CMSC Rules Changes under Consideration Market Operations Standing Committee December 3, 2003 PUBLIC.

Slides:



Advertisements
Similar presentations
Order 2000 and PJM: A Natural Match Craig Glazer Manager of Regulatory Affairs PJM Interconnection, LLC.
Advertisements

2000, Independent Electricity Market Operator All Rights Reserved 1.
Assessment of differences in market designs in the CS region Milan 18 July 2008.
Winter 2013/2014 Reliability Solution Including LNG MWHs N. Jonathan Peress Conservation Law Foundation Greg Lander Skipping Stone NEPOOL Markets & Reliability.
Congestion Management Settlement Credits December, 2002.
Discussion of Inter-RTO Seams Issues Presented by: Midwest ISO and NYISO Independent Market Monitor David B. Patton, Ph.D. Potomac Economics October 7,
Highlights of the 2004 State of the Market Report New York Electricity Markets David B. Patton, Ph.D. Potomac Economics Independent Market Advisor May.
Implementation of new Information Disclosure Reports Report to MOSC June 4, 2003 Report to MOSC June 4, 2003.
Demand Response in New York State Northwest Power and Conservation Council DR workshop February 24, 2006.
Ramping and CMSC (Congestion Management Settlement Credit) payments.
MISO’s Midwest Market Initiative APEX Ron McNamara October 31, 2005.
1 TAC Review of PRR 650 August 3, Board Charge to TAC Board remanded PRR 650 to TAC for: “an analysis of how to ensure that consumers pay only.
Utah Schedule 37 Update June 25, Schedule 37 Background Schedule 37 – Published rates for standard power purchase agreements with qualifying facilities.
Special Protection Systems - Market Rule Amendment Submission Presentation to: Market Operations Standing Committee Barbara Reuber, Regulatory Affairs.
Valuing Economic Benefits from Transmission Planning ERCOT System Planning March 22, 2006.
1 Adjusting the “Dispatch Instructions” to the Defined Metering Point (DMP). “Functional Deferral 6 (FD-06)” Market Operations Standing Committee (MOSC)
NGEIR Technical Conference Presentation May 16, 2006.
Challenges for the SEM.  Day-ahead price coupling is a key feature of the final draft Framework Guidelines on congestion management issued by ERGEG in.
Insight Information Company ONTARIO POWER SUMMIT Policing the Market: Upholding Conduct & Performance Harry Chandler Director, Market Assessment & Compliance.
Public Market Surveillance Panel Consultation on CMSC Issues Related to Constrained off Payments to Generators and Imports Market Operations Standing Committee.
Proposed CMSC Amendments - Imports & Exports Intertie Trading Sub-committee November 24, 2003 PUBLIC.
Ontario Electricity Supply Forum PEO Mississauga Chapter - September 6, 2007 Rhonda Wright-Hilbig, P.Eng Market Analysis - IESO.
The Ontario Electricity Market 1 Year in Richard Penn Mgr - Market Assessment The IMO Richard Penn Mgr - Market Assessment The IMO.
Day Ahead Market Working Group April 14, Agenda Discussion of SMD-style DAM review questions posed by the DAM WG and Coral regarding the SMD-
Market Evolution Program Day Ahead Market Project How the DSO Calculates Nodal Prices DAMWG October 20, 2003.
Transmission Reliability Program Review Market Monitoring Tools Bernie Lesieutre and Bob Thomas Lawrence Berkeley National Laboratory Cornell University.
RPRS ERCOT System Wide Insufficiency Charge Presented at the Technical Advisory Committee June 1, 2006.
Treatment of Intertie Failures Intertie Trading Subcommittee November 24, 2003.
SM April Peak Week Operations Review Presentation to ISO Business Issues Committee May 22, 2002.
Market Operations Standing Committee of the IMO Market Operations Standing Committee April 23, 2003.
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
