Presentation For the Moldova Safeguards Training Workshop October 28-31, 2008 By Victor B. Loksha Consultant Europe and Central Asia Region The World Bank.

Slides:



Advertisements
Similar presentations
Environmentally sound management of ship recycling- simple or complex? Roy Watkinson Department for Environment, Food and Rural Affairs UK Promoting Sustainable.
Advertisements

Training Workshop for Financial Intermediaries and Implementing Agencies Kiev, May 2011 Ruxandra Floroiu Senior Environmental Engineer, ECA Region, World.
Training Workshop for Financial Intermediaries and Implementing Agencies May 2011 Ruxandra Floroiu Senior Environmental Engineer, ECA Region, World Bank.
SUPPORTED BY THE EUROPEAN UNION’S OBNOVA AND PHARE PROGRAMMES EIA TRAINING RESOURCE MANUAL FOR SOUTH EASTERN EUROPE Scoping.
UNRESTRICTED Infrastructure Assessment as Viewed by Technology Holders IAEA Technical Meeting December 10-12, 2008 R. Godden.
1 “Environmental Auditing in the Republic of Macedonia” “Environmental Auditing in the Republic of Macedonia” State Audit Office Nada Sekulovska Gorast.
Contractor Management and ISO 14001:2004
ENVIRONMENTAL MANAGEMENT PLAN
Secretariat to the Espoo Convention and its Protocol on SEA
SÄTEILYTURVAKESKUS STRÅLSÄKERHETSCENTRALEN RADIATION AND NUCLEAR SAFETY AUTHORITY Protection of the environment from ionising radiation - views of a regulator.
Overview of Environmental and Social Safeguards Environmental Management Plan Checklist for Simple Civil Works Zagreb, May 6-8, 2009 Presenter: Natasa.
ENVIRONMENTAL MONITORING AND REPORTING BY ENTERPRISES FEASIBILITY OF DEVELOPING MONITORING GUIDELINES FOR CHEMICAL INDUSTRY IN EASTERN EUROPE, CAUCASUS.
Strategic Environmental Assessment and environmental issues in programme evaluation Ivana Capozza Italian Evaluation Units Open Days Roma, July 5, 2006.
Environmental Impact Assessment (EIA): Overview
Jerzy Jendrośka Introduction to the Environmental Impact Assessment (EIA) and the Strategic Environmental Assessment (SEA) Directives INTERACTION BETWEEN.
This project is funded by the European Union ENVIRONMENTAL COLLABORATION FOR THE BLACK SEA GEORGIA, MOLDOVA, RUSSIA and UKRAINE Euroconsult This project.
Implementing the Second Pillar of the Aarhus Convention: Problems Identified in the National Implementation Reports Magda Tóth Nagy, Senior Expert Geneva,
PEIP National workshop in Montenegro: developing environmental infrastructure projects in the water sector Feasibility Study Preparation Venelina Varbova.
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Staffing and Training.
The Aarhus & Espoo Conventions Making implementation work for stakeholders.
Report on the current legal structure and resources available to the environmental protection agencies and inspectorates in Croatia 1st BERCEN Exchange.
UNECE Convention on the Protection and Use of Transboundary Watercourses and International Lakes A unique framework for improved management of shared waters.
Ministry of Waters and Environmental Protection, ROMANIA 1 BERCEN 1 st Exchange program – November 2002 Croatia PROBLEMS AND SOLUTIONS IN COOPERATION.
1 Permitting of industrial facilities in Croatia.
Kavala Workshop 1-2 June 2006 Legal protection of Transitional Waters [in the Cadses area]: A comparative analysis Dr. Petros Patronos / Dr. Liliana Maslarova.
Safeguard Training Workshop Zagreb, Croatia May 7, 2009 Ruxandra Floroiu (Environmental Engineer)
Gulana Hajiyeva Environmental Specialist World Bank Moscow Safeguards Training, May 30 – June 1, 2012.
Slovak Environmental Inspectorate Procedure of issuing the permits in the Slovak Republic.
UNEP Training Resource ManualTopic 2 Slide 1 The EIA process The EIA process comprises:  screening - to decide if and at what level EIA should be applied.
Mini-Case / Quiz Topic: EA Categorization and EMP Requirements By Victor B. Loksha ECA Safeguards Team Europe and Central Asia Region The World Bank Discussion.
State of implementation of the decision III/6f regarding Ukraine (MOP 2, June, , 2008, Riga, Latvia)
Information and transboundary cooperation – challenges and responses Francesca Bernardini United Nations Economic Commission for Europe.
