1 How does ERCOT Review, Verify and Approve RMR Costs? (In response to questions that were asked during PRR 632 discussions) Prepared for the 01-18-05.

Slides:



Advertisements
Similar presentations
Fiscal Monitoring: Ensuring Accountability of Your Sub-Grantees
Advertisements

ALTERNATIVE SEARCH PROCEDURE/PROCESS/PROTOCOL (ASP) Office on Volunteerism and Community Service.
Award Close-out Procedures-an overview Review award documents Complete Reconciliation Sheet Budget Reconciliation Expense Reconciliation Oracle Balances.
Reimbursement Procedures for Title I Charter Schools School Year Department of Federal and State Programs.
MODULE 8 MONITORING INDIANA HPRP Training 1. Role of Independent Financial Monitors 2 IHCDA is retaining an independent accounting firm to monitor its.
1 Appeal to ERCOT Board Regarding Use of Fuel Oil Index Price (FOIP) Larry Gurley TXU Wholesale June 19, 2007.
RCWG Update to WMS April 9, VCMRR-VC for Cancellation of RUC Committed Resources Paragraph (3) of Nodal Protocol Section regarding Cancellation.
Consolidated Equipment Financing Program (CEFP) Department of Financial Services Bureau of Accounting.
Large Scale Projects Aleksejs Šaforostovs LSP Project Manager Joint Technical Secretariat.
ERCOT Billing, Settlement Disputes & Data Extracts
HOW TO WRITE A BUDGET…. The Importance of Your Budget Preparation of the budget is an important part of the proposal preparation process. Pre-Award and.
First 5 LA Invoicing & Budget Modification Workshop OHCD Contractors FY
April 15, TAC Report to the ERCOT Board April 15, 2003.
3-n-1 Financing 1.Purchase 2.Remodel 3.Make Energy Efficient.
Overview of FIP Issues in the RUC, Verifiable Cost, and other Nodal Market Processes January 28, 2009 WMS Meeting.
ERCOT RMR Basics Ino González Supervisor, S&B Market Analysis.
Settlement of Mothballed RMR Resources for System Capacity November 15, 2011 RDTF Meeting Ino González ERCOT November 14, 2011.
Report to TAC February In Brief Chair and Vice-Chair for 2009 Chair and Vice-Chair for 2009 Working Group Reports Working Group Reports QMWG QMWG.
January 14, New logic and invoices used in January 2015 when closing out December 2014 New Bill Determinants: CRRBAFA- CRR Balancing Account Fund.
Presentation to WMS Regarding PRR 731- Fuel Oil Index Price (FOIP) Larry Gurley July 18, 2007.
MARCH 9, 2006 Boating Safety and Enforcement Grant Program Regulations Stakeholder Workshop Proposed Conceptual Regulations Department of Boating and Waterways.
PRS - RPRS Task Force Status Summary - August 14, PRS RPRS Task Force Status Summary Prepared for WMS and PRS August 2006.
Texas Nodal Section 9: Invoicing ERCOT, Settlements & Billing SDAWG - August 2007.
Is Reactive Power Worth Anything? The sun sets on a lightless New York City – August 14th Reactive & Voltage Maintenance Joint Proposal by TexGenCo/Calpine.
Mr. Thilak de Silva. BSc. Eng., MSc, CEng, FIE(SL), FIET(UK), CITP(UK), MBCS(UK), MIEEE (USA) M.Sc. in IT - Year 1 Semester II
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Real Time Reliability Must Run Settlements Business Requirements.
1 Briefing Session on Application for Fee Revision for the 2013/14 School Year by DSS Schools Submission of budget and financial information MA Section.
Marketing & Tendering. Budget Forecasting Profit is the key to Business Success – Profit is amount of money after all expenses Materials Labour Insurances.
1 Briefing Session on Application for Fee Revision for the 2012/13 School Year by DSS Schools Submission of budget and financial information MA Section.
A T H E N A 1 E UROPEAN U NION ATHENA ATHENA E UROPEAN U NION ATHENA ATHENA Council decision 2007/384/CFSP of 14 May 2007 ( OJ 13/06/2007.
JCRI Business Operations – Post-Award. Processes relating to the collection of sponsored clinical trial funding.
RMR Task Force Decision Points for ERCOT Technical Advisory Committee April 3, 2003.
Load Profiling Working Group RMS Presentation 8/01/2002 by Ernie Podraza Reliant Energy Retail Group Chair PWG.
Initial eligibility assessment and ex-post monitoring of State aid in EU funds co-financed projects.
QMWG Update to WMS S. Looney December 3, Assignments from WMS ERCOT Market Operations Report – Two SASMs in October, no AS insufficiency – Two unique.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Nodal Verifiable Costs Process WMS Meeting May 15, 2007 Ino.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee February 2, 2006.
Nodal Short Pay and Uplift Process CWG Meeting May 28, 2008.
Protocol Revision Subcommittee Report to ERCOT Technical Advisory Committee December 5, 2002.
OBSERVAL CONTRACT 25/01/2008 2/10/ Summary 2/10/ Agreement & its annexes First pre-financing payment Progress report 2 nd pre-financing payment.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee October 1, 2009.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Verifiable Costs for Nodal WMS Meeting.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee September 3, 2009.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Verifiable Costs Process Settlement and Data Aggregation Working.
02/22/061 Review of Balancing Energy Neutrality Adjustment (BENA) WMS Meeting ERCOT Settlement and Billing.
1 Project Prioritization Review May 14, Approved Revision Requests “Not Started” – Planned to Start in Future Months Revision Request Target Start.
Compliance Update July Control Performance Highlights  NERC CPS1 Performance ERCOT’s May score was 146.1; June’s score was May has typically.
Making a Budget Independent Living October 27, 2015.
Settlement Stability 2015 Q1 Update to COPS- DRAFT Blake Holt ERCOT COPS 07/15/2015.
1 TAC Report to the ERCOT Board July 18, TAC Summary 4 PRRs for approval (3 unanimous) 4 PRRs for approval (3 unanimous) 5 Nodal PRRs for approval.
© 2015 Deloitte & Touche IPSAS 24 Presentation Of Budget Information In Financial Statements Deloitte & Touche August 2015 A closer look.
Grant Applications Shanna Graham-Garrett
Overview of FIP Issues in the RUC, Verifiable Cost, and other Nodal Market Processes November 12, 2008 VCWG Meeting.
Reliability-Must-Run (RMR) Cost Evaluation and Settlement Basis Ino González ERCOT RMR Workshop May 24, 2016.
Chapter 36 Financing the Business Section 36.1 Preparing Financial Documents Section 36.2 Financial Aspect of a Business Plan Section 36.1 Preparing Financial.
PRR 503 Coordination of Resources Due to TSP Section Management of Transmission Forced Outage or Maintenance Outages.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
Reliability Must Run Resources for Summer Slide 2 RMR for Summer 2011 RMR Contracts for Mothballed Units ERCOT has signed RMR Agreements with two.
February 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott March 3, 2015 TAC Update to RMS 1.
Field Office Training 1 U.S. Department of Housing & Urban Development CFFP Overview Field Office Conference Call March, 2008 Todd Wendorf Office of Capital.
1 Commercial Operations Working Group Update to TAC April 7, 2005.
Job Description: Financial Controls & Budgeting: Perform company’s budgeting, forecasting, costing, cost allocation and analysis, review of pricing are.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Settlement Statements and Calendar Business Requirements Settlements.
TAC Report to the ERCOT Board
Nodal COMS Additional Items Update
Resource Cost Working Group
RMR Update November 6, /05/2002.
Chapter 8 Acquisition and Expenditure Cycle
Acquisition and Expenditure Cycle
Delayed June 2018 State Aid Borrowing Process
Presentation transcript:

1 How does ERCOT Review, Verify and Approve RMR Costs? (In response to questions that were asked during PRR 632 discussions) Prepared for the WMS Meeting Settlements and Billing

2 Description of Process QSE submits proposed budget. ERCOT reviews proposed budget. (Operations, Legal, S & B, and consultant). Budgets are submitted for each individual unit. ERCOT verifies projects are necessary and approves final budget. Approved budget is used for Initial Settlement. (Same amount each month) Actual costs submitted to ERCOT before Finals and True-ups. “Only Actual and Appropriate Eligible Costs attributable to operating the RMR unit.”.

3 Description of Costs “Capacity Payments” (Standby Price) based on “Eligible Costs” in section (Base Cost of Operations, Outage Maintenance Cost, Non-Outage Maintenance Cost, Other Budget Items) --- submitted on monthly basis. “Energy Payments” (Fuel Costs) --- submitted on monthly basis (for each individual unit). “Only Actual and Appropriate Eligible Costs attributable to operating the RMR unit. Costs that are identified as inappropriate are disallowed and not paid. QSE can dispute.

4 Key Parts of the Process QSE submits costs with signed cover sheet for each month for each unit. “These are actual costs attributable to operating this RMR unit” ERCOT reviews monthly submittals. We do not hesitate to ask for more documentation (or explanation letters) to verify costs.

5 Use of Consultant ERCOT has had a consultant review budgets and actual costs submitted by RMR service providers. Asked to identify: Excessive costs or errors (including allocations from parent or related companies). Compliance with “eligible costs” as defined by the protocols. Costs or expenses that are inconsistent with other units, plants or projects which are “similar to” the reviewed units. The salvage value of any Capital Expenditure.

6 QUESTIONS / CONCERNS?