Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.

Slides:



Advertisements
Similar presentations
Local Agency Bridge (LABP) Program Overview Informational Presentation – January 7, 2011 Carol Olsen, ODOT LGS Bridge Program Manager Local.
Advertisements

ODOT Structure Project Management Seminar Bridge Preliminary Design Report.
Railway Grade Separations Issues. Railway Grade Separations 1.Introduction Qualifications/experience to undertake bridge planning for railway grade separations:
Project Management Requirements Prof. Ralph V. Locurcio, PE.
Alternatives Categorical Exclusion Training Class.
1 C E T A S Range of Alternatives Presentation Date Project Name Project location (city, county) ODOT Key Number:
Project Prospectus and Design Acceptance Package ( and a little more) Alan Lively Project Delivery Specialist January 30, 2009.
Environmental Assessment Public Meeting
Clinton Street Bridge over the Maumee River ODOT Project DEF December 2, 2014 Stakeholder’s Meeting.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Computers: Tools for an Information Age
Project Management Session 7
إدارة المشروعات Projects Management
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
AGENDA  PROJECT HISTORY  NORTHERN SECTION UPDATE  SOUTHERN SECTION OVERVIEW  INTERCHANGES  PROJECT SCHEDULE  UPCOMING ACTIVITIES  OPEN DISCUSSION.
4 4 By: A. Shukr, M. Alnouri. Many new project managers have trouble looking at the “big picture” and want to focus on too many details. Project managers.
© 2011 HDR All rights Reserved. Value Engineering Ken L. Smith, PE, CVS (360) April 27 th, 2011.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Design Exceptions Presented by David Joe Polly PE, PLS, WRE Senior Standards Engineer Roadway Engineering Unit
Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.
Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting.
IS-700.A: National Incident Management System, An Introduction
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
Initiating and Planning Systems Development projects
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
Demystifying the Business Analysis Body of Knowledge Central Iowa IIBA Chapter December 7, 2005.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
CCJPA Sacramento to Roseville 3 rd Track Project Sacramento Stakeholder Advisory Committee (SAC) Meeting #1 HDR Office Tuesday, May 20, :00 - 9:00.
PLANNING FOR DESIGN Shawn Dikes, AICP FHWA / KYTC / ACEC Partnering Conference 2015.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Product Documentation Chapter 5. Required Medical Device Documentation  Business proposal  Product specification  Design specification  Software.
PROJECT SCOPING FOR LOCAL AGENCY FEDERAL AID PROJECTS.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
Local Government Section Welcome Marty Andersen ODOT Local Government Section 355 Capitol Street NE, Rm. 326 Salem, Oregon Ph:
Project Life Cycle – Project Initiation © Ed Green Penn State University All Rights Reserved.
1 C E T A S Purpose and Need Presentation Date Project Name Project location (city, county) ODOT Key Number:
1 C E T A S Triage Presentation, Date Project Name Project location (city, county) ODOT Key Number:
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
April 9, 2011 Mike Wieszchowski, P.E., PTOE Professional Traffic Operations Engineer Road Use Planning Guidelines to Protect Your Roadways.
Applied Software Project Management
Introduction Session 01 Matakuliah: S0753 – Teknik Jalan Raya Tahun: 2009.
Chapter 15 Introduction to Systems Development. Learning Objectives Learn how information systems are developed Understand importance of managing SD process.
2 nd Knowledge Area : Project Scope Management. Importance of Good Project Scope Management 1995 CHAOS study cited user involvement, a clear project mission,
Information System Project Management Lecture three Chapter one
Locally Administered Federal-Aid Project Initiation Workshop Prospectus Part 3 and NEPA Requirements Presenter: Howard Postovit; ODOT Region 5 Region Environmental.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Chapter 6: THE EIGHT STEP PROCESS FOCUS: This chapter provides a description of the application of customer-driven project management.
Contractor Alternate Design Serving the Public’s Best Interest.
Project Development Process. ODOT’ PDP A project management and transportation decision-making tool. Developing the detail to the level necessary to make.
1 Introduction to Value Analysis Caltrans Delivers Value By Renee Hoekstra, CVS RH & Associates, Inc. for Caltrans.
د. باسم ممدوح الحلوانى Lecture 3 Scope Management.
Public Involvement. Why? Who Cares? –What we do matters to the public –Effective PI enables proactive input and enhances the decision- making process.
Salt Lake City – Las Vegas High Speed Rail – Alignment Study Student Engineering Associates.
Project Scoping. Project Scoping – learning objective Who should complete the Project Initiation Package (PIP)? How is PDP Path used in scoping? Task.
August 19, 2015 Port Bienville Rail EIS Scoping Meeting Presented by: Rhea Vincent Mike McGuire.
ANALYSIS PHASE OF BUSINESS SYSTEM DEVELOPMENT METHODOLOGY.
SCOPE DEFINITION,VERIFICATION AND CONTROL Ashima Wadhwa.
Project Management Requirements Prof. Ralph Locurcio, PE Dr. Troy Nguyen, PE.
The Project Concept Phase - Concept Report Requirements Presented by the Georgia Department of Transportation Roxana Ene – LCI Coordinator
PURPOSE & NEED Categorical Exclusion Training Class.
Rob Connatser NSS Instrument Work Packages and XLPM.
Prof. Shrikant M. Harle.  The Project Life Cycle refers to a logical sequence of activities to accomplish the project’s goals or objectives.  Regardless.
Value Engineering Study and Risk Assessment
FOR LOCAL AGENCY FEDERAL AID PROJECTS
Chapter 3: Cost Estimation Techniques
FOR LOCAL AGENCY FEDERAL AID PROJECTS
Project Scope Management
Chapter 3: Cost Estimation Techniques
Presentation transcript:

Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010

Project Scoping Fundamentals PROJECT SCOPE – The work that must be done in order to deliver a product with the specified features and functions. PROJECT SCOPE MANAGEMENT – The processes required to ensure that the project includes all work required to complete the project successfully.