EIA-legislation and practice in Norway history history latest amendments of regulations latest amendments of regulations integrated planning/EIA processes.
Environmental Management Plan (EMP) Required for: Full EIA based on Palestinian EIA Policy Category A projects based on World Bank Policy.
Environmental Impact Assessment in the Slovak republic.
INTERNATIONAL EXPERIENCE AND TRENDS IN EIA FOR DEVELOPMENT PROJECTS Clive George EIA Centre and Institute for Development Policy and Management University.
Capacity Building of Kazakhstan Aarhus Centres in Providing Access to and Exchange of Environmental Information Olga Melnik, Information and Analysis Center.
Permitting and Inspection. 1. When is decentralization effective? Delegate most permit writing and inspection functions to lowest possible level to effectively.
PPSD in specific sectors in Bulgaria - Regional Plans for Development National Programme for Ports Development (2006 – 2015) Vania Grigorova, Jacquelina.
Strengths and weaknesses of the permitting system and enforcement process in RIEW – Veliko Turnovo Regional Inspectorate of Environment and Water - Veliko.
Technical Meeting on Milestones for nuclear power infrastructure development Radiation Protection Khammar Mrabit Head, Regulatory Infrastructure and Transport.
Consultation seminar on the preparation of full Application Form for LSP 6 December 2011, Tartu Consultation seminar on the preparation of full Application.
Specific Safety Requirements on Safety Assessment and Safety Cases for Predisposal Management of Radioactive Waste – GSR Part 5.
SEA in the Czech Republic Prague, 24 September 2008.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
1 The Protocol on Water and Health TASK FORCE ON PUBLIC PARTICIPATION IN DECISION-MAKING October 2010, Geneva, Switzerland Tomasz Juszczak, UNECE.
Overview of Environmental and Social Safeguards Environmental Management Plan Checklist for Simple Civil Works Chisinau, October 28-31, 2008 Ruxandra Floroiu,
1 Short overview of the implementation of IPPC, LCP, Seveso II, Waste Landfill and Incineration directives Short overview of the implementation of IPPC,
Joint bodies according to the UNECE Convention on the Protection and Use of Transboundary Watercourses and International Lakes Francesca Bernardini United.
Achievements in IPPC Directive Implementation: problems and constraints Albania Ministry of Environment 3 rd BERCEN Exchange Programme for the Environmental.
National Environmental Assessment Requirements and Relation to World Bank Policies Relevance to Central Asia Gulana Hajiyeva WB Safeguards Training Workshop.
Pilot Project on implementation of SEA for regional planning in Ukraine Prof. Dr. Michael Schmidt Dmitry Palekhov Brandenburg University of Technology.
DG ENV Environmental assessment procedures for energy infrastructure projects of common interest (PCIs)
Peter Lukáč Ministry of Environment of the Slovak Republic Department of Environmental Assessment.
Lecturer: Lina Vladimirovna Zhornyak, associated professor.
1 Legal Frameworks for Public and Stakeholder Engagement by Carl Bruch Asia Regional Workshop on Stakeholder Engagement in International Waters Management.
Lithuanian Water Suppliers Association LEGAL REGULATION OF WASTEWATER DISPOSAL AND TREATMENT IN LITHUANIA.
Lecturer: Lina Vladimirovna Zhornyak, Associate Professor.
1 1 The Project Description: Framing the CEQA Analysis Terry Rivasplata.
ISO Session 3 Environmental Management and Ethics in Management.
IPPC A general overview Nigel Barraclough Policy Adviser Industrial Pollution Control Branch Air and Environment Quality Division. Taiwanese Environmental.
Environmental Safeguards
GEOECOLOGICAL PROJECT
Overview of public participation in strategic decision-making in the UNECE area David Aspinwall.
Towards Modern Environmental Impact Assessment (EIA) in Uzbekistan
Jerzy Jendrośka Transboundary procedures
Communication and Consultation with Interested Parties by the RB
Nick Bonvoisin Secretary to the Convention on the
Relationship between World Bank and Romanian EA requirements
World Health Organization
Presentation transcript:

Presentation For the Moldova Safeguards Training Workshop October 28-31, 2008 By Victor B. Loksha Consultant Europe and Central Asia Region The World Bank Relationship between World Bank and national Environmental Assessment requirements

Regulations on EIA/SEE in ECA countries Environmental Impact Assessment (EIA) systems of many Europe and Central Asia (ECA) countries have common roots and are similar In a large group of countries, including Moldova, the EIA systems are based on the state ecological “expertise” (review) system (SEE) developed in Soviet times The screening procedures are typically weak leading to arbitrary treatment of projects: –No clear criteria for what kind of activities need to be subject to SEE, so practically all projects with even very minor impacts must undergo SEE –At the same time, in some countries (including Moldova) the requirement of EIA (or “full EIA”) is applied only to very high environmental impact projects

ECA traditional approach to EIA Detailed (final) EIA is available only after the engineering design phase is completed Final EIA is often based on complex models: –Analysis of project activity in combination with background environmental quality is usually required –The cumulative concentration is compared with maximum allowable concentrations (e.g., of air pollutants) Standard computer models developed by the State Hydrometeorological Service must be used for this

ECA traditional approach to EIA (cont’d) SEE approves the project twice: –At the stage of feasibility study –At the stage of detailed design documentation The environmental protection plan (EPP) is part of the detailed design documentation

Preliminary Environmental Impact Assessment Detailed Design Project Identification Preparation Planning/Feasibility Monitoring Supervision of Construction/Implementation Operation EIA and Project Cycle: Standard Practice in Many ECA Countries Final EIA, including the mitigation measures (EPP) Environmental Permit Construction Permit

Moldovan Regulations on EIA/SEE EIA (“OVOS”) in Moldova is regulated by two laws and a series of regulations and guidelines: –The Law on Protection of the Environment: No XII, 1993 with amendments Other laws and regulations: –Law on SEE and EIA (1996) –Regulation on Environmental Audit of Enterprises (1998) –Regulation on Public Participation in Decision Making (2000) –Resolution on the Approval of the Instruction for Organization and Implementation of the SEE No. 188 approved Moldova is a party to the Espoo Convention on EIA in a transboundary context

Institutions in charge of SEE/EIA in Moldova The Ministry of Ecology and Natural Resources is the institution responsible for EIA The Ministry has an Ecological Inspectorate which includes a special division on State Ecological Expertise –For particularly complicated projects that require a full EIA, the Pollution Prevention Division from the Ministry’s central body is in charge of reviewing the EIA

EIA documentation is developed at early planning stage EIA is a mandatory part of planning and project documentation (PPD) –Note: Literal applicability of this norm can be problematic since most projects reviewed by SEE do not require an EIA per se (“full EIA”) PPD must contain a section on environmental protection Positive decision of the SEE is required to start preparation of the environment section of PPD /1/ Resolution on the Approval of the Instruction for Organization and Implementation of the SEE, №. 188, approved ; published in Monitorul Oficial № 014 on Moldovan Government regulations /1/ require that:

