NCSX NCSX Project Update Hutch Neilson, Project Manager for the NCSX Team Princeton Plasma Physics Laboratory Oak Ridge National Laboratory Briefing for.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
Hutch Neilson NCSX Project Manager Princeton Plasma Physics Laboratory Oak Ridge National Laboratory NCSX Research Forum #1 Princeton Plasma Physics Laboratory.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Server Virtualization: Navy Network Operations Centers
September 30, 2003 NCSX Modular Coil Winding Form Prototype FDR1 NCSX Prototype Modular Coil Winding form FDR Phil Heitzenroeder PPPL September 30, 2003.
1 BROOKHAVEN SCIENCE ASSOCIATES Plans for LOBs and Site Master Plan Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
SC Project Review of NCSX, April 8-10, 2008 NSCX Poloidal Field Coils Michael Kalish.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Hutch Neilson Princeton Plasma Physics Laboratory Stellarator Team Meeting 3 March 2011 Stellarator Program Update.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
SC Project Review of NCSX, April 8-10, 2008 Ron Strykowsky - page 1 Office of Science NCSX Project Review of NCSX April 8-10, 2008 Cost and Schedule Ron.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Anthony Indelicato DOE-Princeton Site Office May 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the NSTX.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
1 | Program Name or Ancillary Texteere.energy.gov Water Power Peer Review Abrasion Testing of Critical Components of Hydrokinetic Devices Monty Worthington.
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
NCSX NCSX Trim Coil Peer Review 11/6/07 1 Tom Brown Art Brooks Raki Ramakrishnan Mike Kalish NCSX Trim Coil Peer Review.
NCSX NCSX Project Meeting Wayne Reiersen 15 December 2004.
NCSX NCSX Vacuum Vessel R&D, Risk Management and Manufacture NCSX Preliminary Design Review October 7-9, 2003 Princeton, NJ Mike Viola, Phil Heitzenroeder,
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
NCSX Project Overview and Management Hutch Neilson, NCSX Project Manager Princeton Plasma Physics Laboratory Oak Ridge National Laboratory Office of Science.
NCSX November 18-20, 2003NCSX Performance Baseline ReviewMichael Viola 1 NCSX Vacuum Vessel R&D, Risk Management and Manufacture Mike Viola, Phil Heitzenroeder,
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
AWB Dimensional Control Requirements for the Modular Coils and TF coils Field Period Assembly Peer Review October 11-12, 2006 Art Brooks.
Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014.
SchedulingProducingControllingSchedulingProducingControlling.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
The categories for ILC budget planning are: R&D – work done in laboratories to develop and verify subsystem components. This supports the cost reduction.
PPPL Stellarator Program Overview Hutch Neilson NCSX Project Manager NCSX Program Advisory Committee Meeting #6 Princeton, NJ December 9, 2002.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
Vendor Date VALU Monthly Project Review (VMPR) Project Name/IN #
Time to resolve Design Issues 1. Disclamer Due to the engineering meeting last week I have not had time to coordinate this material with Tim or the L3.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Anthony Indelicato DOE-Princeton Site Office December 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
NCSX Vacuum Vessel Fabrication
Status of the MICE Construction Project
External Independent Review (EIR)
Conventional Facilities
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

NCSX NCSX Project Update Hutch Neilson, Project Manager for the NCSX Team Princeton Plasma Physics Laboratory Oak Ridge National Laboratory Briefing for Office of Fusion Energy Sciences June 24, 2005

NCSX 2 MCWF Delivery Delays Will Impact the FY-05 Joule Target But Not CD-4 (July, 2009) Vendor’s best case forecast: MCWF#1 will ship July 30 (an 11-week slip). Manufacturing process development requirements were under-estimated by the vendors. Because of this, the schedule for MCWF#1 has grown: –2 weeks in pattern-making, 4 weeks in casting, 5 weeks (projected) in machining. Machining issues encountered so far have been resolved and should not recur. –The solutions that were found apply to all remaining units. –Vendor believes their original 12 week projection still holds for remaining castings. Pattern and casting delays have not recurred. –Pattern #2 has now been produced, #3 (the last) has been started. –Castings are now being poured near the rate planned (every 3 weeks). 4 castings have been poured. Vendor estimate of the remaining time to complete MCWF#1 is probably optimistic. A factor of 2 underestimate of remaining work would put delivery in mid-September, but… The baseline schedule is robust to delays in MCWF production: –MCWF#1 could slip to Sept. 30 without impacting CD-4 or schedule float (5 months). –Machining time on remaining units could grow to 20 weeks, also with no impact. We will not complete the FY05 Joule Target on schedule (Sept. 30). –By Sept. 30, winding activities will be under way on modular coil #1. –We will complete winding the first coil (the Joule target) before Dec. 31.

