U N C L A S S I F I E D Progress Report on the Dual-Use Cryostat John C. Ramsey Los Alamos National Laboratory.

Slides:



Advertisements
Similar presentations
Design of the T962 Cryostat L. Bartoszek BARTOSZEK ENGINEERING 5/10/07.
Advertisements

Upgrade Plan of KEKB Vacuum system Pre-kickoff KEK1 Y. Suetsugu KEKB Vacuum Group Contents Challenges for vacuum system Designs for.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
SPECTRAP - GSI progress report and status overview.
Progress of the BEPCII Injection System Kang Wen.
Tagger and Vacuum Chamber Assembly Procedure. Preassembly of second bottom yokes and poleshoes. a) Install special support. b) Place the second bottom.
Status of VLPC Cryo-Cooler Cryostat Design Russ Rucinski (Alan Bross) Fermilab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
Status of the Power Core Configuration Based on Modular Maintenance Presented by X.R. Wang Contributors: S. Malang, A.R. Raffray and the ARIES Team ARIES.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Spectrometer Solenoid Lead Testing Update S. Virostek and Mike Zisman Lawrence Berkeley National Lab MICO Meeting January 19, 2010.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
NEDM Collaboration Meeting, May 25-26, He Relaxation Steve Williamson UIUC.
Assembly Scenarios Draft 1 MODEL simulation based on CXUO-CRY-AP-001.
FP420 Vacuum Ray Veness. Contents o What is FP420? o How would it be installed in the LHC? o What would it look like? o What are the issues/interest for.
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
Assembly Organisation and Duration. Work Site Organisation STORAGE SMA18 UNLOADING CLEAN ROOM CERN-SITE CLEANING MANUFACTURE DIRTY TRIAL ASSEMBLY ISO7.
HV-SQUID Compatibility Test Study the SQUID performance in a HV environment. Study the HV breakdown –in superfluid under pressure. –using different materials.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
11/30/20151Robin Lafever The existing 300 K Flange This is certainly an older version but is useful to illustrate The proposed modifications.
Refurbished Booster RF John Reid October 24, 2012.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
EDMEDM EDM Collaboration Meeting 3-06 Jan Boissevain, P-25 March 2, 2006 NCSU EDM Experiment Design Status.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
Study Plan of Clearing Electrode at KEKB Y. Suetsugu, H. Fukuma (KEK), M. Pivi, W. Lanfa (SLAC) 2007/12/191 ILC DR Mini Work Shop (KEK) Dec.
P25 Interface 5/19/08 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The nEDM Subsystem Managers Duke University,
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
EDMEDM LANL Review of EDM Cost and Schedule Jan Boissevain for Walter Sondheim, P-25, Los Alamos February 11, 2005, at Los Alamos National Laboratory Conventional.
Yousef I. Makdisi DIS03 St. Petersburg April 24,2003 Polarized Jet target status The overall view The Dissociator stage The Atomic Beam stage The RF transitions.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
1.Placement of support base for 70 degree-dipole magnet(D) ・ Support base for 70 degree-dipole magnet(D) should be placed horizontally with a spirit level,
PASI OsC meeting 12th July 2012
SLHC Engineering Upgrade FCAL Remove-Install step by step procedure. Mircea Cadabeschi-University of Toronto March 01,
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Summary of RIKEN visit. Chamber Top plate Bottom plate Middle cylinder.
SKEKB Mini Work SKEKB Vacuum System – Arc Section – Contents Y.Suetsugu KEKB Vacuum Group 1.Beam Chambers 2.Pumps: Pump, Pressure,
NEDM Collaboration Meeting 5/2008 Preliminary Engineering Report nEDM Central Detector John C. Ramsey Los Alamos National Laboratory.
EDM in ER2 at LANSCE Jan Boissevain LANSCE ER-2 Stake Holder Meeting
EDMEDM LANL Review of EDM Cost and Schedule Jan Boissevain, P-25 February 11, 2005, Los Alamos National Laboratory EDM Reference Design Tour of the Reference.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
3 He R&D Plan at Los Alamos Takeyasu Ito Los Alamos National Laboratory EDM Collaboration Meeting May 26, 2006 Oak Ridge, TN.
Conceptual Design for HYLIFE-II Maintenance Ryan P. Abbott ARIES Project Meeting May 6, 2003 This work was performed under the auspices of the U.S. Department.
EDMEDM EDM Collaboration Meeting 6-05 Jan Boissevain, P-25 June 20, 2005, Los Alamos National Laboratory EDM Reference Design.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
DON LYNCH OCTOBER 28, October 28, 2014 sPHENIX Detector Integration & Assembly Concept.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
MICE Prototype Coupling Coil Cooling Circuit Design Dan Cheng Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Specifications for the Integrated Tests II Paul Huffman.
Teleconf ACS – FREIA 28th March 2017
Mechanical and cryogenic configurations
Update on PANDA solenoid design
LARP Vertical Test Facility
Diffuser status October 2017
Far Detector Activities Late 2017 – Early 2018
STO2 I&T at APL.
Teleconference ACS – FREIA 20th February 2018
Teleconference ACS – FREIA 19th June 2017
Presentation transcript:

U N C L A S S I F I E D Progress Report on the Dual-Use Cryostat John C. Ramsey Los Alamos National Laboratory

U N C L A S S I F I E D 2 Dual-Use Cryostat Introduction Dress rehearsal for the nEDM upper cryostat Test-bed for various features Provides a home for R&D work for the He3 Injection system and the High Voltage system

U N C L A S S I F I E D 3 Vacuum Chamber Assembly Status Vacuum chamber test assembly in progress Pump-down and leak check this week or early next week

U N C L A S S I F I E D 4 Radiation Shield Assembly Split at two locations to facilitate assembly and modification inside the cryostat Top flanges also split 45° adapters can be installed after vacuum can All components have arrived

U N C L A S S I F I E D 5 High Voltage System Modifications High voltage insert design nearing completion System currently open and undergoing disassembly Completed design for 4K shield addition, off to shops early next week New cradle allows HV system to be easily moved and lifted into position under cryostat Adding cooling lines for shields and central volume Connections to the upper cryostat to be made from the bottom without disturbing the upper cryostat

U N C L A S S I F I E D 6 Cryostat Support Stand Simple support stand will arrive at LANL in a few weeks Makes use of small crane to overcome hook height problems in the building Auxiliary stands for the crane and atomic beam source forthcoming

U N C L A S S I F I E D 7 Coming Soon! Completion of test assembly / pump-down / leak check Modification of DR impedance Assembly of cryostat on support platform Commissioning and debugging runs A little finger-crossing, some late nights, and some R&D!