The purpose of Draft STIP Scoping Establish the problem statement Develop solutions and options Develop cost estimates Develop a schedule Identify impacts right-of-way, environmental, utilities Identify stakeholders

NEED FOR PROJECT SCOPING

Scoping is the foundation upon which your entire project is built Just as you would not consider building a house without a proper foundation, you should not consider developing a project without a proper scope Your project is only as good as the foundation upon which you built it

What is the problem What are the alternatives What are the impacts What are the goals of your project Scoping verifies and documents the purpose and need for your project

Verifies and fixes the right problem Project is correctly programmed Project is kept within budget and on schedule Benefits of Good Scoping

Months of wasted time Hundreds of hours of staff time Thousands of dollars in PE costs Millions of dollars in construction costs Proper Scoping Can Save You

Project scoping is based on several concepts. They provide the basis for the process by which scoping is done The concepts include teamwork, public and stakeholder participation, informed decision making, and proper documentation Basic Concepts of Project Scoping

Teamwork Project scoping is collaborative effort involving team work among diverse stakeholders to identify problems an propose solutions The project team plays a critical role in identifying and evaluating issues/concerns to appropriate depth and detail

Stakeholder participation is the cornerstone of successful project scoping and design Know who your stakeholders are Reach out to them at the beginning of scoping Stakeholder Participation

Projects require a level of scoping commensurate with the type of proposed work. Project data requirements depend on a projects problems and needs, complexity, significance of issues, scope and scale of alternatives to be evaluated. Informed Decision Making

Project needs can be clearly understood Stakeholders issues can be identified Clear project objectives can be established Environmental considerations are identified Feasible alternatives are outlined/compared Project cost and schedule can be estimated Sufficient data needs to be gathered to ensure:

Proper Documentation Clear and concise documentation and good record keeping is essential. Project documentation provides a clear picture of what is to be accomplished It is used to grant scope approval and provides information for future stages of the project development

GETTING STARTED Project Research Scoping Team Scoping Site Visit Project Prospectus Estimate

OFFICE RESEARCH

Project purpose and need statement What is the problem we are trying to correct Design standards to be used – Does the current alignment meet standards Current and future traffic volumes- Build year and design year

Accident history, accident rate, analysis of accident “hot spots” Existing pavement conditions and preliminary ideas for surfacing treatments Bridge inspection reports and recommended actions Vicinity maps, Right of Way Maps, and as constructed drawings

SCOPING TEAM

SCOPING TEAM MEMBERS Project Leader (Local, ODOT/Consultant) Engineering - Roadway, Bridge, Traffic Right of Way Environmental Utility Specialist Construction Project Management

Additional Members Geo/Hydro Pavements Planning Surveying Rail Safety Public Affairs Access Management

SITE VISIT

Take good notes and document Safety concerns and possible solutions Pavement conditions and surfacing design alternatives Stage construction concerns and alternatives Right of Way impacts and needs

LOOK FOR Access issues Utility impacts Pedestrian and bicycle needs ADA needs, ramps, sidewalks, driveways Level of Survey work required

AND THESE Environmental impacts –Wetlands –Hazmat –Threatened and Endangered Species (ESA) –Historic –Archaeological

The project prospectus is a tool to convey information about a project to various organization inside and outside of ODOT It starts the process of identifying the problem to be solved and presents ideas on how to solve it PROJECT PROSPECTUS

It contains information on the Project: –Costs –Funding sources –Funding years –Right of Way impacts –Environmental impacts

Its Divided into Three Parts Part 1 - Project Request Part 2 – Project Details Part 3 – Project Environmental Class

The project location Overview of the project Problem statement Proposed solution Cost estimates for PE, CE, Right of Way, and construction Part 1 provides information on:

Who is responsible for completing the different categories of the project design Base design requirements Roadway element widths Structure size and cost Right of Way information Part 2 defines:

Details environmental impacts Environmental baseline information Require permits, reports and clearances and The items in Jerry’s presentation Part 3 – Environmental details:

Preliminary Schedule & Cost Estimate

Schedule Create a preliminary schedule, based on the input from the scoping team members. to help determine which year the project can be delivered for use on of ODOT’s MS Project schedule templates.

Keys to a sound estimate Identify all the major elements tasks and bid items required for the project Research and assign reasonable unit prices to all items

Questions? Questions? Alan Lively Project Delivery Specialist Local Government Section ODOT, Local Government Section 355 Capitol Street NE, Room 326 Salem, OR