STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Science Team Meeting May 2, 2005 Presented by Edward Reynolds APL STEREO Project.

Slides:



Advertisements
Similar presentations
Superior Solar Conjunction Planning May 8, 2014 Dan Ossing STEREO Mission Operations Manager (240)
Advertisements

Watch the following video and answer the questions on your question sheet. Importance of Testing.
STEREO Science Center Status Report William Thompson NASA Goddard Space Flight Center Phase E Kickoff Meeting February 23, 2007.
Project X pedition Spacecraft Senior Design – Spring 2009
IMPACT Report SSMO Receiving Review– January 23, 2007.
GLAST LAT Instrument GLAST Monthly Mission Review October 29, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview October 29, 2007 Ken.
GLAST LAT Project ISOC Peer Review - March 2, 2004 Document: LAT-PR Section 2.3 Verification and Validation 1 Gamma-ray Large Area Space Telescope.
Constellation Orion Visible Light Constellation Orion Infrared Light.
Lunar CRater Observation and Sensing Satellite Project LCROSS Site Selection Workshop Oct , 2006 NASA/ARC, Mountain View, California LCROSS Orbital.
STEREO Science Center SWG – Dec 2004 William Thompson NASA Goddard SFC Code Greenbelt, MD
STEREO Science Center SWG – May 2005 William Thompson NASA Goddard SFC Code Greenbelt, MD
Comet Impact: July 4, 2005 Impact Velocity: 23,000 mph Spacecraft Size: Flyby spacecraft - nearly as large as a Volkswagen Beetle automobile. Impactor.
STEREO IMPACT SEP Critical Design Review 2002-Nov-20 TvR IMPACT/SEP Thermal Design John Hawk, GSFC (301)
IMPRS June Organigram of ESA, in the late 1980s
STEREO Media Activities Rachel A. Weintraub NASA Public Affairs Officer / TV Producer Dec STEREO Working Group.
THEMIS FRRSC - 1 KSC, Feb 12, 2007 SPACECRAFT OVERVIEW/STATUS Peter R Harvey THEMIS Project Manager.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
Satellites and Launch Vehicles. “Gee Whiz” Facts Number of satellites currently in orbit is over 900 Satellites orbit at altitudes from 100 miles (Low.
5-1 Constellation Space Suit System Government Capabilities and Facilities Crew and Thermal Systems Division.
NASA’s Goddard Space Flight Center LRO Operations Concept Richard Saylor Jr. HTSI/Code 444 August 16-17, 2005.
20a - 1 NASA’s Goddard Space Flight Center Attitude Control System (ACS) Eric Holmes, Code 591 Joe Garrick, Code 595 Jim Simpson, Code 596 NASA/GSFC August.
( ELR) - 1 STEREO - Solar Terrestrial Relations Observatory Mission STEREO SWG STEREO OBSERVATORY Status Edward Reynolds APL STEREO Project Manager.
Van Allen Probes Spacecraft Operations July 29, 2015 Kristin Fretz
Rachel Weintraub Public Affairs Officer & TV Producer NASA Goddard Space Flight Center More information:
The Solar System Chapter 6 COPY DOWN THE LEARNING GOALS ON PG SKIP 5 LINES BETWEEN EACH!
1 Observatory I&T and Launch Campaign Flow Greg Jones May 20, 2009 JWST-PRES
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
Spacecraft and Ground Segments Status March 21, 2014 Dan Ossing STEREO Mission Operations Manager (240)
STEREO Science Center Status Report William Thompson NASA Goddard Space Flight Center STEREO SWG April 2008 Meudon, France.
Polar Gateways 2008THEMIS Constellation Operations − Jan 2008 THEMIS Constellation Operations Dr. Manfred Bester University of California at Berkeley.
