT ON QUALITY SANITATION TO HOUSEHOLDS PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP)
Provincial Budgets and Expenditure as at 31 December /08 Financial Year PUBLIC WORKS, ROADS AND TRANSPORT SCOF (NCOP) Hearings Presented by:
Expanded Public Works Programme (EPWP) for the Social Sector – Conditional Grant Presentation to the Select Committee on Appropriations | National.
Portfolio Committee on Education National Assembly
1st QUARTER CONDITIONAL GRANTS SPENDING
Monitoring Structures & Processes to ensure that the pothole reparation project across the 9 Provinces has the necessary delivery impact" 02 August.
Basic Education Supplementary Presentation: National &Provincial Education Expenditure Trends and Projections Presentation by Dept of Basic Education to.
Select Committee on Appropriations Dinaledi Schools Grant, 3rd and 4th quarter Expenditure /13 Presenter: Edgar Sishi | Chief Director – Provincial.
Portfolio Committee on Health Parliament
PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL.
SCHOOL INFRASTRUCTURE
EPWP PROGRESS REPORT TO PORTFOLIO COMMITTEE ON PUBLIC WORKS
Report on Conditional Grants
EPWP Incentive Grant 4th Quarter 2009/10 performance 18th May 2010
Select Committee on Finance National Council of Provinces
Presentation to the Select Committee on Appropriations Conditional Grants Expenditure as at 31 December 2009 NATIONAL TREASURY 20 April 2010.
1st QUARTER CONDITIONAL GRANTS SPENDING: LAND CARE PROGRAMME GRANT
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Presentation transcript:

THE IDT’S ROLE IN DELIVERY OF SCHOOL INFRASTRUCTURE PRESENTATION TO SELECT COMMITTEE ON PUBLIC SERVICES 25 February 2014 by The Independent Development Trust

Outline of Presentation History of IDT’s participation in the delivery of School Infrastructure IDT Service Delivery Model IDT School Infrastructure over the last 5 years Current IDT School Infrastructure Programmes IDT Participation in SIP 13 Alternative Construction Methods Financial overview Conclusion History of IDT’s participation in the delivery of School Infrastructure IDT Service Delivery Model IDT School Infrastructure over the last 5 years Current IDT School Infrastructure Programmes IDT Participation in SIP 13 Alternative Construction Methods Financial overview Conclusion

History of IDT’s participation in the Delivery of School Infrastructure Participation in the Public Works funded programme for urgent school construction using alternative construction technologies: Participation in the National Eradication of Mud Schools and Inappropriate Structures Programme funded by the National Treasury (Provincial Grants): MTEF Period An IDT funded programme in which IDT contributed Programme Management expertise as well as R150m for actual school infrastructure: Participation in the Provincial school-building programme funded through the Infrastructure Grant to Provinces (IGP): 2000 – 2014 and the DBE ASIDI programme 2011/12 – 2013/14 Participation in the Public Works funded programme for urgent school construction using alternative construction technologies: Participation in the National Eradication of Mud Schools and Inappropriate Structures Programme funded by the National Treasury (Provincial Grants): MTEF Period An IDT funded programme in which IDT contributed Programme Management expertise as well as R150m for actual school infrastructure: Participation in the Provincial school-building programme funded through the Infrastructure Grant to Provinces (IGP): 2000 – 2014 and the DBE ASIDI programme 2011/12 – 2013/14

IDT Service Delivery Model (Infrastructure Orientated)

IDT’s Expenditure in School Infrastructure over the last 5 years

Work Opportunities - Schools Infrastructure 2012/13 REGION Work Opportunities 12/13 Expenditure Eastern Cape1949 R Free State198 R Gauteng1215 R KwaZulu-Natal2286 R Limpopo73 R Mpumalanga299 R North West1491 R Northern Cape533 R Total8044 R

Women/Youth Contractors 2012/13 In all IDT Social Infrastructure programmes the following was achieved: R1.035bn contract value was awarded to women contractors/service providers (18% of total programme spend) R652m expenditure on youth contractors/service providers (12% of total programme spend) R3.554bn BBBEE expenditure (63% of total programme spend) A total of 34,534 work opportunities were created by IDT in its social infrastructure programmes In all IDT Social Infrastructure programmes the following was achieved: R1.035bn contract value was awarded to women contractors/service providers (18% of total programme spend) R652m expenditure on youth contractors/service providers (12% of total programme spend) R3.554bn BBBEE expenditure (63% of total programme spend) A total of 34,534 work opportunities were created by IDT in its social infrastructure programmes

