Rapid Assessment Process Project Strategic Plan City of Marfa Water and Wastewater System Improvements Marfa, Texas Presented to: Stakeholders and Project.

Slides:



Advertisements
Similar presentations
Assessing Capacity Through Sanitary Surveys. SDWA §1420 Capacity Development ~To receive their full Drinking Water State Revolving Fund allotment, States.
Advertisements

Annual Inspections of First Nation Water and Wastewater Facilities Derek Hill, P.Eng., Senior Engineer Mohammed Karim, P.Eng., Senior Engineer, Water\Wastewater.
Wakulla County Sewer Project Eutaw Utilities Presentation April 7, 2011.
Lunenburg CWMP Phase II – Management Techniques and Alternatives Identification and Screening Lunenburg Comprehensive Wastewater Management Plan Workshop.
US-Mexico Border Infrastructure Program Drinking Water and Wastewater Projects Javier Torres Regional Project Manager FY2009/2010 BEIF-PDAP Prioritization.
The Idaho Department of Environmental Quality Mark Mason, P.E., Engineering Manager Idaho DEQ - Boise Regional Office 1445 North Orchard Boise, ID
TEXAS COMMISSION on ENVIRONMENTAL QUALITY. PROPOSED STUCTURE FOR CHAPTER 217 < Subchapter A Administrative Provisions < Subchapter B Design Bases < Subchapter.
City of San Juan Water & Wastewater Systems Improvements Hidalgo County, Texas Presented to: Project Sponsor and Agency Stakeholders July 24, 2003 City.
Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
Energy Efficient Design Low Cost State Loan Low-Impact Construction Novato Sanitary District Wastewater Facilities Upgrade Presenter: Beverly James, Manager-Engineer.
Funding for Municipal Infrastructure Ruth Noemí Colón Acting Secretary of State George Stafford Deputy Secretary of State Public Finance and Management.
Water Services Department Arizona Mexico Commission Bi-National Meeting March 9-11, 2008 David Cavazos Deputy City Manager Water Services Department Arizona.
Town of Plattsburgh Cumberland Head Sewer District Welcome To CUMBERLAND HEAD SEWER DISTRICT INFORMATIONAL MEETING JULY 2009.
2 Water and Waste Loans and Grants United States Department of Agriculture??? Rural Development: Mandate to improve the quality of life in Rural America.
City of Oshkosh Water System. Public Works Utility Division Water Filtration Plant Water Distribution System Wastewater Collection System Pumping Stations.
Cuba’s Future Development Needs, Funding Models, and Alternatives. A Perspective of the Operation of a Cuban Water & Sewer Utility. Eduardo Vega-Llort,
 Why  Project Status  Future Course Lime Sludge Biosolids Water/Wastewater System Life Cycle Raw Water Wells (12) Water Treatment Plant Storage Tanks.
Holden Heights Community Improvement Project Update Orange County Board of County Commissioners December 17, 2013.
Rapid Assessment Process Project Strategic Plan City of Alamo Municipal Water and Wastewater Project Hidalgo County, Texas Presented to: Project Sponsor.
The City of North Bend Sanitary Sewer System
11 City of Hallandale Beach Water, Wastewater and Stormwater Facilities Plan Public Meeting.
Feasibility Study of Constructed Wetlands for Wastewater Treatment and Wildlife Habitat Luna County, NM Public Meeting November 10, :00 am Presented.
1 ASEI Sanitation Project ‘A Vision For Change’ Presented at the 2008 ASEI Sanitation Symposium February 9, 2008 Sharanpal (Paul) Sikand Jayant (Jay) Patel.
City of Polson April 5, 2010 PUBLIC HEARING Water System Improvements PRESENTATION ON PRELIMINARY ENGINEERING REPORT.
Imagine the result Impact Study on MSD Rate Payers of Proposed Consolidation/Merger Phase II – Towns of Biltmore Forest, Montreat and Weaverville Presentation.
2015 Needs Assessment Our Strategy for Success Scott Torpie Washington State Office of Drinking Water.
ATTACHMENT C Photographic Report. Photo 1 - Influent Pipe to Wastewater Treatment Plant Photo 3 - Influent Flume for Flow Metering Photo 2 - Chart Recorder.
Niland Sanitary District Rapid Assessment Process Project Strategic Plan Niland Sanitary District Wastewater Systems Improvements Niland, California Presented.
Rapid Assessment Process Project Strategic Plan Doña Ana MDWCA Water and Wastewater System Improvements Doña Ana County, NM Presented to: Stakeholders.
City of Lordsburg Rapid Assessment Process Project Strategic Plan City of Lordsburg Water and Wastewater System Improvements Lordsburg, New Mexico Presented.
