ABB Summary: ABB Suite of Power Transmission Test Cases Mats Larsson Corporate Research ABB Switzerland Ltd. Jan 19, 2004
Collapse Scenario Line tripping (L3) after 100 s Inherent Load Recovery Tap Changer Tries to Restore Voltage Generator field limit activated at 286 s Collapse Tap Controlled LoadGenerator Voltage Overload limit reached Tap Changer Control
Control Objectives Stabilize all voltages within p.u. Use minimal amount of load shedding Control voltage at bus 4 as close as possible to 1 p.u. Capacitor and tap changer control can be used freely
“ Medium Scale” ABB Test Case Three copies of small case Similar control objectives Recovery dynamics in : load (continuous) Transformers (discrete) Inputs: Line impedances (disturbance) 3 Capacitors 3 Voltage Refs. Transformer (optional) 3 Load shedding Outputs: 3 Load voltages 2 Generator field voltages
Case 1 – Tripping of Lines Vload[2]Vload[3] GEfd[2]GEfd[3] pos[2]pos[3] Collapse in 400 secs
Case 2 – Cap Switch in Area Vload[2]Vload[3] GEfd[2]GEfd[3] pos[2]pos[3] System.C2.step Cap switch at 100 secs stabilizes
Case 3 – Tap Reference Change (-5%) Vload[2]Vload[3] GEfd[1]GEfd[2] pos[2]pos[3] Tap reference at 100 secs stabilizes
Case 4 – Second line trip Vload[2]Vload[3] GEfd[1]GEfd[2] pos[2]pos[3] No longer stable...
Case 5 – Added load shedding at bus Vload[2]Vload[3] GEfd[1]GEfd[2] pos[2]pos[3] Additional load shedding stabilizes
Model Complexity 6 disturbance inputs - (0,1,2) Control inputs: 3 capacitors - (0,1) 3 load shedding – (0,1,2,3) 3 tap voltage refs – (0.8–1.2) Continuous dynamics: 3 loads (2 dynamic states each) Discrete dynamics: 3 transformers (3 states each) 2 generator limiters (2 states each)
Possible work on new model Scaling of Model-predictive approaches (ETH, Grenoble?) Testing of decentralized schemes (Lund, Grenoble) Requests for customized versions welcome...
Large scale case – CIGRE Nordic 32 52 Discrete control inputs Load shedding Generator voltage setpoints Tap changers 10 Controlled outputs Load voltages 67 Constrained outputs All voltages, generator currents State-space ~ nodes
At 10 s – Gen 4062 Trips Lost generation compensated by hydro units in the north Increased losses in transmission corridor, lower voltage in southern region Generators in the south increase reactive power production Generator Trip – No Emergency Control At 30 s – Gen 1043 and 4042 at limit Voltage support lost in middle and southern parts At 50+ s – Tap changers restore load Further voltage decrease Collapse at 180 s
Generator Trip – Model Predictive Control Time (sec) Voltage (p.u.) V1043 V4012 V4042 Generator trip
Constraint Management Armature Currents