Excavating and Lifting Part 1
Site Grading Site Grading Civil Engineering and Architecture
Loading and Hauling.
CTC-275 Construction Methods
Excavating and Lifting Part 2
Load and Haul Fleet Selection Based on Fixed Plant Production
Loading and Hauling Part 2
3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine.
Lecture 4 Excavating and Lifting
Draglines and Clamshells
Eng. Malek Abuwarda Lecture 8 P1P1 Construction Methods Lecture 8 Loading and Hauling.
Lecture 7 Loading and Hauling
Front End Loader Costs ©Dr. B. C. Paul 2000 Start Detailed Economic Comparison of 3 machines l Strategy Go Through Each Machine and Figure the Cost Compare.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 10 Trucks and Hauling Equipment.
Front shovel, back hoe and loader. Group member: Lam Wai Kei Hui Tan La
Excavating and Lifting Hmwk Ch 2 # 1,2,5,8 Ch 3 #2,4,6,10.
Earthmoving Materials and Operations
TRUCKS THE MOST COMMON HAULING EQUIPMENT USED FOR MILITARY CONSTRUCTION SITE ARE 2 1/2, 5, AND 20 TON DUMP TRUCKS. THE HAUL CAPACITY CAN BE EXPRESSED.
Matching An Excavator to Our Trucks ©2009 Dr. B. C. Paul Note – These Slides contain tables and information found in the Caterpillar Performance Handbook.
Pricing Excavation and Backfill
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Excavating and Lifting Part 2
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
CEE 404 Winter Productivity Refresher. CEE 404 Winter Excavator Cycle Time.
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
Excavating and Lifting Part 1
Loading Considerations © 2000 Dr. B. C. Paul revisions 2009 Note These slides include screen shots from the Caterpillar Performance Manual Edition 29.
Lecture 6 Loading and Hauling
CONSTRUCTION TECHNOLOGY & maintenance
TYPES OF CONSTRUCTION MACHINERY. FOLLOWING ARE THE MAJOR TYPES OF EQUIPMENTS THAT IS BEING USED IN THE CONSTRUCTION INDUSTRY.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 6 Machine Equipment Power Requirements.
Lecture 2 Introduction to Earthmoving
Planning for Earthwork Construction
Team Assignments C D A B Clayten Greenwell Ryan Franklin Elliot Magoto
Horticulture CD Unit C 6-3: Nursery, Landscaping, and Gardening.
Matching Shovels ©Dr. B. C. Paul 2000 revised 2008 Note – Matching procedures depicted in these slides are widely understood among those schooled in the.
1. 2 Civil Engineering Practice Introduction Instructor: Dr. Attaullah Shah Lecture # 1 Department of Civil Engineering Swedish College of Engineering.
Soil Compaction Topic I Topic I.
Compaction.
Step #1 Matching ©Dr. B. C. Paul 2000 revised 2008 Note many of the ideas expressed in these slides can be found in Surface Mining Manuals, the Book Surface.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 7 Dozers.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
Where’s My Material? Appropriate Planning for Cap and Habitat Restoration Material Quantities Presented by Paul LaRosa, P.E., John Verduin, P.E., and Ram.
نظام المحاضرات الالكترونينظام المحاضرات الالكتروني Construction Methods By Ruqaya ALZubaidi.
FPC Assignment 1. Go to Your Project and Fire-Up MSOPIT.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
Resource Leveling Advantages/Applications of Resource Leveling 1. Maintain the lowest uniform number of employees to perform the work. 2. Establishing.
Types of Loaders ©Dr. B. C. Paul 2000 Loading Equipment l Four Basic Types of Loaders Cable Shovel Hydraulic Front Shovel (also called hydraulic excavator)
A Heap Leach Plan. My Concept I’ll build one great big pad I’ll fill it in with rows of material about 40 feet high I’ll then fill in between the rows.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
Obtaining Moving Cycle Times ©Dr. B. C. Paul 2000 revised 2008 Note – The methods shown in these slides are adapted to use FPC, a program produced by.
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
Checking On Production ©2009 Dr. B. C. Paul Note – These slides contain material from slides dating back to 2000 and also contains screen shots from the.
Earth Moving Equipment Companies in Sharjah
3.9 Continued….Word Problems Involving Proportions
Process Equipment Design and Heuristics - Pumps
CONSTRUCTION METHODS & TECHNOLOGY
SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING Excavation
TRUCKS & HAULING EQUIPMENT
Lecture 7 Excavators TSP-308 MPK Ferdinand Fassa.
Lecture 6 scrapers TSP-308 MPK Ferdinand Fassa.
CONSTRUCTION EQUIPMENT MANAGEMENT
Compaction.
Lecture 5 Dozer TSP-308 MPK Ferdinand Fassa.
MUHAMMAD WAJAHAT AMIN (INTERNEE, MINE PLANNING) OPEN PIT MINING TOPICS.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Freshwater quiz review
Presentation transcript:

SHOVELS

SHOVELS William S. Otis, of the firm of Carmichael, Fairbanks and Otis, when living in Canton, Massachusetts in 1834 and 1835, while his firm was performing grading work for the Boston & Providence Railroad built the first steam excavator – a steam shovel.

OTIS SHOVEL

AN EARLY SHOVEL

SHOVELS Front shovels are used predominately for hard digging above track level and for loading haul units. Loading of shot rock would be a typical application.

STEP 1: BUCKET SIZE Shovels can usually be equipped with different size buckets. Bottom dump buckets are also available.

STEP 1: BUCKET SIZE Buckets are rated in both heaped and struck capacities. Both PCSA and SAE use a 1:1 angle of repose for evaluating heaped bucket capacity. CECE specifies a 2:1 angle of repose. Heaped Capacity is the rating of interest for Production Estimating.

STEP 2: FILL FACTOR The Fill Factor adjusts Heaped Capacity in lcy based on the type of material being handled. Table 9.1, page 258

STEP 2: FILL FACTOR HEAPED BUCKET CAPACITY  FILL FACTOR = VOLUME (lcy)

STEP 3: CYCLE TIME There are four elements in the production cycle of a shovel: Load bucket Swing with load Dump load Return swing See page 260

STEP 3: CYCLE TIME Height of cut affects shovel production. Optimum height of cut ranges from 30 to 50% of maximum digging height, with the lower percentage being representative of easy-to-load materials, such as loam, sand, or gravel. Table 9.2

STEP 3: CYCLE TIME Angle of swing affects shovel production. If the angle of swing is increased, the time for a cycle will be increased, whereas if the angle of swing is decreased, the time for a cycle will be decreased. Table 9.2

STEP 3: CYCLE TIME Ideal production of a shovel is based on operating at a 90° swing and optimum height of cut. The effect of the angle of swing on the production of a shovel is illustrated in Table 9.2.

STEP 4: EFFICIENCY FACTOR When selecting a minutes per hour efficiency factor visualize the work site and consider: Materials being handled, bank or broken Size of the shovels’s dumping target, (large or small)

STEP 5: CLASS of MATERIAL Production will be in lcy, will need swell factor to adjust to bcy. TABLE 4.3

STEP 6: PRODUCTION X Heaped Capacity (lcy) X Fill Factor X height/swing factor = Production (lcy/hr)

OTIS STEAM SHOVEL