Michael L. Kaiser STEREO Project Scientist NASA/Goddard Space Flight Center STEREO June 11, 2008 STEREO at 1.4 years.
1 JWST Functional Flow Diagrams and Schematic Block Diagrams.
Deep Impact FRRJan. 8, 2005Page 1 Deep Impact Overview/Status Flight Readiness Review January 8, 2005 Rick Grammier Project Manager.
Proprietary BalloonWinds Update Author: Ivan Dors – UNH Presented By: Michael Dehring -- MAC 28 June 2006.
STEREO Science Center Status Report William Thompson NASA Goddard Space Flight Center STEREO SWG March 27-28, 2007.
Mission Operations –Launch February 15, 2000 at 22:02:15 UTC = 14:02:15 PST –41 Days IOC and antenna deployment period –2 year science mission operations.
Instrument Status GLM Science Team Meeting 9 September 2016 Marc Rafal/GSFC GLM Instrument Manager.
24b - 1 NASA’s Goddard Space Flight Center LRO Safety Dave Bogart Code 302 August 16-17, 2005.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
Telemetry Constraints during Early Operations The STEREO telemetry rate is restricted during the phasing orbits due to S/C RF interference with each other,
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
1 System Architecture Mark Herring (Stephen Merkowitz Presenting)
Michael L. Kaiser STEREO Project Scientist NASA/Goddard Space Flight Center STEREO May 2, 2008 STEREO at 1.25 years.
S. Frey, UCB, THEMIS 1 25th ISSFD, Munich, Germany, Oct.19-23, 2015 ARTEMIS THEMIS ARTEMIS The Revised Concept of the THEMIS and MMS Coordination Sabine.
SWT Overview 1 UCB, Nov15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Mission Overview Peter R. Harvey Project Manager University of California - Berkeley.
Solar Probe Plus A NASA Mission to Touch the Sun Mission Operations Review News Elena Adams 7/16/2015.
STEREO Science Center Status Report William Thompson NASA Goddard Space Flight Center STEREO SWG November 2007 Pasadena, California.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
THEMIS MRRI&T − 1GSFC, January 5, 2007 Integration and Test.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR Section 5 IOC Subsystem 1 GLAST Large Area Telescope: IOC Subsystems WBS: 4.1.B.
THEMIS MRRSystems - 1 GSFC, Jan 5, 2007 Systems Engineering.
SSC Preflight Status Tested during Sim #3: –Telemetry ingest –Beacon processing –Science planning –Archiving of MOC data products, including level-0 telemetry.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration with PFP, Qualification, ATLO 2011 March 28 Dave Curtis.
EDGE™ Preliminary Project Plan P09102 – METEOR Stage Separation System JJ Guerrette (ME)
Lunar Reconnaissance Orbiter (LRO) SRR/Mechanical System August 16-18, 2005
Power Philip Luers NASA/GSFC Code 561 August 16-17, 2005.
Gayle K. Martin November 14, 2016
CINEMA System Engineering
Maxim Pathfinder Prework 16 August 1999
Technical Resource Allocations
FIELDS SCM Thermal iPER
0.0 Instrument Suite Name Presenter’s name
Current SOC-Ground System Integration Schedule (Jan )
The Moon Image Credit: T.Rector/NOAO.
SDO Flight Dynamics Subsystem
GLAST Large Area Telescope: Cost/Schedule Review September 1, 2005
Launch and On-orbit Checkout
Integration and Test Organization Chart
LAT Operations Scenario Subsystem Meetings
The Deorbiting of GOCE – A Spacecraft Operations Perspective
Presentation transcript:

STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Science Team Meeting May 2, 2005 Presented by Edward Reynolds APL STEREO Project Manager

(ELR 4/29/05) - 2 STEREO - Solar Terrestrial Relations Observatory Mission STEREO General Status Observatory Integration status –Core spacecraft integration is nearly complete –Both spacecraft are ready for instrument integration Mission Operations Center –Facility complete and equipment operational –MOC facility used for Mission Simulations and DSN tests –POC facility ready for instrument teams Four Mission Simulations performed on each spacecraft Five Dress rehearsals performed using equipment and personnel being planned.

(ELR 4/29/05) - 3 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Spacecraft Stacking Operations

(ELR 4/29/05) - 4 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Spacecraft Stack – Dynamics Load Testing

(ELR 4/29/05) - 5 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Integration Status Spacecraft integration at APL –Both spacecraft integrated within the same room –Facility controlled for contamination, ESD, and security –Spacecraft to remain at APL until after stacked vibration testing Most environmental testing to occur at GSFC –Acoustics, thermal vacuum, shock, ESD, mass properties Launch activities will occur over a 11-week period –While at GSFC and Launch site, spacecraft will be controlled from MOC at APL –Project will follow security procedures of KSC/CCAFS –Background checks need to be submitted in a timely manner –Visitors and guests will be escorted when required –Once spacecraft is fueled, access around it will be limited to essential personnel

(ELR 4/29/05) - 6 STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO I&T Flow

(ELR 4/29/05) - 7 STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Recent Accomplishments -Hi-Shear under contract for Pyro Sep-Nuts (replaces STARSYS QwkNuts) -DSN/CTT Testing Completed on Spacecraft A & B -Performance and Operations -Power, RF, G&C subsystems integrated on Spacecraft A & B -Propulsion system integrated and leak tested on Spacecraft A & B -IEM B cold lock-up root cause identified and mitigated, -IEM B integrated on Spacecraft -Mission Sim #1 on both Spacecraft A & B -Launch, Separation, Detumble, 1 st contact, delta-V and momentum dumps, EA mode -IMPACT IDPU & Boom Integrated on Spacecraft A -Command Loss Timer Test (72-hour) Spacecraft A -85% of thermal blanketing complete -Flight batteries ready for integration -Solar arrays delivered and undergoing flash illumination testing -HGA assemblies completing TV chamber testing (deployments, actuations)

(ELR 4/29/05) - 8 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Photo Gallery

(ELR 4/29/05) - 9 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Educational Video Production

(ELR 4/29/05) - 10 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Mission Orbit Sun Earth +22  /year -22  /year Heliocentric Inertial Coordinates (Ecliptic Plane Projection) Ahead Behind Earth 1 yr. 2 yr. 3 yr. 4 yr. 1yr. 2yr. 3 yr. 4 yr. 5 yr.

(ELR 4/29/05) - 11 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Phasing Orbit Mission Timeline Launch: Feb. 11 – 24, 2006 ~4:00 am EST S1: April 8, 2006 S2: May 16, 2006 Lunar Orbit +22°/yr Ahead -22°/yr Behind 4.5 Revolutions in Phasing Orbit First lunar swingby, S1 –Behind escapes –Ahead spacecraft enters 1 month ‘outer loop’ Second lunar swingby, S2 –Ahead escapes  To Sun A1 A2 A3 A4 A5 S1 S2

(ELR 4/29/05) - 12 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Day 1 (11-Feb) Phasing Orbit Schematic A1 7.2 / 77 A / 137 TIP 42 min / h=178 km C3 = -1.6 km 2 /s 2 P / 1.32 P / 1.58 P / 1.80 P / 2.21 S S Behind Ahead Key Event ID Elapsed Time (days)/Distance (Re) A / 77 A / 65 A / 65 = Planned  V = TCM  V Summary Min. Perigee Altitude = 2,036 P1 Lunar Flyby Radius: S1: Ahead = 12,361 km, Behind = 8,105 km S2: Ahead = 16,214 km

(ELR 4/29/05) - 13 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Spacecraft Mission Operations Mission Operations Center Facility MOC Space Command Pit HIL A HIL B B Primary Backup A Primary Backup Assessment Workstations Engineering Display Workstations

(ELR 4/29/05) - 14 STEREO - Solar Terrestrial Relations Observatory Mission STEREO Spacecraft Mission Operations Mission Operations Center Facility – At APL POC Space