Addressing Constrained-Off Payments for Intertie Transactions Darren Matsugu, Supervisor - Markets, IESO Presentation to Technical Panel: June 2, 2015.
14 Jan 2004Market Operations Standing Committee1 Special Protection Systems: Operational and Compensation Issues.
IWWG Annual Conference Wind Management at MISO July 22, 2011.
PJM©2013www.pjm.com Demand Side Working Group Loads in SCED Angelo Marcino Real-Time Market Operations – PJM April 14, 2014.
DAM Design Issues - Participants & Obligations May 12, 2003 Market Evolution Program.
CMWG Update WMS September 2015 Meeting. CRR Balancing Account Fund Discussion The CRR Balancing Account fund appears to be working as expected The cap.
Sep 22, 2003Market Operations Standing Committee of the IMO1 Change Management: Market Rules Update John MacKenzie, IMO.
Unit-Specific Bid Limits based on Modified Generic Cost.
SOUTHERN CALIFORNIA EDISON SM Southern California Edison Company’s Proposal to Participate in Convergence Bidding August 23, 2010.
Jun 18, 2003Market Operations Standing Committee of the IMO1 Market Pricing Integrated Proposal: Consequences, Trade-Offs & Implementation.
MCWG Update to WMS 11/13/2013. MCWG Update to WMS General Update - October 30 th Joint MCWG/CWG Meeting Review September 25 Meeting Minutes - Approved.
1 IG Meeting Milan, 18 th July 2008 Cost of Firmness of Capacity.
Revisions to the Information Confidentiality Catalogue Presentation to the Market Operations Standing Committee April 23, 2003.
Wholesale Electricity Spot Market (WESM)
2004/06/0 2 Market Operations Standing Committee of the IMO1 Small Facilities - Technical Requirements Rhonda Wright.
Linnfall Consulting Market design: the energy-only market model Linnfall Consulting September 2015.
Market Working Group Update Presentation to CAWG March 29, 2011 Jim Sanderson, KCC.
Market Operating Level Agreement (OLA) Discussion Betty Day 8 December 2009 Nodal Advisory Task Force.
Role Of ERC in the WESM To enforce the rules and regulations governing the operations of the WESM and monitors the activities of the Market Operator and.
Market Operations Standing Committee MOSC October 19, 2005 Pat Doran.
02/18/2003Market Advisory Council of the IMO1 Market Evolution Program Document ID #: MAC
MOSC Meeting Operations Market Manual updates October 22, 2003 Presented by:Ron Falsetti Steve Cooper.
Recommendation on DACP SE-22 Presentation to the SAC Darren Finkbeiner, Manager – Market Entry and Analysis November 1, 2006.
1 Market Evolution Program Day Ahead Market Project Regulatory Affairs Standing Committee Meeting May 14, 2003.
Jul 23, 2003Market Operations Standing Committee of the IMO1 Market Pricing Issues Update John MacKenzie.
Proposal for Consideration Regarding Holistic Solution to Congestion Irresolvable in SCED Issue:How do you identify when constraint is irresolvable Proposal:Adopt.
3 Dec 2003Market Operations Standing Committee1 Change Management: Market Rules Update John MacKenzie.
Lead from the front Texas Nodal 1 Texas Nodal Energy & Market Management System EMS/MMS Projects Requirement Documents November.
CAISO Market Design Initiatives Update Donald Tretheway Senior Market Design and Policy Specialist CPUC Storage Proceeding January 14, 2013.
EIAScreening6(Gajaseni, 2007)1 II. Scoping. EIAScreening6(Gajaseni, 2007)2 Scoping Definition: is a process of interaction between the interested public,
Wind Management at MISO
Consolidated EIM Initiatives from 2017 Roadmap Issue Paper
Pilot Project Concept 30-Minute Emergency Response Service (ERS)
Review of Abnormal MCPEs
Electricity Wholesale Markets: Designs for a low-carbon future
PJM & Midwest ISO Market-to-Market Coordination (APEx Conference 2007)
Special Protection Systems: Operational and Compensation Issues
Market Pricing Initiatives Update September 9th, 2003
Market Pricing Issues: Update
Presentation transcript:

