ECOSTILER, coordinators MEETING October 22, 2012
Demo sites Amsterdam New West London Lambeth Måbjerg
Amsterdam 84 months highlights All refurbishment demo’s complete (468 dwellings, m2) Biogas plant in waste to energy plant complete Exhaust gases in waste incinerator tested with good results: significantly lower emissions District heating backbone of 12 km complete, current connection rate about 4000 dwellings/year Renewables support program complete Monitoring of dwellings completed
Monitoring results On average, 33% energy savings by refurbishment. Quality of work is a major issue
London Lambeth 84 month highlights All planned refurbishment buildings complete (571 dwellings, m2) CHP installations complete, but being optimized R&D program complete
Måbjerg 84 month highlights Biogas plant construction started August 2010 All related research finalized Official opening June 18, 2012 Auditing and energy monitoring of Farms completed Energy efficiency measures in stables have been executed.
Måbjerg impressions Production volumes Biogas18,6 mio. m 3 / year Liquid fertilizer tons / year
Energy management in farms
Yet to do, lessons Amsterdam, London, Måbjerg Finalizing reporting All major demonstrators have been accomplished Lessons Monitoring should have been approached differently from the beginning Energy reductions are in part consumed as comfort increase
Progress summary