Water Crisis in Gaza Strip A study of the Impact of Middle East Conflict upon Water Quantity and Quality in Gaza Strip By: Ayman H. Afifi Islamic University.
Water & Waste Disposal Loans and Grants The funding purpose is to construct, enlarge, extend or improve water, wastewater and solid waste systems in rural.
BORDER ENVIRONMENT COOPERATION COMMISSION Mitigating Impacts on Water Resources: Environmental Infrastructure Investment.
Money Talks: Stretching Precious Dollars Drinking Water State Revolving Fund December 11, 2013.
WSNTG Annual Conference September 2006 Water Services National Training Group 10 th Annual Conference 7 th September 2006.
Water Supply Planning Initiative State Water Commission November 22, 2004.
Rapid Assessment Process Preliminary Project Plan City of Alpine, Texas Public Water and Wastewater System Improvements Presented to: Texas Agencies February.
Los Osos Community Services District Basin Management Planning and Proposed Work Program June 5, 2008.
2008 Facility Plan Update May Purpose  Comprehensive Plan through 2033 –Builds on Past Work –Adjust for Changing Conditions  Identify Capacity,
Energy, Utilities, and Telecommunication Summer Study Committee Meeting September 2, 2014 Thomas W. Easterly, P.E., BCEE Commissioner IN Department of.
City of San Luis, Arizona Rapid Assessment Process Project Strategic Plan City of San Luis Water & Wastewater Improvements Yuma County, Arizona Presented.
Short and Long Range Water Supply Planning and Aquifer Performance Test (APT)
City of Calipatria Rapid Assessment Process Project Strategic Plan City of Calipatria Wastewater Systems Improvements Calipatria, California Presented.
Orange County Board of County Commissioners Update on USEPA Rulemaking for Numeric Nutrient Criteria Utilities Department January 26, 2010 Utilities Department.
All About Sanitary Surveys David Edmunds Environmental Program Specialist ADEC Drinking Water Program Sustained Compliance: What It Means to Public Water.
April 21, 2015 Presented by: Heidi Springer, P.E. Brian Ginter, P.E.
Investing In Our Future. Statement from Mayor Tom Murphy “The Gillette Regional Water Supply Project is essential for quality of life and economic development.
Rapid Assessment Process Project Strategic Plan Village of Columbus Water Supply and System Improvements Luna County, New Mexico Presented to: Stakeholders.
Council Workshop, June 24, Image Date: 1/15/2014 Future WWTF No. 2 Capacity 2.0 MGD., Expandable to 6.0 MGD. Future WWTF No. 2 Capacity 2.0 MGD.,
Wastewater Treatment Plant # 2 Engineering Services Council Workshop July 8, 2014.
Mejoras en los sistemas de Agua Potable y Saneamiento en San Benito, Texas Water and Wastewater Facility Improvements in San Benito, Texas.
1 NORTH VALLEY REGIONAL WATER AND WASTEWATER PROJECTS MEETING OF THE NEW MEXICO-TEXAS WATER COMMISSION May 19, 2005.
1 1 City Commission Workshop for the DRAFT Basis of Design Report December 14, 2015 CRAVEN THOMPSON & ASSOCIATES, INC.
Town of Genoa October 6, Agenda Why are we here? Background Capacity Analysis & Facilities Plan Preferred Alternative Board Direction Implementation.
THE IMPORTANCE OF SANITARY SURVEYS by Mary L. Howell, Backflow Management Inc.
Public Information Meeting Wastewater Treatment January 26, 2016.
Water System Master Plan & Rate Study City of DeKalb, Illinois City Council Presentation May 16, 2015.
CITY OF ARCATA -WATER AND WASTEWATER CAPITAL IMPROVEMENT PROGRAM: RATE SETTING.
Growing Smarter Pennsylvania’s Land Use Agenda. Percent of Land Developed in Pennsylvania Source: Natural Resources Conservation Service, U.S. Department.
Phase II and Compost Facility Upgrade Projects February 16, 2012.
FY 2016 Water & Sewer Rates Presented by: The Department of Public Works Works.
February 21, General Information Utility staff is not aware of any mandate from city ordinance or state statute to provide water and sewer services.
UTILITY PARTNERSHIP CITY OF STOCKTON & OMI / THAMES WATER SERVICE CONTRACT.
Recycled Water Project Basis of Design Report
Wastewater Treatment.
CITY OF MARSHALL CHLORIDE ISSUES September 26, 2017
City of Roundup, Montana
CITY OF MARSHALL CHLORIDE ISSUES NOVEMBER 22, 2016
PLANNING DOCUMENTS 2018 New Mexico infrastructure finance conference
Indiana Finance Authority (IFA)
Presentation transcript:

Rapid Assessment Process Project Strategic Plan City of Marfa Water and Wastewater System Improvements Marfa, Texas Presented to: Stakeholders and Project Sponsor El Paso, Texas February 6, 2003

 General Aspects  Environmental and Human Health Indicators  Technical Approach, Objectives and Funding Plan  Public Participation  Sustainable Development  Project Development Schedule  Stakeholder Comments/Discussion Agenda

General Aspects Project Location §Marfa is located in Pecos County on Highway 90 between Valentine to the Northwest and Alpine to the East.

Existing Water Supply and Distribution System  Water is supplied from three wells at a central site to a 1 MG Ground Storage Tank  Booster Pump Station at central site pumps chlorinated water to the system and an Elevated Storage Tank  Distribution system consists of three pressure zones made up of 1-inch to 8-inch water lines  Distribution system includes two booster pump stations, a stand pipe and ground storage tanks General Aspects

Water System Problems and Concerns  Water does not meet secondary drinking water quality standards for fluoride  Undersized and dead end lines resulting in:  Low pressure areas  Low chlorine residual  Fire flow concerns  Concerns: Compliance with TCEQ regulatory requirements for fluoride, chlorine residual, low pressures and fire flows

Proposed Water Supply and System Improvements  Water supply improvements to meet TCEQ regulatory requirements for fluoride  Distribution system improvements to upsize and loop lines in problem areas to alleviate pressure, chlorine residual and fire flow concerns General Aspects

Existing Wastewater Collection & Treatment System  WWTP consists of influent meter, bar screen, 2 Imhoff tanks and 2 sludge pits and 2 sludge drying beds  Effluent Disposal by irrigation of 62 acres of non-public access pasture land  Permitted flow = MGD Average Flow = 0.08 MGD  Collection system comprised of 4-, 6-, 8- and 10-inch lines and two sanitary lift stations  Portions of system date back to late 1920’s

General Aspects Wastewater System Problems and Concerns  Outdated, substandard technology – Imhoff Tanks  74 Year old WWTP  Effluent storage pond required by TCEQ – Condition of Permit  Undersized, substandard lines – old, 4-inch VC pipelines  Line condition suspect – deterioration, root intrusion, surcharged manholes.

General Aspects Proposed Wastewater System Improvements  WWTP Effluent Storage Pond  WWTP Technology Upgrades  Relief or replacement of capacity deficient, problem area sewer lines

Total Estimated Cost Budget for design and construction pending further definition of the needs, alternatives analysis and project development. General Aspects

 Population: 2,121 / 2,178 / 2,355*  Annual growth rate: 2.0%**  MHI: $24,712  Unemployment rate: 4.9%  Legal utility provider  1,204 metered accounts  7 employees  Collection efficiency: 98% *2000 Census/TWDB Agreed/City of Marfa service area meters **TWDB agreed upon  CDBG: $2.3 Million over the past 9 years  TDHCA: Grant for 2000 Planning study  No prior BECC assistance Project Sponsor Profile:Prior Agency Support:

General Aspects  2000 – City of Marfa Planning Studies Document  Water and Sewer System Facilities Plan  1970 – City of Marfa Comprehensive Plan Prior Studies:

Human Health Indicators  Fluoride levels close to 3 times the recommended level can cause dental and skeletal fluorosis.  Low or no chlorine residuals in dead end lines can lead to illness.  Specifically, improvements to the water supply quality will address concentration of fluoride, chlorine residual and minimum pressures. Environmental and Human Health Indicators

Environmental Indicators  Improvements to the water system are necessary to meet fire protection demands, which poses a direct threat to the health and safety of the City of Marfa residents.  The City’s three water wells are located on the same site such that if one is contaminated, it could affect all three. Alternate source is advisable.  Correction of collection system capacity problem will help mitigate overflows and resulting pollution.  WWTP upgrades will result in a controllable effluent discharge to fields. Environmental and Human Health Indicators

Compliance with Environmental Norms & Regulations Including Violations  Fluoride above secondary standard  Substandard water and sewer lines (1- & 2-inch water and 4-inch sewer)  Outdated WWTP technology – Imhoff Tanks Environmental and Human Health Indicators

Project Objectives  Improve water treatment and distribution  Improve wastewater collection and treatment. Technical Approach  Technical Assistance needed to develop documents which may include:  QAPP  Facility Plan & Environmental Information Document  Engineering Design  Financial Analysis  Public Participation Program  Rate Study Technical Approach, Objectives and Funding Plan

Technical Assistance Tasks TaskSource RAPBECC Facility Plan and EIDBECC Financial AnalysisBECC Public Participation ProgramBECC Preliminary DesignBECC Project Certification DocumentBECC Final DesignBECC/Other Technical Approach, Objectives and Funding Plan

Identified Potential Funding Sources  USDA/Rural Utility Services (RUS)  Funds tailored for rural areas with populations of less than 10,000  Grant  Texas Water Development Board  SRF Loan  North American Development Bank (NADB)  BEIF Grant and IDP Grant/Loan  Border Environment Cooperation Commission (BECC)  PDAP program Grant Technical Approach, Objectives and Funding Plan

Institutional Capacity Building  The project sponsor identified such needs as a capital improvement plan, rate study and the development of public participation programs as institutional needs.  Additional needs may include assistance in both the institutional and human capacity to administer the project.  The Frank M. Tejeda Center has conducted an Institutional Capacity Needs Assessment with the City of Marfa. Technical Approach, Objectives and Funding Plan

Potential Obstacles  The project sponsor and the BECC are not aware of any legal issues that may jeopardize the proposed project, or any litigation problems with the current local government.  A notable potential obstacle is the high cost of providing water treatment to address the quality issues present in the water basin near the City of Marfa.  Rate modifications may also provide a potential obstacle for receiving community support. Technical Approach, Objectives and Funding Plan

Identification of Main Stakeholders  City of Marfa, Texas  TCEQ  TWDB  North American Development Bank  Frank M. Tejeda Center  Border Environment Cooperation Commission  United States Department of Agriculture  Environmental Protection Agencies Local Politics  The City of Marfa local government is comprised of a Mayor and five representatives. The City passed a resolution on September 5, 2000 authorizing the Mayor to seek Technical Assistance from BECC. Public Participation

Minimum Criteria Requirements  The City of Marfa made a commitment to comply to all applicable minimum requirements for the project in compliance with the BECC’s sustainable development criteria.  11 of 14 minimum requirements will apply to the project. Sustainable Development

Project Development Schedule Task NameDurationStartFinish Rapid Assessment Process129 days08/22/0202/18/03 Technical Assistance Process130 days08/22/0202/19/03 Project Development Process (TA, Public Participation, NEPA) 462 days02/19/0311/25/04 Final Design Process253 days12/04/0311/22/04 BECC Certification Process42 days11/17/041/13/05

Agency Perspectives - NADB TWDB TCEQ USDA Technical Approach, Objectives and Funding Plan

Stakeholder Comments/Discussion Thank you for your participation and valuable input.