Total IDT Schools Infrastructure Programmes 2013/14

IDT New/Replacement Schools Programmes – 2013/14

IDT Schools Infrastructure Programmes – Water/Sanitation /14

IDT Schools Infrastructure Programmes – Renovations/ Additions 2013/14

IDT Participation in SIP 13 IDT has been appointed as one of the Implementing Agents by DBE under the ASIDI programme Appointment relates to construction work in 52 schools (10 in FS and 42 in EC). IDT appointment for ASIDI EC schools includes 27 schools to be constructed using ACMs Construction work in schools is largely upgrades of existing mud and inappropriate schools entailing additions and replacements IDT also appointed in KZN, EC, LP and NW by DBE to upgrade/install water and sanitation facilities in schools The IDT has been advised of the PICC intention to appoint it as a co-coordinator with DBSA for SIP 13. This, however, has not yet materialised IDT has been appointed as one of the Implementing Agents by DBE under the ASIDI programme Appointment relates to construction work in 52 schools (10 in FS and 42 in EC). IDT appointment for ASIDI EC schools includes 27 schools to be constructed using ACMs Construction work in schools is largely upgrades of existing mud and inappropriate schools entailing additions and replacements IDT also appointed in KZN, EC, LP and NW by DBE to upgrade/install water and sanitation facilities in schools The IDT has been advised of the PICC intention to appoint it as a co-coordinator with DBSA for SIP 13. This, however, has not yet materialised

Challenges and Conclusion Shortcomings in infrastructure delivery planning often resulting in non alignment between funding and delivery Timeous transfer of programme funds to implementing agents resulting in undue delays in payment of service providers Service quality degeneration in the built environment particularly in the professional consulting space i.e. Architects, Engineers & Quantity Surveyors Generally concerning levels of corruption in the country often manifests in collusions in the delivery value chain Long term sustainability uncertainty of the IDT i.e. if funding is not secured, the R20bn IDT portfolio managed for government might suffer Shortcomings in infrastructure delivery planning often resulting in non alignment between funding and delivery Timeous transfer of programme funds to implementing agents resulting in undue delays in payment of service providers Service quality degeneration in the built environment particularly in the professional consulting space i.e. Architects, Engineers & Quantity Surveyors Generally concerning levels of corruption in the country often manifests in collusions in the delivery value chain Long term sustainability uncertainty of the IDT i.e. if funding is not secured, the R20bn IDT portfolio managed for government might suffer

Alternative Construction Methods (ACMs)

What are ACMs? Alternative Construction Methods (ACM) use materials and methods that are not conventional, i.e. not brick and mortar. ACMs are Agrément SA certified complete building systems (from sub-structure to roof) ACMs are generally panelised systems Alternative Construction Methods (ACM) use materials and methods that are not conventional, i.e. not brick and mortar. ACMs are Agrément SA certified complete building systems (from sub-structure to roof) ACMs are generally panelised systems

Use of ACMs For an ACM to be used in the public sector it must be certified by Agrément The Certificate refers to a Quality Control Manual that ensures the system is installed according to the standards Departure from the conditions of the Certificate could invalidate the Certificate, and make the system non-compliant with Agrément, in which case an Occupation Certificate may be refused by the Local Authority ACM contractors need to be licensed by the certificate holder For an ACM to be used in the public sector it must be certified by Agrément The Certificate refers to a Quality Control Manual that ensures the system is installed according to the standards Departure from the conditions of the Certificate could invalidate the Certificate, and make the system non-compliant with Agrément, in which case an Occupation Certificate may be refused by the Local Authority ACM contractors need to be licensed by the certificate holder

Design ACM methods can be applied to any design. However, to achieve design flexibility using manufactured systems requires that maximum use of the kit is made, i.e., the design must follow the kit, not the kit the design. This requires a new design approach, one that is very disciplined with regard to dimensional co-ordination, modularity, size and shape, and jointing, if the kit is to be maximised and wastage reduced. ACM methods can be applied to any design. However, to achieve design flexibility using manufactured systems requires that maximum use of the kit is made, i.e., the design must follow the kit, not the kit the design. This requires a new design approach, one that is very disciplined with regard to dimensional co-ordination, modularity, size and shape, and jointing, if the kit is to be maximised and wastage reduced.

Energy efficiency Manufactured systems will generally out-perform conventional brick and mortar systems when it comes to energy efficiency. Most panelised systems make use of insulated cores that offer higher thermal resistance values than conventional construction. Furthermore it is possible to achieve improved air- tightness which improves the energy efficiency of the building. Manufactured systems will generally out-perform conventional brick and mortar systems when it comes to energy efficiency. Most panelised systems make use of insulated cores that offer higher thermal resistance values than conventional construction. Furthermore it is possible to achieve improved air- tightness which improves the energy efficiency of the building.

Environmental Considerations ACMs are generally more environmentally friendly because the materials are: Inert (no off-gassing or flaking) Safe (no toxins) Recyclable (steel) Resource efficient (minimum waste) Environmentally friendly (less cement, aggregates and water used) ACMs are generally more environmentally friendly because the materials are: Inert (no off-gassing or flaking) Safe (no toxins) Recyclable (steel) Resource efficient (minimum waste) Environmentally friendly (less cement, aggregates and water used)

