Laser Beam Transport and Integration. AWAKE Collaboration meeting. Mikhail Martyanov Christoph Hessler CERN, EN-STI-LP Valentin Fedosseev CERN09-11.04.2014.

Slides:



Advertisements
Similar presentations
Summary of the Design Report and Next Steps Edda Gschwendtner for the CERN AWAKE Project Team Edda Gschwendtner, CERN1.
Advertisements

Ultrafast XUV Coherent Diffractive Imaging Xunyou GE, CEA Saclay Director : Hamed Merdji.
Philippe Hering October 30, 2007 Drive Laser Commissioning Results and Plans 1 Drive Laser Commissioning results and plans Philippe.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
1 Stefan Moeller 1 AMO Instrument Schedule ARR AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009.
LCLS Studies of Laser Initiated Dynamics Jorgen Larsson, David Reis, Thomas Tschentscher, and Kelly Gaffney provided LUSI management with preliminary Specifications.
Vacuum optical compressor: Tentative ideas, layout, size … Mikhail Martyanov, CERN AWAKE TB and PEB meeting December 2014.
Compressor status AWAKE Technical Board meeting 19 May 2015.
Matching and Synchrotron Light Diagnostics F.Roncarolo, E.Bravin, S.Burger, A.Goldblatt, G.Trad.
Laser news AWAKE performance meeting Overview There was a meeting on with the supplier of the laser system (AMPLITUDE) No new information.
AWAKE workshop, Greifswald, September 24 th -26 th, 2014Steffen Döbert, BE-RF AWAKE electron source update.
AWAKE electron source New Electron Source WP at CERN
UCLA Frequency-domain interferometry diagnostic system for the detection of relativistic plasma waves Catalin V. Filip, Electrical Engineering Department,
Summary of the AWAKE Technical Board Meeting September 2014 – March 2015.
The AWAKE Project at CERN and its Connections to CTF3 Edda Gschwendtner, CERN.
What’s already existing?What’s already existing? Laser system & impacts on Optics TransportLaser system & impacts on Optics Transport –Laser power –Focusing.
Impact on Project Planning and Cost. Agenda CERN Project Budget Planning Summary E. Gschwendtner, 9 April
Utilities 14 October 2008 Martin Nordby, Gordon Bowden.
Summary of issues. RF-Gun cavity – Disk and washer (DAW) : very fast RF ageing, 2 MeV is not enough. – Quasi travelling wave side couple structure : Lower.
Integration of the Experimental Facility in West Area & CNGS 1Ans Pardons, 18/10/2012 Integration of experimental facility in West Area and CNGS With input.
AWAKE Electron Spectrometer Simon Jolly, Lawrence Deacon, Matthew Wing 28 th January 2015.
Photon Diagnostic Station For TAC IR-FEL Test Facility ILHAN TAPAN* *on behalf of the TAC collaboration Uludag Universitesi, Bursa,16059, TURKEY References.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Low Emittance RF Gun Developments for PAL-XFEL
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
Laser Status Update J. Moody, E. Oz, P. Muggli MPP Future Accelerators AWAKE Collaboration
Update on Laser Beam Lines Christoph Hessler, Mikhail Martyanov, Valentin Fedosseev (CERN laser team)‎ Thanks to M. Battistin, N. Chritin, F. Galleazzi,
Compressor status AWAKE Technical Board meeting 19 August 2015.
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
Requirements for the Interlock System of the Phase1 beam line Janet Schmidt on behalf of CP3.
Plasma Wakefield Diagnostic on AWAKE using Photon Acceleration Muhammad Firmansyah Kasim Supervisor: Peter A. Norreys and Philip N. Burrows.
Update on the Laser Beam Line
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Laser Notcher Status Dave Johnson PIP Meeting June 26,2012.
Design, integration and installation milestones Legend: 2015/Q1= 1 st quarter of 2015 (January-March) Phase 1 = proton & laser beams operation Phase 2.
LER Workshop, October 11, 2006LER & Transfer Line Lattice Design - J.A. Johnstone1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Introduction The.
Dec7,2007 ie-FP7 Test Beams for detector R&D at CERN The PS East Area The SPS North Area Irradiation facilities.
HiRadMat – Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,
Integration and Installation Status for Collaboration Meeting Ans Pardons, 29/9/2015.
Status of the AWAKE Control System Edda Gschwendtner, Janet Schmidt, Marine Gourber-Pace, Roman Gorbonosov, Peter Sherwood AWAKE Technical Board, 27 January.
AWAKE: D2E for Alexey beam properties Silvia Cipiccia, Eduard Feldbaumer, Helmut Vincke DGS/RP.
Issues Concerning Different Beam Lines Integration C. Bracco, E. Gschwendtner, B. Goddard, M. Meddahi, A. Petrenko, F. Velotti Acknowledgements: WP3 and.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Compressor Helium filled optional equivalent plane imaging laser beam dump hole in mirror for e-beam SSA and more.
Latest results on electron trapping and acceleration Konstantin Lotov, Alexey Petrenko, Alexander Sosedkin, Petr Tuev Budker Institute of Nuclear Physics.
Awake electron beam requirements ParameterBaseline Phase 2Range to check Beam Energy16 MeV MeV Energy spread (  ) 0.5 %< 0.5 % ? Bunch Length (
F. Peauger19th June #3-CTF3 Committee1 CALIFES STATUS CA.BHB 0400CA.SNH 0110CA.SNI 0120 CA.VVS 0100 CA.DHG/DVG 0130 CA.VVS 0200 CA.MTV 0215 CA.BPM.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Summary of the AWAKE Technical Board Meetings Edda Gschwendtner.
Beam on Target Diagnostics Beam on Target Meeting 2013 March Tom Shea.
AWAKE: A Proton-Driven Plasma Wakefield Acceleration Experiment at CERN C. Bracco on behalf of the AWAKE collaboration C. Bracco - ICHEP2014.
European Advanced Accelerator Concepts Workshop, Elba, September 14 th -18 th, 2015Steffen Döbert, BE-RF Electron accelerator for the AWAKE experiment.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
NLCTA Facility Capabilities E. R. Colby 5/18/09. NLCTA Overview RF PhotoInjector Ti:Sapphire Laser System Next Linear Collider Test Accelerator Cl. 10,000.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
Status of AWAKE Laser Line Installtion For the EN-STI Management Board - 30 May 2016 Presented by Valentin Fedosseev.
Laser Arm for Photo-injector Mikhail Martyanov, Valentin Fedosseev, Christoph Hessler AWAKE PEB meeting , CERN.
V. Bagnoud PHELIX, Plasma Physics department GSI Darmstadt
ELENA installation and commissioning status
F Braunmüller, M. Hüther, M. Martyanov, P Muggli, E. Öz
EuPRAXIA working package report
Laser Beam Transport and Integration AWAKE Collaboration meeting Mikhail Martyanov Christoph Hessler CERN, EN-STI-LP Valentin Fedosseev.
Business Development Manager, Bucarest 2011
Electron Source Configuration
Perturbation of Focusing Field Profile due to HV Support Tube
X-ray Pump-Probe Instrument
TEC assembly and commissioning at Lyon
Drive Laser Commissioning Status
AWAKE Experiment at CERN
Presentation transcript:

Laser Beam Transport and Integration. AWAKE Collaboration meeting. Mikhail Martyanov Christoph Hessler CERN, EN-STI-LP Valentin Fedosseev CERN

M.Martyanov, CERN2 AWAKE Experiment Laser room e-gun room p + beam e - beam laser beam Laser safety shutters Laser shutters Fast valves plasma e- spectrometer Laser dump p + / e - diagnostics CV SAS AWAKE gallery Control room 1km Laser / p + merging point

Overview Short intense laser pulse is needed for: – to create a 100% ionized plasma – moving ionization front is a source of perturbation for proton-laser instability (micro-bunching and wake-field with a stable phase) Plan for the Laser system: – First it is delivered to MPP Munich for plasma experiments - mid 2014 – Then it goes to CERN- Autumn M.Martyanov, CERN3

Overview Laser system comprises: - laser with 2 beams (for plasma and for the e-gun) - delay line is possible in either one of these beams - focusing telescope (lenses, in air), long 40m focusing - optical compressor (in vacuum) - small optical in-air compressor and 3 rd harmonics generator for e-gun Laser parameters for plasma: - max energy 450 mJ - pulse duration 120 fs after compression - max beam diameter 40 mm Only reflective optics on the way Rule of thumb (B<1): I[GW/cm 2 ]  L[cm]< M.Martyanov, CERN4

Laser System Base-line Laser, Telescope and Compressor are in the laser room Focusing down to 40 meters to the center of the plasma Back solution: Compressor and Telescope are next to merging point in the proton tunnel Focusing down to 25 meters to the center of the plasma Question is if this possible? Crucial points are: Focusability of the laser beam down to 40 meters, ionization dynamics, diffraction? No detailed information on the laser system yet (beam quality) The placement of the optical compressor and the focusing telescope has an impact on the position of the anew drilled connection tunnel Availability of vacuum components for the compressor and telescope is under study Torr “easily” achievable. Pellicle or differential pumping as an option to go better M.Martyanov, CERN5

M.Martyanov, CERN6 Scope of Laser Line WP Laser room preparation -Clean room, cooling and ventilation, facilities -Access control Laser transfer line to the plasma cell -HV vacuum line -Remote control of the mirrors -Laser beam position monitoring Laser transfer line to the photo-gun -Fore-vacuum line -Remote control of the mirrors -Laser beam position monitoring -In-air compressor and 3 rd harmonic generation <- Electron source WP Laser installation -Laser arrangement on the tables -Integration to the AWAKE environment

 1m compressor 2 x 1 m optical table SAS CV units 4m 3m 0.9m 2 x 1 m optical table 2.5 x 1 m optical table 2.5 x 1 m optical table Arrangement in the Laser Room Fore-vacuum laser transfer line for e-gun (on the ceiling) M.Martyanov, CERN7 PP+ power supply 600x600x(H)850 CCM rack 700x800x(H)1400 ~1m

