TB 19.4.06 Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.

Slides:



Advertisements
Similar presentations
ALICE TPC Ne/CO2 Gas System. Mixing Rack CO 2 -Removal & (O 2,H 2 O)- Cleaning Rack.
Advertisements

Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
1 Jim Thomas - LBL A Brief Introduction to the STAR Time Projection Chamber Jim Thomas Lawrence Berkeley National Laboratory June 4 th, 2009.
M1 Installation Schedule Plans Burkhard Schmidt Muon Meeting
ALICE TPC field cage status Sardinia May 2004 Michael Hoch Cern-TA2.
Dariusz Miskowiec, TRD status meeting Oct alignment... i.e. how to figure out where the detectors are, and how to use this knowledge in the reconstruction.
Status at P2 C. Lippmann Jan. 22, 2007 TRD DCS workshop at PI, Heidelberg.
TB Peter Glässel, Heidelberg1 TPC Status.
The STAR HFT PXL system is designed to be inserted in situ. Is housed in 2 large frame aligned with rails inside Inner Detector Support. Inserted from.
3 June 2003U. Frankenfeld1 TPC Detector Control System Status.
Malte HildebrandtMEG Review Meeting, 14th February 2007 Report of Run Coordinator Run 2006 Summary Malte Hildebrandt MEG Review Meeting, 14th February.
TPC-Meeting : Københaven Ne-CO 2 Gas System : Status CO 2 - Gas System : Insulating Gap Resistor Rod : –Contacts –Cooling --> Liquid –Cooling -->
February 12 th, 2004 Heidelberg TPC Meeting J.B. TPC SECTOR TEST at T10 May 3 rd – June 2 nd MOTIVATION REQUIREMENTS STATUS OF SYSTEM TIME SCHEDULE CONCLUSIONS.
Development and Performance of the High Voltage Distribution System for the ALICE TRD A. Markouizos, P. Mantzaridis, P. Mitseas, A. Petridis, S. Potirakis,
TPC DCS update. CR3 UX-A/C CR4-Z08 UX-A/C CR3 CR4-Z08 UX-A/C CR4-Y08 Chambers ISEG Chambers Wiener Ethernet RCU Chambers, detector ELMB
GIF++ gas systems 21/01/2014Ernesto, Roberto PH-DT-DI gas service1.
Progress with the TPC gas monitor Dariusz Antończyk Outline : Motivation Simulations Measurements Summary & Outlook.
DC12 Commissioning Status GOALS: establish operating conditions, determine initial calibration parameters and measure operating characteristics for the.
FEE + ROC cooling S. Popescu CERN, U. Frankenfeld, H.R. Schmidt GSI.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters.
TB Peter Glässel, Heidelberg1 TPC Progress.
Calliope ENEA Casaccia MON = monitor MWPC (CH1) T1 = test MWPC (CH3) T2 = test MWPC (BTF,CERN1,CERN2) T = temperature sensor P = atmospheric.
2-3rd. September 2002TPC Collaboration Meeting1 TPC INTEGRATION & SERVICES Mini Space Frame Back Frame Cooling Systems Cables Gas Systems Items Requiring.
, GSI DarmstadtMartin Winkler, GSI DIRACsecondary Beams Annual report on Large-area beam tracking detectors for fast extracted beams Task 8 –
108 Mar 2007L. Musa TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa Outline Pre-commissioning above ground (2006) Preparing for.
ALICE TPC Status, Meeting with LHCC referees ALICE TPC – Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader:
Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish  Certification of field cage…………………
TOF Gas System Project Overview. Content Prototype for Aging tests done for RPC’s TOF Gas System: parameters and module layouts. Special Technology: channel.
STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.
Status of the Remote HV System 10 June 2015 TileCal week, upgrade session Roméo Bonnefoy, Romain Madar and François Vazeille ● Summary of performances.
1 Status and Outlook of the RPC Commissioning Marcello Maggi/INFN-Bari.
RD51-WG7 Report RD51 collaboration week CERN, November 2009 Matteo Alfonsi & Yorgos Tsipolitis RD51 collaboration week CERN, November 2009 Matteo Alfonsi.
LASER CALIBRATION SYSTEM for STAR TPC Alexei Lebedev (BNL) for STAR collaboration  Design and description  Performance  Goals and results  Future developments.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
GIF++ gas systems 11/07/2014Ernesto, Roberto PH-DT-DI gas service1.
Marian Ivanov TPC ExB and V drift calibration and alignment.
Large-Area GEM Detector Development at CMS, RD51, and Fl. Tech – A brief overview – Marcus Hohlmann Florida Institute of Technology, Melbourne, FL PHENIX.
TB Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
CLAS12 Drift Chamber Prototyping
Status of the PSD upgrade - Problems with PSD in Be runs - Modification of cooling system - New temperature control - Upgrade of HV control system - MAPD.
Technical FORUM, Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
YETS activities in n_TOF O. Aberle, S. Montesano (EN/STI)
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
HBD Report Craig Woody BNL DC Meeting January 7, 2009.
1 HBD Commissioning Itzhak Tserruya DC meeting, BNL December 13, 2006 Progress from October 3 to November 28, 2006.
TB Peter Glässel, Heidelberg1 Preparing TPC Installation.
Installation of the T600 at Fermilab CSN2, September 22,
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
André Augustinus 17 June 2002 Detector URD summaries or, what we understand from your URD.
Piquet report Pascal, Yuri, Valentin, Tengiz, Miriam Calorimeter meeting 16 March 2011.
GIF++ gas system Outline:  Beam and cosmic trigger  Gas distribution panels  Gas detection (present and final layout)  Conclusions 14/1/2015R. Guida,
TRD Gas System Layouts Production Readiness Review 03 – Nov F. Hahn.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
The GOOFIE detector as a Ternary Mixture Monitor
Rosario Turrisi INFN Padova
Marian Ivanov TPC status report.
Atlas: Upgrade Phase I Massimo Della Pietra.
Pre-installation and Functional Tests
Gas System Commissioning
LHC Experimental Vacuum Systems Status October ‘07
TPC Field Cage Progress Report
TPC Status Outline Completion of installation 14 September 2006
Alice TPC DCS.
TPC Detector Control System
Presentation transcript:

TB Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg Technical coordinator: Peter Glässel, Heidelberg

TB Peter Glässel, Heidelberg2 Main Activities Front End Electronics ‘Dry’ testing of sectors w/o HV started Laser system Shipped today, to arrive About 1 week (incl weekend) to install and align A-side Cabling Gas system Accorde Drift HV 100 kV (Heinzinger) installed, test with DCS ELMB pt1000 sensor system: Sensors cabled up 90%

TB Peter Glässel, Heidelberg3 C-Side

TB Peter Glässel, Heidelberg4 Accorde is in place Next: complete cabling, setting up trigger

TB Peter Glässel, Heidelberg5 Gas system Gas commissioning started Re-commissioning complete functionality (after software upgrade) With new gas lines (modifications on plug) and dummy volume Improvements on filling cycle: try to speed up filling cycle by using higher pressure, lower temperature on CO 2 absorber TPC gas lines prepared for switch to gas system Start gas system with TPC end of week, filling next week (expected to take 2 to 3 weeks) → mid May Clean room part of system

TB Peter Glässel, Heidelberg6 TRD/TPC heat screen Design done 0.5 mm Al panels with Al water lines (avg 1% X 0 ) Fixed to SF from TPC side with bolts welded to SF Water manifolds along axial SF beams Bidding ongoing Installation before TRD installation (June)

TB Peter Glässel, Heidelberg7 Summary Commissioning started A lot to do before we see the first tracks

TB Peter Glässel, Heidelberg8 -- Spares –

TB Peter Glässel, Heidelberg9 Pre-Commissioning plans, SLXL2 Commissioning of gas system from to ~19.4. Commissioning of Field cage, FEE and ROCs DCS system Drift HV Laser ROC HV Gating Readout chain Trigger for cosmics, laser Online monitoring Verify each sector, at least with laser tracks Tracks (laser, cosmics) with 2 sectors (joining, opposite, …) Commissioning of temperature sensors Move to UX25:

TB Peter Glässel, Heidelberg10 Gas system Previously commissioned with dummy volumes Pre-commissioning with TPC in SXL2 with final gas mixture Control Backup Mixer Purifier CO2 Distr Analys Pump

TB Peter Glässel, Heidelberg kV system

TB Peter Glässel, Heidelberg12 TPC with 2 I-bars During ITS installation, I-bars will be on A-side