NCSX 3 MCWF Delivery Is Delayed By Unexpected Growth in Non- Recurring Vendor Development Activities Delays were experienced in each phase. –2 weeks delay in producing the first pattern. Patterns now well off critical path. –4 weeks in the casting phase. oWeld upgrades and re-inspection took more time than expected. oCause was determined and corrected by pattern modifications. oWe are now seeing shorter lead times on subsequent castings. 12 weeks for #2 vs. 16 weeks for #1. Castings #3 & #4 are poured and in-process. –5 weeks in the machining phase. oDevelopment of optimum machining strategies took more time than expected. oUse of the MCWF prototype for machining development has partially mitigated the schedule impact. Although they under-estimated the development requirements, the vendors have used their resources proactively to mitigate schedule risks. High quality standards are being maintained.

NCSX 4 MCWF #1 Casting Problems Have Not Recurred Pattern modifications after #1 were successful. –Post-pour processing time on casting #2 (ready to ship from foundry) was 3 weeks less than #1. –#2 was produced in 12 weeks, per original plan. Castings are now being poured near the rate required to support their baseline delivery schedule. Those with the tightest schedule requirements (first 4) have already been poured. Pour dates: #112/20/04 #24/15/05 #35/24/05 #46/10/05 #57/8/05 (F) F = forecast 16 weeks 6 weeks 3 weeks 4 weeks (F)

NCSX 5 Weeks 1-3. Initial roughing went well. Weeks 4-6. Optimized deep “plunge cutting” roughing machining. –Changes were made to reduce chatter and vibration which were initially encountered. oSmaller machining heads used to permit better access and reduce cutting tool extension. oMachining fixtures were stiffened. oComputer Aided Machining (CAM) variables including tool size, tool path and feed rate, rpm’s, were optimized. –Result: roughing got back on track with better performance than originally planned. –Solution will benefit remaining units. Machining Process Optimization on MCWF#1 Will Benefit Remaining Units

NCSX 6 Weeks 7-8: Poloidal break machining completed. –Operation went very well; no spring back or casting deformation was encountered. Week 8. Contour milling process optimized. –Machining rate greatly improved by using a new type of machining cutter. –Computer Aided Machining (CAM) variables including tool size, tool path and feed rate, rpm’s. were optimized. This Experience and Investment in Optimization Will Benefit All Remaining Units. Poloidal Break Machining Was Easy. Contour Machining Has Been Optimized.

NCSX 7 Major Tool Is Working to Mitigate Schedule Risks in the Remaining Operations 3 axis machining operations on MCWF#1 – to be completed by July 8. In parallel, the prototype is being used to develop the 5 axis and finish machining operations. –Using the prototype in this way will: improve the efficiency of these final operations, verify the CAM program, and reduce risks of machining errors. 5 axis and finish machining operations – to be completed by July 19. Final tests (liquid penetrant examination; x-ray inspection; magnetic permeability) and inspections (surface finish; dimensions) – to be completed by July 29. –NCSX engineers, QA specialists, and DCMA specialists will be on site to assure that any issues which develop can be quickly addressed. –Dimensional inspection methodology, requirements, and reporting will be discussed in on-site meeting next week to assure common vision. –NCSX and EIO have started compiling the MCWF#1 documentation package to assure that no issues will remain to be resolved which may impact shipping. oMaterials test data show that properties meet and may exceed requirements. Ship – by July 30.

NCSX 8 Vendor Estimate to Complete MCWF#1 is Probably Optimistic But Project Can Accommodate More Delay Vendor’s July 30 delivery forecast is their best case scenario. Incorporates lessons learned to date, but the potential for further surprises and delays cannot be excluded. –5-axis machining operations are new ground. Prototype development should reduce, but may not eliminate, schedule risks. –Inspection and testing could stretch out if there are issues requiring analysis or re-work. The time to complete remaining work could double, delaying delivery to mid-September. The project baseline could accommodate this much delay, or more.