CMSC Rules Changes under Consideration Market Operations Standing Committee December 3, 2003 PUBLIC

Proposed Rule Amendments and Issues Background Facility induced CMSC Reference price for hydroelectric facilities Negative price offers for imports Constrained off imports / exports & scheduling protocols CMSC for constrained off exports

Background Longstanding MSP concern about constrained-off payments –Consultation began with discussion paper, in February 2003 –MSP report presented to IMO Board on July 3 –One conclusion and six recommendations Urgent rule for uncontested exports interties –questions about the beneifts to the market from constrained off export CMSC

Summary of MSP Recommendations Conclusion: not to pursue removal of constrained off payments at this time Recommendations requiring rule changes: No constrained-off CMSC for generators or loads where it is self-induced Redefine Hydroelectric historical reference price No constrained-off CMSC for negative offers Imports that cannot be scheduled should be removed from stack so they do not receive CMSC payments. Recommendations for working groups: to look at the Niagara 25 Hz sub-system to look at transmission planning issues in Ontario

Endorsements from Board The IMO Board endorsed the recommendations authorized IMO to take actions necessary to implement them. At the same time Board approved an Urgent Rule amendment related to negative offer prices for generators Other rules have come to the Technical Panel proposed changes being sent to December Board Working groups under way

“Self-Induced” (Facility Induced) Would apply in 4 generic situations, where CMSC is induced by: –dispatch deviations* –inaccurate telemetry –quoted ramp rates for dispatchable load below dispatch threshold* –facility operational constraints lead to limit on dispatch * Initially proposing only rules for dispatchable load –Because of complexity associated with generators –will need further stakeholdering

Scheduled or Actual Production (MW) 20 MW 29 MW 50 MW Market Schedule Dispatch Actual CMSC Payment Dispatch Deviations Can Lead to CMSC Interval

Scheduled or Actual Production (MW) 72 MW 70 MW 100 MW Market Schedule Dispatch Actual CMSC Payment Low Ramp Rate Can Lead to CMSC Interval Filter off for 1 interval

CMSC Mitigation for hydro Existing price screens do not reflect market conditions and opportunity cost as closely as they might. –Hydro price screens should be 30-days (rather than 90 days). Historical price should be replaced by weighted MCP. Effect will be to broaden safe harbour for constrained on and narrow it for constrained off payments. No hydroelectric screen is perfect. This is better –actual conditions will be discussed with participant

Hydroelectric Reference Price Price Market Schedule 0 MCP Offer Price Contributes to current HRP Contributes to proposed HRP

Negative Price Offers for Imports Issue: –Potentially large CMSC without efficiency rationale If 50 MW constrained off at -$2000 offer & zonal price $100 CMSC = [50 * (100 -(-$2000))] = $105,000 per hour. Compared with energy payment if scheduled Energy Payment = 50 * $100 = $5000 per hour Rationale for Recommendation: –If payment of zonal price is sufficient for producing energy, it should be sufficient for not producing. Large negative prices are not indicative of costs incurred

Negative Price Offers - Proposal Proposed rule to limit CMSC payments to imports –when offer prices are below zero. CMSC calculated assuming a lower price limit –limit is zero $/MWh unless zonal price is less than zero, then limit is zonal price –for fairness / symmetry, applies to positive and negative CMSC, constrained on and constrained off situations Interim application: after-the-fact adjustment –for subset: positive CMSC, > 1 MW constrained off Can monitor if future conditions change if reduced CMSC does not cover constrained off costs

Negative Price Offers - Examples Price $/MWh 0 Zonal Price Offer Price Proposed CMSC Applied Limit Case 1: Zonal Price > 0 Generic Case: Import Constrained off from 50 MW (MS) to 0 MW Proposed CMSC not paid

