SR 1 BLUFFTON Public Hearing September 25, 2012. INDOT Mission: INDOT will plan, build, maintain and operate a superior transportation system enhancing.

Slides:



Advertisements
Similar presentations
U.S. 20 Pavement Replacement Project Michigan City High School Wednesday, September 17, 2014.
Advertisements

Maryland Avenue and Arkwright Street Jerry Auge, PE Project Manager Ramsey County April 2, 2013.
Titusville to Edgewater Bike Loop PD&E Study
Proposed S.R. 26 Pavement Replacement Project Thursday, December 13, :00 p.m. Presentation East Jay Middle School 225 East Water Street in Portland.
State Road 46 Pavement Replacement Owen Valley High School Wednesday, September 3, 2014.
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
Public Scoping Meetings September 26, 2011 and September 29, 2011 Cajalco Road Widening and Safety Enhancement Project.
S.R. 1 Intersection Improvement Project Wells County Public Library, Bluffton, IN 6:00 p.m. Presentation Thursday, April 24, 2014.
U.S. 31 & S.R. 28 Interchange Project
I 65 Added Travel Lanes Project Clark County Ivy Tech Community College Thursday, March 12, 2015.
S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon Thursday, August 9, p.m. Jennings County High School.
New I-65 Interchange at Worthsville Road Welcome!.
U.S. 33 Northern Connector Alternative
U.S. 421 Bridge DES# Thursday, July 17, :30 p.m. Frankfort Community Public Library 208 West Clinton Street, Frankfort, IN.
Environmental Assessment Public Meeting
S.R. 256 Road Reconstruction Project From City of Austin to S.R. 203 Thursday, February 6, 2014 Austin Elementary School 6:00 p.m.
S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon Wednesday, June 29, :30pm Presentation Jennings County High School.
Welcome to Pinal County. Greg Stanley Pinal County Public Works AACE Regional Conference Oct 1-3, 2008 The Three C’s of Hunt Highway.
I-465 at I-65 Interchange Modification Public Hearing 6:00pm Tuesday, April 10, 2012 South Grove Intermediate School Beech Grove, Indiana.
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
I-65 Added Travel Lanes Project in Tippecanoe County
S.R. 49 Bridge Rehabilitation over Kankakee River Thursday, September 12, :30 p.m. Presentation Wheatfield Public Library Wheatfield, Indiana.
S.R. 144 Intersection Improvement and Road Reconstruction Project Tuesday, October 11, :30pm Presentation Neil A. Armstrong Elementary School 1000.
U.S. 150 / S.R. 56 Roadway Rehabilitation Project Thursday, August 22, :00 p.m. Presentation Orange County Community Center Paoli, Indiana.
U.S. 24 over Tippecanoe River Bridge Replacement
SR25 Preventative Maintenance Project in Tippecanoe County
Interchange Modification U.S. 41 at S.R. 62/66 (Lloyd Expressway) 6:00 p.m. Presentation Thursday, November 15, 2012 Southern Indiana Career & Technical.
In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
1 I-75 Reconstruction Welcome! Those wishing to make an official comment concerning any of the projects presented this evening.
U.S. 224 Road Reconstruction Project from the St. Mary’s River Bridge to just east of Jackson Street in Decatur, Adams County 6:30pm Presentation Erekson.
ILLINOIS ROUTE 23 (LaSalle St.) DOWNTOWN RE-ALIGNMENT December 2, 2008.
SR 997 / KROME AVENUE Florida Department of Transportation April 27th, 2006 South Miami-Dade Watershed Study Advisory Committee.
U.S. 33 Northern Connector Alternative Goshen High School Auditorium, Goshen, IN Thursday, March 20, 2014.
New I-65 Interchange at Worthsville Road April 11, 2013 Welcome!
