GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 8 NCRs were generated during TMCM preproduction NCR #00029, CLOSED.

Slides:



Advertisements
Similar presentations
SAE AS9100 Quality Systems - Aerospace Model for Quality Assurance
Advertisements

GLAST LAT ProjectF-to-F, March, TrackerR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face March Meeting Robert Johnson.
Quality Management System
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
GLAST LAT ProjectLAT I&T Subsystem CDR, March 28, 2003 Document: LAT-PR Section 4 - Page 1 GLAST Large Area Telescope: I & T Peer Review Performance.
GLAST LAT ProjectTKR Peer Design Review, Mar 24-25, ANick Virmani 1 GLAST Large Area Telescope Tracker Subsystem Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST Large Area Telescope: Manufacturing Preparation Design Engineering Meeting Jerry Clinton 1 April 2003 Stanford Linear Accelerator Center Stanford,
GLAST LAT ProjectMonthly Status Review – Sept. 1, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectMonthly Status Review – December 2, 2004 GLAST Large Area Telescope: Performance & Safety Assurance Darren Marsh SLAC Performance & Safety.
GLAST LAT ProjectSubsystem Managers Face to Face, November 17, GLAST Large Area Telescope: Darren Marsh Stanford Linear Accelerator Center Performance.
Tracker Subsystem1 GLAST LAT Project FM4/5 PSR, May 31, 2005 GLAST LAT Tracker Tower-4/5 Pre-Ship Review INFN-Pisa.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
GLAST LAT ProjectF2F, June 15, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety Assurance Manager.
MRB on SLAC NCR 226 MCM Encapsulation Delamination R.P. Johnson January 3, 2005.
GLAST LAT ProjectFeb. 17, 2004 Hartmut Sadrozinski: TKR Flex Cables 1 TKR Flex Cable Issues addressed TKR Flex Cable Issues addressed Mechanical 1.Grid.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 16 EEE Parts 1 GLAST Large Area Telescope Gamma-ray Large Area Space Telescope.
GLAST LAT Project18 July GLAST Large Area Telescope: NCR 529 Systems Engineering R. Bright Gamma-ray Large Area Space Telescope.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
GLAST LAT ProjectTEM &TEM-PS Manufacturing Readiness Review – September 16, 2004 GLAST Large Area Telescope: Performance & Safety Assurance Pat Lujan TEM.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
GLAST LAT Project May 2, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems.
GLAST LAT ProjectTKR Peer Design Review, Mar 24-25, BNick Virmani 1 GLAST Large Area Telescope Tracker Subsystem Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 GLAST Large Area Telescope: Tracker Subsystem MCM Production Readiness.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001 Robert P. Johnson 1 GLAST Large Area Telescope: Silicon-Strip Tracker/Converter.
GLAST LAT ProjectMay 25, 2006: Pre-Environmental Test Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: Pre-Environmental Test.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
GLAST LAT ProjectMonthly Review, November 3, 2004 Tracker SubsystemP. S. Drell 1 GLAST Large Area Telescope: Tracker Subsystem WBS Persis S. Drell.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: LAT Pre-Ship Review Performance.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR Section 15 Manufacturing Process 1 GLAST Large Area Telescope Manufacturing Process.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Schedule Summary; Critical.
INSPECTION AND ACCEPTANCE CRITERIA. PRODUCT CONFORMANCE Dimensional conformance - within tolerances as defined on product drawing Dimensional conformance.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
10/4/07 Policy Development Division 1 FSIS Directive , Rev.1 U.S. Exported and Returned Products.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: EM Mini-Tower Robert Johnson.
Tracker SSD Ladder Preproduction Review Actions and Changes Since Last Week September 16, 2002 Alessandro Brez Robert Johnson.
GLAST LAT ProjectMonthly Status Review – June 30, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
Tracker Subsystem1 GLAST LAT Project TRAY DELTA MRR, 18 Nov., 2004 GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at.
GLAST LAT ProjectMarch 24, F Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS F: Tray assembly A. Brez I.N.F.N.
MRB on SLAC NCR 226 Excess of Disconnected MCM Channels R.P. Johnson November 9, 2004.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: Electronics Module Testing.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 100 EFW DFB Systems Assurance Trent Taylor LASP.
GLAST LAT ProjectMonthly Status Review – Nov 3, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectMonthly Status Review – December 15, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren Marsh SLAC Performance & Safety.
GLAST LAT ProjectMarch 24, E Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS E: MCM Assembly Gamma-ray.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Electronic Parts & Materials.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 J. Clinton 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 LAT QA has hired a full-time on-site representative (Donald Knaepple)
GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 Survey & Process Review conducted at Teledyne on Nov. 14, 2003.
Cable MRB July 13, 2005 R.P. Johnson. July 13, 2005R.P. Johnson2 Cable Status Needed in Italy to support Tower 8,9 Environmental Testing July 19.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 100 EFW DFB Systems Assurance Trent Taylor LASP.
01.Oct.01 SPIRE BSM Product Assurance Team Briefing 1 BSM Product Assurance Plan Team Briefing & PA plan roll-out Ian Pain.
Tracker Timing Margin MRB R.P. Johnson U.C. Santa Cruz October 15, 2004.
Procedure for MCM rework on tray MID 070
EFW DFB Systems Assurance
EFW DFB Systems Assurance
9.0 Nonconforming Product Lifecycle
GLAST Large Area Telescope:
Preproduction Status & Results
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 8 NCRs were generated during TMCM preproduction NCR #00029, CLOSED –Re-qualification of Omnetics connector is required based on process and design revision. NCR #00041, OPEN- Cause and Corrective Action submitted –Finish machining dimensions did not meet dimension specified on drawing. –Configuration management process was not adhered to, released drawing was not revised and re-released to reflect correct dimensions. –Tracker meeting held to review drawing release & configuration management process. –Drawing was updated with correct finish machine dimensions and released. PWBs were re-inspected per released design. NCR Summary

GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 2 NCR #00042, OPEN- Cause and Corrective Action submitted –One PWB dispositioned “scrap” for exposed copper –One PWB dispositioned “scrap” for foreign material/stain –Qty 9 TMCMs RTV for re-label of Serial No. Traceability maintained, Re-inspection will be performed. NCR #00043, OPEN- Cause and Corrective Action submitted –Omnetics connector saver is being redesigned; 1) Jack screw too long. 2) Gap under jack screw introducing stress and bond of plastic body to alum. shell fails. 3) Low shear strength of bond line. –Redesign complete, NCR will remain open until redesign verified. NCR Summary

GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 3 NCR #00044, OPEN- Cause and Corrective Action submitted –GSFC rejected dielectric thickness per IPC-6011, Class 3 –Configuration management was not adhered to. TMCMs were built to unreleased rev. 6. –Tracker Meeting held to review configuration management process. –Design released, parts meets dielectric requirement. NCR #00046, CLOSED –Teledyne reported SN 176 to have physical damage to Pitch Adaptor traces. Unit passed Final Electrical Test. –Disposition preproduction unit “use-as-is”. Teledyne reviewed handling procedures to preclude recurrence. NCR Summary

GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 4 NCR #00048, CLOSED –GSFC rejected panel #152 coupon test for internal annular rings shorter that inches. –Audit performed on all PWBs in bldg. 33. –152-2 & scrapped. –152-1, 152-3, were utilized in non-flight preproduction MCMs. These MCMs are marked non-flight, introduction into flight stream is not possible. NCR #00050, CLOSED –GSFC rejected panel #158 coupon test for internal annular rings shorter that inches. –All nonconforming PWBs (qty 4) located and quarantined in Bldg. 33 MRB cabinet. NCR Summary

GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 5 Waivers were requested and granted during TMCM preproduction for the following: –Source inspection not performed Source Inspector hired –Reject compound wire bond per MIL-STD-883 Test in process to translate original wire bond on die off - center to allow room for re-bond if required. –Second application of encapsulation to cover exposed wire bonds near ends of TMCM. Standard rework instructions developed –Wire bond over disturbed metal Test in process to translate original wire bond on die off - center to allow room for re-bond if required. Preproduction Waivers