Negative Price Offers - Examples Zonal Price Zonal Price = Applied limit Proposed CMSC = $0 Generic Case: Import Constrained off from 50 MW (MS) to 0 MW Price $/MWh Case 2 0 Case 2: Zonal Price < 0 Applied Limit CMSC not paid

Negative Price Offers - Examples Generic Case: Import Constrained off from 50 MW (MS) to 0 MW Offer Price CMSC < 0 No Change Potential Limit, below offer; no change IOG will be positive IOG + CMSC ~ zero Price $/MWh 0 Case 3: Zonal Price < Offer Price < 0

Constrained Off Imports / Exports - Current Procedure After 2 hour ahead IMO pre-dispatch –IMO notifies NYISO of successful constrained schedule imports and exports NYISO applies these as upper limits –in their hour ahead market. Going into 1 hour ahead IMO pre-dispatch –IMO applies limit for the constrained run only –allows the unconstrained market schedule to float Could be further adjustments –for failures during checkout or new TLRs

Proposed Limits on Schedules Proposed rules to recognize such limits –generic: possible changes with New York or others Planned implementation for New York –CS 1  CS 2 [ CS = constrained predispatch schedule] Same as current procedure 2 hr ahead constrained pre-dispatch is limit on 1 hour ahead –MS 1  max (MS 2, CS 2 ) [ MS = predispatch market schedule] 1 hour ahead unconstrained market schedule is limited –physical limit: 2 hour ahead constrained value –economic limit: 2 hour ahead market schedule ensures CMSC for congestion management of physically feasible schedules

Limits on Schedules with NYISO - Examples * Old / New MS 1 Limit relevant when 1 hr Ahead predispatch energy price increases, potentially increasing market schedule

Implications of Scheduling Limits Constrained schedules not affected since these are already limited May be no impact on market schedule and CMSC –if either CS 2 or MS 2 = offer limit –if 1 hr ahead energy price  2 hr ahead price Or no negative payment impact for import / export –if offer price > 0 real time zonal price negative CMSC case schedule and CMSC change, but IOG and CMSC offset –similar implication for exports except no IOG, so may be net reduction in negative CMSC

25-Hz Subsystem Inefficiency of 25 Hz subsystem a longstanding issue. Time to resolve it CMSC payments reduce incentive to look for solutions; create theoretical potential for gaming –The IMO should lead a working group including Stelco, Hydro One and OPG to resolve this issue in the best possible fashion. If at the end of six months there is no resolution... the IMO Board... should then consider alternatives, including the possible elimination of both constrained off and constrained on CMSC payments to generation on the Niagara 25 Hz system.

Transmission Planning IMO, Hydro One, other transmitters and OEB should work together to develop MOU that –sets out appropriate roles /accountabilities in facilitating transmission planning and approval of projects aimed at enhancing efficiency in a competitive market –identifies any changes to market rules, statutory authorities and resources necessary to allow appropriate planning processes to take place Report to respective Boards by end of December –Followed by market participant comment Can consider outage planning & coordination in this working group, if appropriate

Constrained off Export Payments - Background When MR developed to address uncontested export interties, questions raised: The purpose of constrained off payments to exports; and The benefits of these payments to the IMO administered market in light of the Ontario spot market risk of high CMSC payments where bid prices may be high –whether based on high replacement costs or “strategic bid”

Initial View Ontario benefits from exports –pay a component of transmission costs (Tariff) –generators receive additional energy payments But there are issues related to –whether there is similar treatment in other markets –may introduce inefficiencies across markets –local market power mitigation process may not control risks

Updated View Traders say the CMSC is only mechanism for hedging export risk –where (financially) committed for replacement costs and there is a risk of scarcity pricing in the other market Could likely lead to reduced exporter activity and liquidity in IMO market both import / export Residual issue –there are circumstances where strategic bid prices lead to CMSC compensation which exceeds the risk in the destination market

Options for Residual Issue Status Quo –Accept the implied “over-payment” Cap the payments –either a price limit or limit on number of hours of payment Allow a case by case review –allow exporter to receive / keep CMSC equivalent to risk or cost