NCSX 9 The MCWF Plan Supports the Project Schedule In re-planning the project to accommodate reduced funding, we built in some float between EIO’s MCWF delivery milestones and the project’s. We did not rebaseline the MCWF contract. They are working to get back to the original schedule. EIO forecasts that MCWF #1 through #6 will be delayed by 11, 11, 9, 7, 6, and 5 weeks relative to the contract baseline. –Patterns: 2 of 3 have been fabricated. #3 has been started and is well off critical path. –Casting: #2 was produced within the 12-week estimate. Castings are being poured at the rate needed to support the schedule. –Machining: Major Tool and EIO stand by the 12-week estimate for remaining units. Some new issues are expected on the first of each type, but the additional development time needed on #1 is not expected to recur.  To gain confidence, we will work with vendor to better understand the basis for their estimates and increase visibility of intermediate milestones. Site visit next week. Dramatic schedule improvements in repeated engineering tasks are normal: –Machining of W7X coil cases: 1200 hrs. on #1, 400 hrs. after 4-5. (4:1 improvement) –Winding of NCSX twisted racetrack coil: 1/2 turn/day at start, 2 turns/day at finish (4:1) –Winding of NSTX PF1a: first coil 11 weeks, second coil 5 weeks (2:1) –Diamond Wire Cutting in TFTR D&D: first cut 4 weeks, last cut 1 week (4:1).

NCSX 10 Winding Form Delivery Schedule

NCSX 11 Project Schedule Basis and Risk Mitigation Basis for Winding Operations Baseline Plan –First coil will take 50% longer than subsequent coils. –2 winding stations with 3 teams. Third team dedicated to 2 nd shift on first 10 coils –All shifts 5 days/week –Conductor installation (70% of winding operations) assumes 10 hour days Risk mitigation flexibilities –Continue 2 nd shift operations for last 8 coils –Add a fourth winding team providing capability to wind two coils on 2 shifts –Additional overtime –Saturday and Sunday work Conclusion –Unexpected MCWF delivery delays were an identified risk that was mitigated in our planning.

NCSX 12 History and Resolution of the FY-05 Joule Performance Target “Award, through a competitive process, production contracts for the NCSX Modular Coil Winding Forms, Conductor, and Vacuum Vessel. Complete winding of the first Modular Coil.” History Dec. 15, Project and DOE agreed on the FY-05 target in its present form. –MCWF was in final design. Project’s estimated MCWF#1 delivery date was Dec., Sept. 10, Project informed DOE that the FY-05 target was at risk. –At this point we had received and agreed to EIO's contract proposal in which the MCWF#1 delivery would be May 15, Apr. 19, Project reported to DOE that MCWF#1 would slip to June 24. FY-05 target at increased risk. Resolution The three production contracts listed in the Joule target have been awarded. The conductor will be wound on the first coil by the end of December. –Includes allowance for MCWF delivery delay past vendor forecast date, and uses winding estimate based on twisted racetrack R&D.

NCSX 13 Cost Risks Associated With MCWF Delays MCWF contract is fixed price. Vendor has given no indications of cost escalation. However The current experience with the first machining could indicate that that the vendor’s cost was underestimated. What if the vendor submitted a claim to recover cost growth? How much might it be? –Suppose the 12 week machining time grows to 20 weeks for #1 and 16 weeks average for the remainder, a 33% increase. –At $155k per casting for machining this could mean approx. $920k risk. –This would be offset by the $637k set-aside by the project as contingency on the remaining MCWF work. (Total remaining contingency is $12.8M.) –Estimated net cost exposure could be $284k. Conclusion –Unforeseen cost growth would be largely mitigated by contingency already set-aside.

14 Lab resources will still be used effectively with the MCWF delay Ample NCSX work is available. –Preparation of modular coil winding parts. –Completion of modifications to the Coil Manufacturing Facility –Preparation of the Test Cell for Field Period Assembly Ample work is available on other PPPL projects. Vacation time will be re-scheduled.

15 Progress in Coil Winding Preparations Construction of the TF Winding Station is underway. The winding table has been installed. The Coil Test Facility has been completed. The Planar Racetrack Coil is being installed as a dummy load. Twisted Racetrack Coil should be completed this week. Coil is potted. Clamps are being preloaded and cooling manifolds are being installed.

NCSX 16 Summary MCWF#1 delivery has slipped. –Vendor forecasts July 30 as best case. We can accommodate a delay to Sept. 30 without impacting project critical path and CD-4 date. We can accommodate a stretchout from 12 to 20 weeks in the machining phase of remaining winding forms. Delays are due to first-unit development issues and are not expected to recur. –Patterns are nearly done. –Casting problems have not recurred. –Machining solutions apply to remaining units. Project cost and schedule are not at risk.