U.S. 31 at C.R. 400 South Intersection Improvement Clifty Creek Elementary School May 22, 2014, 6:00 p.m.
State Road 5 over Eel River Bridge Rehabilitation DES# South Whitley Community Public Library Thursday, February 5, :30 p.m. Please silence.
S.R. 930 and Green Street Intersection Improvement Project Tuesday, May 22, :00 p.m. Presentation Park Hill Learning Center Auditorium New Haven,
Presentation Outline  Recommendation  Project Background  Public Involvement  Proposed Design  Citizen Comments/Questions  Summary and Recommendation.
MD 97 (Georgia Avenue) at Randolph Road Purpose Improve vehicular, bicyclists and pedestrian safety Improve Levels of Service Increase capacity Improve.
U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, :00pm Presentation Orange County Community Center 1075.
U.S. 33 Road Reconstruction Goshen High School Auditorium 6 p.m. Wednesday, August 20, 2014.
STA Safety Project PID #76439 December 12, 2006.
Bridge Replacement and Road Realignment on U.S. 6 over Norfolk Southern Railroad Albion Municipal Building Thursday, October 22, 2015.
Titusville to Edgewater Bike Loop PD&E Study FDOT Project Number: Volusia County, Florida FDOT Project Number: Brevard County,
Route 12B Safety Improvement Project New York State Department of Transportation Mark Silo, P.E. Thomas J. Madison, Jr. Regional DirectorCommissioner.
From US 17 to SR 11 and SR 11 to Cone Road FPID No October 25, 2011.
SR 256 Road Rehabilitation Town of Austin January 18, :00pm Austin Elementary School.
General Tab Project, Cost Schedule, and Work Limits Roadway Character
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
156 th Street Design in Bennington Public Open House Meeting October 28, 2009 City of Bennington, NE.
HOOSIER HEARTLAND HIGHWAY SR25 Segment Four Cass County Public Information Meeting December 10, 2009 Design Consultant – United Consulting Engineers.
U.S. 20 Intersection Improvement Project at Waverly Road Porter Town Hall Thursday, August 13, 2015.
Geometric Design: General Concept CE331 Transportation Engineering.
1 MD 5 (Point Lookout Road) Leonardtown (Phase 1) Intersection Reconstruction At Abell and Moakley Streets Informational Meeting January 19, 2016.
New Interchange at I-69 and 106 th Street Fishers City Hall Auditorium Thursday, September 10, 2015.
MED SR 18 Corridor Project MED PID October 13, 2015.
I-465 at I-65 Interchange Modification Public Meeting 6:00pm Monday, October 1, 2012 South Grove Intermediate School Beech Grove, Indiana.
U.S. 20 Intersection Improvement Project at Waverly Road Porter Town Hall Thursday, January 21, 2016.
Secondary & Cumulative Effects Analysis Training Program Module 1: How to Determine Which Resources Should be Considered in a SCEA How to identify what.
S.R. A1A SIDEWALK PROJECT SR A1A Sidewalk FPID Pre-Design Public Information Meeting July 13, 2011 Presented By: Derek Dixon, FDOT.
State Route 28/U.S. Highway Route 127 Improvements Project Fentress County, Tennessee Public Hearing March 15, 2011 South Fentress Elementary School 5018.
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
DICKINSON AVENUE RECONSTRUCTION
I-85 Widening Project MM Cherokee County Public Hearing March 14, 2017.
I-85 Widening Project MM Cherokee County Public Hearing March 14, 2017.
PROJ. 566(17) LOR PID MAJOR WIDENING
S.R. 26 Road Rehabilitation in Clinton County
Walker Street Reconstruction Project 25% Design Public Hearing
U.S. 20 at State Road 2 New Interchange
Presentation transcript:

SR 1 BLUFFTON Public Hearing September 25, 2012

INDOT Mission: INDOT will plan, build, maintain and operate a superior transportation system enhancing safety, mobility and economic growth INDOT Values: Respect Teamwork Accountability Excellence INDOT

6 district offices 3,722 employees $396 million/annual operating budget $1 billion/annual capital expenditures 28,410 total lane miles 5,098 lane miles of interstate 16,519 lane miles of two-lane roads 5,320 INDOT-owned bridges INDOT Profile

Hearing Agenda  Welcome  Presentations  Public Statement for the Record  Adjourn

Comments For The Record  Verbally as a Public Statement  Comment Form  Mail or Fax  Please feel free to use any and all methods. Comment period ending October 10, 2012.

Project History Environmental Document released for public involvement on December 6, 2011 Scope of Environmental Study:  Evaluate impacts to natural and human environments  Social and economic factors  Waterways, wetlands, and endangered species  Historical properties

Project History continued  Legal Notice of Public Hearing  The News Banner  September 10 th & 17 th, 2012  Community Input  One of the final steps of the Environmental process

Real Estate Acquisition Process /realprop/index.html /rights/index.html

Real Estate Acquisition Process  “Uniform Act” of 1970  All federal, state, and local governments must comply – just compensation  Acquisition Process  Appraisals  Review appraisals  Amount of compensation cannot be less than fair market value  Offer will be made in writing  No agreement  Mediation  Condemnation

Project Need Numerous commercial property access points and high traffic volumes Lack of access control and turning lanes impedes traffic operations Poor surface drainage patterns

SR 1 classified as a principal arterial roadway SR 116 classified as a minor arterial roadway One travel lane in each direction, limited turn lanes and passing blisters Speed limit: 40 mph, decreases to 30 at the south edge of the Wells County 4-H Park Existing SR 1 south of Spring St.

Asphalt travel lanes 12 ft wide Paved shoulders 3 ft to 6 ft wide Last resurfaced in 2003 Land use is commercial and light industrial with agricultural at the south end

Existing SR 1 Conditions Currently in fair condition Ruts and cracks beginning to show in the wheel paths Tight turn radii at SR 116 and other intersections Few access points south of 4-H Park North of 4-H Park almost completely paved with few defined driveways

Existing SR 1 Conditions (cont’d) Poorly defined drainage system Roadside ditches show signs of standing water Existing discharge points have inadequate capacity for new runoff

 Incidental Construction (Blue)  Widening and Resurface (Green)  Cul-de-sac for Scott Street (Red) N SR 1 Construction AreasN State St. SR 116 (Harrison Plaza) Harvest Rd. 4-H Park Rd. Harvest Rd. Spring St. Scott St. Delong Ditch

12’-0” 2’-7” 14’-0” 12’-0” 2’-7” SR 1 Proposed Typical Section One 12’-wide Lane Each Direction 14’-wide Continuous Two-Way Left-Turn Lane New Concrete Curb and Gutter Widening with Overlay of Existing Pavement Proposed SR 1

Permanent Right-of-Way (Orange) Typical Width – 80’ (40’ each side) Maximum Width – 113’ 5.88 Acres Temporary Right-of-Way (Green) 0.52 Acre SR 1 Proposed Right-of-WayN South Half State St. Harvest Rd. SR 116

Permanent Right-of-Way (Orange) One commercial relocation (Pink) Temporary Right-of-Way (Green) SR 1 Proposed Right-of-WayN North Half 4-H Park Rd. Spring St. Scott St. 4-H Park Rd. Spring St. Scott St.

 Phase 1  One travel lane in each direction  Lanes shifted to west and narrowed to 10’  Widening and storm sewers constructed on east half  Access will be maintained to all properties  Construction zone speed limit 30 mph Maintenance of Traffic (MOT)

 Phase 2  One 11’ travel lane in each direction  Lanes shifted east to new widening  Widening and storm sewers constructed on west half  Access will be maintained to all properties  Construction zone speed limit 30 mph Maintenance of Traffic (MOT)

Public Comments  Indiana Department of Transportation Public Hearings Office, Room N North Senate Avenue Indianapolis, IN   INDOT respectfully requests comments postmarked by October 10, 2012 All comments will be reviewed and evaluated and given full consideration during the decision-making process