Moldovan vs the Bank’s EMP requirements Moldovan Environmental Law has no provision for preparation of an Environmental Management Plan (EMP) per se Moldovan legal and regulatory framework does have provisions for an Environmental Protection Plan (EPP) EPP defines the mitigation measures based on EIA EPP is integrated into project development cycle: –Technical solutions presented to SEE must be substantiated on the basis of environmental impact reduction… –The documentation presented to SEE must contain sufficient and well substantiated environmental protection measures to ensure environmental safety for the entire project cycle –Resolution on the Approval of the Instruction for Organization and Implementation of the SEE, №. 188, approved ; published in Monitorul Oficial № 014 on

Moldovan environmental mitigation requirements The Government regulations (Instructions) specify types of environmental protection measures required for each environmental media E.g., the project documentation must contain the following information on water resources management: –Measures for coastal zone management –Measures for riverine and estuarine management –Measures for sediment management –Measures for possible accidents in water supply and wastewater management –Measures for fish protection –Measures to reduce water consumption

Moldovan environmental mitigation requirements (cont’d): The project documentation must contain the following information on air quality management: Technological measures: –Filter and scrubber equipment –Dispersion enhancement –Reduction of fugitive emissions Planning measures: –Siting of residential and industrial objects according to the prevailing wind direction –Allowing for a sanitary protection zone supported by calculations and adjusted to wind direction and buffer zone allocation

The project documentation must contain the following information on waste management: –Measures for protection from waste pollution –Utilization / burial of industrial wastes in specially designated sites The project documentation must contain the following information on protection of flora and fauna: –Measures (e.g., revegetation) for protection of soils, water and air sheds envisaged in the PPD as measures to protect the genetic fund of plants and animals Moldovan environmental mitigation requirements (cont’d):

Moldovan vs the Bank’s EMP requirements Differences in scope of the Bank’s typical EMP and Moldovan environmental action plan – how significant are the differences? –Legal status: the Bank’s EMP is legally binding Provision on EMP in the Loan Agreement –Different process for arriving at mitigation measures: The Bank’s EMP is derived from EIA study The Moldovan EPP is also based EIA but the Government regulations/instructions also contain lists of required types of mitigation measures –Different timing: The Bank requires EIA/EMP earlier in the process This allows for better disclosure –Different scope and content of EMP vs EPP

What is typically included in the Bank standard EMP? 1.A brief project description 2.Mitigation or pollution control plan Including responsibilities and costs 3.Monitoring requirements Including responsibilities and costs 4.Institutional arrangements to be used to implement the EMP Responsibilities Institutional strengthening (training) arrangements Reporting requirements Schedules 5.Public consultation summary (minutes of meetings with affected groups and stakeholders, etc.). The Moldovan EPP is mostly limited to this

What are the implications? When the country has no provision for a legally binding EMP: –Environmental mitigation measures are more difficult to enforce When monitoring plan is not included: –The effectiveness of mitigation measures cannot be assessed When institutional responsibilities are not assigned: –It is difficult to ensure accountability, monitor compliance, or reward good performance When costs are not estimated: –It is less likely that the mitigation measures will be adequately financed When public consultation is not documented: –It is less likely that consultation will be timely and adequate

Concluding remarks on EMP There are no legal obstacles for expanding the Moldovan EPP to the World Bank’s EMP How to do this? Expand the scope of the Moldovan EPP to include: –Clearly assigned responsibilities –Monitoring requirements –Cost estimates –Training requirements –Public consultation requirements The practical implementation of such an expanded EPP/EMP will remain a challenge… … but the interests of the environment will be better served

Other aspects of environmental legislation/regulation in Moldova Moldova has “made visible progress in adopting new legislation but issues of compliance and enforcement will undoubtedly arise...” Environmental Impact Assessment Systems in Europe and Central Asia Countries. The World Bank, 2002

Other aspects of environmental legislation/regulation in Moldova (cont’d) Areas of good progress made in Moldova: –Analysis of alternatives –Strategic Environmental Assessment –Implementation monitoring: Requirement in the law for environmental authorities to monitor implementation of SEE and/or compliance with EIA requirements –Public participation Moldova is a party to the Aarhus Convention Moldova’s Regulations on Public Participation in Environment Decision-Making introduced in 2000 are best practice in NIS countries

Thank You!