When Things Go Right Cornell’s PeopleSoft 8.9 Upgrade Lisa Stensland Manager, CIT Project Management Office May 15, 2008.

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Targets for the individual and the organisation By Rachel, Claire, Kirsten and Natalie.
6-1 Goldratt’s Critical Chain  In 1997, Goldratt introduced the Critical Chain Project Management (CCPM) methodology to apply the theory of constraints.
Critical Chain Project Management in the Supply Chain Presented By Greg Sullivan APICS Nashville Chapter 19 Feb 2008 Sullivan Group Consulting, Inc.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Critical Path and Gantt
Project Time Management
Source: SSC.Sweetman.CGSC1 Corporate Governance Scrutiny Committee 31 May 2007 SHARED SERVICES CENTRE REPORT By Ron Sweetman Head of Shared Services Centre.
© The McGraw-Hill Companies, Software Project Management 4th Edition Monitoring and control Chapter 9.
Rapid Improvement Leader Rapid Improvement Leader Web System: Thinking About Your RIL Plan.
Project Management Workshop. Nick Cook  Citigroup Corporate and Investment Bank  European Technology Business Office Manager Edinburgh University April.
Supporting people with a learning disability Introduction to Project Management Presenter: Steve Raw FInstLM, FCMI.
Chapter 5: Project Time Management
Importance of Project Schedules
Systems Analysis and Design 8th Edition
Chapter 8 Managing IT Project Delivery
Applied Software Project Management Andrew Stellman & Jennifer Greene Applied Software Project Management Applied Software.
Class 28: Chapter 16: Project Management Class 28 Agenda –Collect Player Diary 2 and Conduct Player Audit No ed diaries – 5 PM Deadline –Discuss Grade.
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
1 Agile Estimating and Planning October, 2013 Technion, Israel Prof. Fabio Kon University of Sao Paulo, Brazil
SA Capstone Requirements and Design Week 10 SYST Winter 2013 Instructors: Jerry Kotuba & Joe Varrasso.
Allocating Resources to the Project
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 7 Project Time Management Part 1.
22 Jul 2005CSE403, Summer'05, Lecture 12 Lecture 12: Scheduling, Estimation, and Prioritization (Part II) Valentin Razmov.
Midterm Review SE503 Advanced Project Management.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Critical Chain From “Theory of Constraints” Developed by Elihu Goldratt in 1984 Goldratt – Many of his key ideas were first explained via “business novels”
Quick Recap.
1 Project Management Introduction. 2 Chap 1 What is the impact? 1994: 16% of IT projects completed “On-Time” 2004 : 29% of IT projects “On- Time” 53%
Project Management. Lecture 5-2 Introduction This lecture discusses the key components of project management, role of project manager and techniques to.
File:CCPGS05 CC present Page: 1 ETXPGS
IS 556 Enterprise Project Management 1IS 556 -Spring 2008 Lecture 2 Apr 7, 2008 //48.
1 Critical Chain From “Theory of Constraints” Developed by Elihu Goldratt in 1984 Goldratt – Many of his key ideas were first explained via “business novels”
Research & Technology Implementation TxDOT RTI OFFICE.
Copyright 2010, The World Bank Group. All Rights Reserved. MANAGEMENT OF A CENSUS, PART 2 THE CENSUS AND MATRIX MANAGEMENT Quality Assurance of Census.
Object-oriented Analysis and Design Stages in a Software Project Requirements Writing Analysis Design Implementation System Integration and Testing Maintenance.
Agile Concepts - II “Agile” Estimating & Planning Nupul Kukreja 5 th November, 2014.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
© 2000 The TOC Center of Australia Pty Ltd 1 Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh The TOC Centre of Australia Pty Ltd The.
VMcG 2/11/02 Critical Chain as an Extension to CPM Vincent McGevna, PMP February 11, 2002
Project Schedules Chapter 4 Applied Software Project Management, Stellman & Greene See also:
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Chain Scheduling, PERT, and MS Project 2003.
Project Management MLP, Careers & Employability Division.
Introducing Project Management Update December 2011.
MEM 612 Project Management Chapter 6 Allocating Resources to the Project.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Test status report Test status report is important to track the important project issues, accomplishments of the projects, pending work and milestone analysis(
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
Project Time Management
1 Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources.
Employee Self-Service. Agenda History PeopleSoft at Queen’s PeopleSoft Upgrade What is MyHR? Benefits of Self-Service Challenges Questions.
Critical Chain A Novel by Eliyahu Goldratt Copyright 1997.
Identify and Explain Effective Working Practices OCR Diploma Level 2.
Engineering Design Building the Team. Elements of Cohesive Teams Trust Willingness to engage in conflict Commitment Accountability Attention to results.
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Supply chain Dynamics in Indian Apparel Export Manufacturing Submitted by: Shikha Aggarwal Vikas Punia.
Chapter 16 – Project Management
Chapter 6: Database Project Management
SE503 Advanced Project Management
Class 27: Project Management Part II
Executive Steering Committee Meeting September 23, 2009
Mike Cohn - Agile Estimating and Planning
Workshop on New Approaches to Statistical Capacity Development
Risk Analysis & Success Driven Project Management
Project management Learning Unit 5.
Reducing Project Duration
Setting up a project file
Setting up a project file
Time Scheduling and Project management
IT Next – Transformation Program
Presentation transcript:

When Things Go Right Cornell’s PeopleSoft 8.9 Upgrade Lisa Stensland Manager, CIT Project Management Office May 15, 2008

Agenda Challenge Change in Methodology and How We Manage Resources Results

Challenge Two critical projects competing for resources –Upgrade PeopleSoft (HR, Payroll, Contributor Relations) from 8.0 to 8.9 –Implement PeopleSoft Student Administration modules Technical implementations could not overlap They both must be done ASAP

Analysis Conducted forecasting of schedule and budget for multiple options –Upgrade first, then implement Student Admin …or… –Implement Student Admin, then upgrade the whole thing Decision –Upgrade first, do it as quickly as possible

What We Knew The forecasting effort indicated that the PS 8.9 Upgrade project would take approximately months to complete –Late Summer Spring 2007 We spent 3 months doing more detailed planning, which resulted –Targeted completion in Winter of 2006 –Estimated $5M budget

What We Knew The timing of a Fall 2006 upgrade was not ideal –Competing business cycles –A “tax/fix version” of PS comes out at that time, and how would we address that? How do we bring the schedule in further when all our planning indicates that we can’t?

I did some digging….

Critical Chain Project Management A way to schedule and track a project that encourages: –Aggressive scheduling –Team Focus –Team ownership of the project commitment

The old way…. Create list of tasks Project Manager asks, “How long will each task take?” Well…about 5 days + I am working on another project + I get interrupted alot + Something usually goes wrong So…10 days!

Safety in estimation Time needed to protect the work estimate commitment from: –Murphy’s Law - what can go wrong, will go wrong –Distraction –Multi-tasking

Parkinson’s Law Work expands to fill the time allotted

“Student Syndrome” Many people will start to fully apply themselves to a task at the last possible moment before a deadline.

What do these factors do to a project? It is normal to focus on task ‘due dates’ Student Syndrome -> Late starts Parkinson’s Law –If nothing goes wrong, the task will finish on time –If something goes wrong, the task will likely finish late Late tasks on the critical path will delay the project

What should be done differently? Remove the safety from the individual tasks Safety Move it to the end…the Project Buffer Safety End Earliest Possible Finish Committed Finish

Refocus the team on… Starting tasks on time Completing tasks as aggressively as possible Managing the amount of Project Buffer that is consumed –Project Buffer is consumed when a task on the critical path is late –Project Buffer is replenished when a task on the critical path is early

July October December

What Had to Change? Estimate aggressively by removing safety from individual tasks –Trust management to not hold staff accountable to aggressive estimates without safety Put safety where the project can use it Minimize multi-tasking Track progress using buffer consumption –Not individual milestones!

Benefits Protection against Murphy’s Law Took advantage of early finishes Team protected the project buffer Opportunity for team to focus Sponsor visibility to what is possible vs realistic Better visibility to when project is in trouble

The Results? Team cutover to PeopleSoft 8.9 in July 2006 –Our most aggressive possible go-live! Project delivered 40% under-budget –$3M spent –$2M saved Staff time not needed - $1.3M Unused contingency - $500K

Moral of the story… Encourage aggressive planning by developing trust between management and the team Allow staff to focus on one task at a time rather than multitask across projects Implement mechanisms that encourage the team to protect the project commitment, rathern than individual commitments

More information… Critical Chain Project Management –