Three optical tables: 2x1, 2.5x1, 2.5x1 m 1 – MENLO oscillator,500x500 2 – Stretcher,1000x500 3 – Regen / preamp,1000x800 4 – Green pump for (3) 5 – 600mJ amplifier,1500x800 6 – Green pump for (5),500x200 7 – Focusing telescope,1000x200 8 – Delay line for e-gun Laser Arrangement on the Tables M.Martyanov, CERN8

4.000 m 3 /h F 30 Pa15 Pa0 Pa Technical RoomLaser RoomSAS 4 m14 m2 m CV technical room already quite small. Other solutions? Access to CV technicians in the clean room for M&O. Very dry air from surface -> comfort and electronics? Laser room air-conditioning principal (by Michele Battistin) M.Martyanov, CERN9

Fresh air supply from surface Air supply duct to the clean room Air extraction to TCV4 CV first integration (by Michele Battistin) M.Martyanov, CERN10

M.Martyanov, CERN11 Laser Room – Integration 3D Model (by Frederic Galleazzi)

M.Martyanov, CERN12 Laser Room – Integration 3D Model (by Frederic Galleazzi)

TT41 – Laser Beam – Civil Engineering (by Frederic Galleazzi) M.Martyanov, CERN13 Safety laser shutter Vacuum pump Vacuum shutter Laser shutter

Mirror Chambers Preliminary Design (by Nicolas Chritin) M.Martyanov, CERN14

Laser beam is not centered on the mirror in horizontal plane, but centered in vertical. The gap between beams is =2mm The gap between proton beam and a mirror is 1mm  Footprint of the laser beam on the mirror 37=26  sqrt(2) Laser beam  26 Mirror  50, S=12 Fused silica Proton beam  12 Beams separation 21mm Towards the plasma p + from SPS M.Martyanov, CERN15 Laser and p + merging

M.Martyanov, CERN16 Laser Beam Size Downstream Merging (not to scale) Laser beam  merging Mirror  50, S=12 Fused silica Proton beam  12 Beams separation 21mm p + from SPS Plasma cell 20m10m 20m  26 Additional laser shutters Fast valves Laser dump Be-window for p+ Experimental area Laser Safety Shutter

SystemTo define / To do Laser room, SAS, CVAir circulation, conditioning, humidity, filters, circuits (electrical, demineralized water, tap water, compressed air, control cables), safety (fire/smoke alarm), shutters, access etc. Connection tunnel  40cm Drilling, position has been defined Access to laser room and p- tunnel AWAKE access concept including Laser Access Modes to p-tunnel and e- gun room, safety shutters Ti:Sa laserLaser arrangement on three tables to be defined by AMPLITUDE. Arrangement of chillers and electronics – to be defined Controls and diagnostics are provided by AMPLITUDE Detailed specification is required Vacuum pulse compressor and focusing telescope. Who supply compressor chamber ? Vacuum agreed to be 1e-06mbar in the compressor Transfer line to p-tunnel Merging point chamber To be designed, work has been started Transfer line to e-gun Separate small compressor 3 rd harmonic generation In fore-vacuum, to be designed Laser installation in laser room M.Martyanov, CERN17

SystemIssues Laser beam in the p-tunnelSteady diagnostics: Focused beam spot monitor (virtual plasma, the same long distance run); near field before merging mirror; screens before and after plasma tube sensitive to “both” beams (laser, electrons, protons) also equipped with fiber-coupling for rough timing measurements On demand or maintenance diagnostics: Auto-correlator, angular spectrometer, phase-front detector, etc. Laser beam in the e-gun room (small compressor and 3 rd harmonic generation are next to the gun) Steady diagnostics: Virtual cathode CCD, UV energy meter, some IR signal coupled to a fiber for rough timing measurement On demand or maintenance diagnostics: Auto-correlator, angular spectrometer, … Delay control between pulses: ionization and e-gun Delay line either on one of 2 beams, proper delay simulation required. Split after RegAmp was proposed by AMPLITUDE with 2.5mJ IR output for e-gun Laser installation in p-tunnel and in e-gun room M.Martyanov, CERN18

Thank you! M.Martyanov, CERN19

M.Martyanov, CERN20

4.000 m 3 /h F 30 Pa15 Pa0 Pa Technical RoomLaser RoomSAS 2 m ! 15 m 3 m CV technical room already quite small. Other solutions? – Make it even smaller ! Access to CV technicians in the clean room for M&O – Assume it is a rare event ! Very dry air from surface -> comfort and electronics? – Poor comfort (manageable), for electronics – to be considered Laser room air-conditioning principal (our proposal) M.Martyanov, CERN21

Attenuated energy option Max 280 mJ Full energy focusing option Max 450 mJ Plasma here Last turning mirror Very smooth focusing Max 100 mJ Focusing geometry, 40 meters Simple propagation of a super-Gaussian beam, no plasma

Focusing geometry, 40 meters Attenuated energy option, Super-Gaussian beam ionizing plasma, 100mJ pulse Ionization ratio in plasma dE = -30mJ