Local Economic Contribution Materials – the local economic contribution is dependent on the type of ACM but typically the majority of building materials (by value) are conventional and can be sourced locally Labour – the construction method is labour-intensive and the larger portion of labour cost can be spent on local labour in the erection of the ACM as well as in conventional skilled labour such as plastering and painting The choice of ACM should be influenced by the availability of local materials and labour to maximise local economic contribution ACMs promote local job creation but with differentiated distribution (in factory and on site). Site job opportunities are however for shorter periods ACMs promote industrialisation and hence contribute to decent job creation Materials – the local economic contribution is dependent on the type of ACM but typically the majority of building materials (by value) are conventional and can be sourced locally Labour – the construction method is labour-intensive and the larger portion of labour cost can be spent on local labour in the erection of the ACM as well as in conventional skilled labour such as plastering and painting The choice of ACM should be influenced by the availability of local materials and labour to maximise local economic contribution ACMs promote local job creation but with differentiated distribution (in factory and on site). Site job opportunities are however for shorter periods ACMs promote industrialisation and hence contribute to decent job creation

Benefits arising from the use of ACMs Quality is generally higher but at least equivalent to conventional methods Facilities can be delivered more quickly than with conventional methods Construction costs are lower than with conventional methods Thermal efficiency is often better but is at least equivalent to conventional methods Delivery of materials is made easier with panelised systems (less and lighter) than conventional methods Quality is generally higher but at least equivalent to conventional methods Facilities can be delivered more quickly than with conventional methods Construction costs are lower than with conventional methods Thermal efficiency is often better but is at least equivalent to conventional methods Delivery of materials is made easier with panelised systems (less and lighter) than conventional methods

Benefits arising from the use of ACMs - cont Performs technically (weatherproofing,) as well if not better than conventional methods Environmentally more sustainable (water, energy, material efficiency) than conventional methods Contributes towards local economic growth through labour and material acquisition Up-skills construction industry Local skills transfer (site fabrication and assembly) Performs technically (weatherproofing,) as well if not better than conventional methods Environmentally more sustainable (water, energy, material efficiency) than conventional methods Contributes towards local economic growth through labour and material acquisition Up-skills construction industry Local skills transfer (site fabrication and assembly)

Limitations of ACMs Long-term durability and life cycle cost of the ACMs under local conditions has not been tested Design must take into consideration the specific nature of the ACM (e.g. panelised system) Once-off use of ACM in an area limits the benefits of skills transfer and the opportunity of utilisation of acquired skills More advocacy work is still required to promote social acceptance, but the initial response has been positive Long-term durability and life cycle cost of the ACMs under local conditions has not been tested Design must take into consideration the specific nature of the ACM (e.g. panelised system) Once-off use of ACM in an area limits the benefits of skills transfer and the opportunity of utilisation of acquired skills More advocacy work is still required to promote social acceptance, but the initial response has been positive

Conclusions: ACMs ACM offers distinct advantages over conventional construction in relation to speed, cost and quality Considering the maintenance intensive nature of ACMs it seems likely that conventional would outperform ACMs in life cycle cost and life span ACMs should be considered by the public sector as a feasible alternative to enhance delivery of school infrastructure, where urgency is a primary factor ACM offers distinct advantages over conventional construction in relation to speed, cost and quality Considering the maintenance intensive nature of ACMs it seems likely that conventional would outperform ACMs in life cycle cost and life span ACMs should be considered by the public sector as a feasible alternative to enhance delivery of school infrastructure, where urgency is a primary factor

Financial Overview The IDT is currently faced with the uncertainty of its future financial sustainabilit.y It requires short- to medium-term (two to three years) funding from National Treasury and the support from Treasury to increase the level of the management fees it charges client departments. The investment fund which has provided the means of funding a proportion of the operational expenditure has been almost depleted. Without this support, the IDT, is not a going concern. The IDT is currently faced with the uncertainty of its future financial sustainabilit.y It requires short- to medium-term (two to three years) funding from National Treasury and the support from Treasury to increase the level of the management fees it charges client departments. The investment fund which has provided the means of funding a proportion of the operational expenditure has been almost depleted. Without this support, the IDT, is not a going concern.

Financial Overview The Department of Public Works is currently driving the preparation of the business case and mandate for the IDT, and is interacting with Treasury on this process. It is essential that the process is concluded as quickly as possibleso as not to disrupt the ability of the IDT to deliver on its programme management functions. The Department of Public Works is currently driving the preparation of the business case and mandate for the IDT, and is interacting with Treasury on this process. It is essential that the process is concluded as quickly as possibleso as not to disrupt the ability of the IDT to deliver on its programme management functions.

Financial Overview It is anticipated that the IDT will no longer be in a position to take on all programmes offered to it in the future but will need to be selective in the work it does undertake – one of the determining factors will be the level of management fees recovered from the programmes, with the emphasis being on social infrastructure programmes. The efficiency ratio (operational costs expressed as a percentage of programme expenditure) has reflected significant improvement over the past four years – from 20% to 6%. It is anticipated that the IDT will no longer be in a position to take on all programmes offered to it in the future but will need to be selective in the work it does undertake – one of the determining factors will be the level of management fees recovered from the programmes, with the emphasis being on social infrastructure programmes. The efficiency ratio (operational costs expressed as a percentage of programme expenditure) has reflected significant improvement over the past four years – from 20% to 6%.

Financial Overview This ratio indicates that the IDT has reached a point where its resources are being stretched to a level which is inherently risky and could result in a drop in quality and performance. The optimum efficiency ratio is considered 8%.