Retail Data Transport Upgrade ERCOT Recommendation ERCOT Public June 2015.

Slides:



Advertisements
Similar presentations
Retail Market Subcommittee Update to TAC Kathy Scott January 28,
Advertisements

Retail Market Subcommittee Update to TAC February 5, 2004.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
April 11, 2007 Prepared by the North American Energy Standards Board 1 North American Energy Standards Board Standards Development Process.
Retail Market Update June 5, New meter is requested for a specific customer’s location. 2.Application is filed by customer and/or the customer’s.
RMS Update to TAC August 7, RMS Update to TAC ► At July 9 RMS Meeting:   RMS Voting Items:
Retail Market Subcommittee Update to TAC Kathy Scott April 24,
1 TDTWG Report to RMS SCR 745 ERCOT Unplanned System Outages Wednesday, July 13th.
1 TDTWG Update to RMS June 2, MarkeTrak API Performance Metrics Review ERCOT continues work with CenterPoint and Oncor to refine/revise the MT API.
1 ERCOT True-Up Resettlement Restart Criteria Discussion Retail Market Subcommittee Meeting, February 24, 2003.
RMSUpdate November 4, 2004 Retail Market Subcommittee Update to TAC.
RMS Update to TAC May 8, RMS Update to TAC ► At April 9 RMS Meeting:  Antitrust Training  RMS Voting Items: ► NPRR097Changes to Section 8 to Incorporate.
1 TDTWG Update to RMS Tuesday January 6, Primary Activities 1.Reviewed ERCOT System Outages and Failures 2.Presented Service Availability and.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Retail Market Subcommittee Update to COPS Kathy Scott July 16,
Texas Data Transport Work Group Review RMS Meeting May 29, 2002.
Retail Market Subcommittee Update to TAC Kathy Scott February 27,
Retail Market Subcommittee Update to COPS Kathy Scott May 13,
RMS Update to TAC January 8, Voting Items From RMS meeting on 12/10/2008  RMGRR069: Texas SET Retail Market Guide Clean-up – Section 7: Historical.
Rob Connell May 1, 2002 Retail Sub-Committee Update.
June 10, 2009 RMS PR90006, Commercial Systems Information Lifecycle Management (ILM) Hope Parrish, ERCOT.
ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745) TDTWG May 7, 2008.
1 TDTWG Update to RMS September 1, Discussion Items ERCOT presented Q2 Performance Measures Reviewed SCR 786 with action item to TXSET regarding.
Item 5: PRS Report John Varnell 2014 PRS Chair Technical Advisory Committee (TAC) Meeting ERCOT Public August 28, 2014.
August 28, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott September 9, 2014 TAC Update to RMS 1.
October 9, 2012 Commercial Operations Subcommittee RMS Update Kathy Scott RMS Vice Chair.
1 TDTWG Scope and Goals 2015 Wednesday January 8, 2014.
Rob Connell May 29, 2002 Retail Sub-Committee Update.
Retail Market Subcommittee Update to COPS Kathy Scott March 17,
1 TAC Report to the ERCOT Board February 21, 2006.
1 TDTWG Update to RMS TDTWG Thursday, March TDTWG TDTWG has continued work necessary to further support of the NAESB EDM V1.6 Project Work primarily.
Retail Market Subcommittee Update to COPS Kathy Scott May 14,
1 Update on the 867_03 Contingency Plan Nancy Hetrick February 25, 2003.
TDTWG Update to RMS Wednesday January 14. TDTWG Update to RMS Scope Texas Data Transport Working Group (TDTWG) is responsible for creating and maintaining.
Retail Operations 2008 Fund Release Proposal Retail Market Subcommittee June 11 th, 2008 Hope Parrish Market Operations Division Projects Organization.
Retail Market Subcommittee (RMS) Update Kathy Scott April 9, 2013Commercial Operations Subcommittee 1.
1 RMS Update By Don Bender January 9, RMS Approved Resolution Upon TAC approval, suspend further True-up settlements for True-up resettlement.
1 TDTMS Update to RMS November 3, Leadership Affirmation (RMS Voting Item) Due to creation of a new Working Group, TDTMS conducted leadership elections.
1 Browser Compatibility Assessment June 2 nd, 2015.
Update to RMS August 4th, RMGRR129 – Revision to Customer Rescission Completion Timeline Timely execution of a customer rescission after completion.
February 10, 2010 RMS ERCOT 1/24/10 Production Issue Overview and Lessons Learned Karen Farley Manager, Retail Customer Choice.
PMO Update to RMS Troy Anderson Program Management Office December 7, 2005.
Demand Response Task Force. 2 2 Outline  Overview of ERCOT’s role in the CCET Pilot  Overview of Stakeholder Process – What’s been done to date?  Questions.
1 TDTWG Accomplishments 2010 Friday January 28, 2011.
1 Texas Data Transport & MarkeTrak Systems (TDTMS) Update to RMS February 2, 2016 Jim Lee (AEP) – Chair Monica Jones (NRG) – Vice Chair.
December 9, 2015 Retail Market Subcommittee Update to COPS Kathy Scott January 13,
1 TDTWG Update to RMS Tuesday March 3, Primary Activities 1.ERCOT System Outages and Failures 2.MarkeTrak Performance 3.Discussed 4 th QTR Performance.
1 TDTWG Report to RMS Recommended Solutions for SCR 745 ERCOT Unplanned System Outages and Failures Wednesday, August 10th.
Retail Market Update August 6, Load Profile Guides In accordance with section § (e) (3) and PUCT Project 25516, Load Profiling and Load Research.
1 TAC Report to the ERCOT Board January 17, 2006.
Protocol Revision Subcommittee Rob Bevill January 5, 2012.
RMS Update to TAC October 2, RMS Update to TAC TAC Confirmation Vote Request Kyle Patrick of Reliant Energy and Independent Power Marketer segment.
February 2, 2016 RMS Meeting 1. * Reasons: * Per the ERCOT Board Report dated 8/5/14 there were 6.6M Advanced Metering System (AMS) Electric Service Identifiers.
RMS Update to TAC November 1, RMS Activity Summary RMGRR057, Competitive Metering Working Group Name Change (VOTE) Update on RMS Working Group and.
1 Texas Data Transport & MarkeTrak Systems (TDTMS) Update to RMS March 1, 2016 Jim Lee (AEP) – Chair Monica Jones (NRG) – Vice Chair.
1 TDTWG Update to RMS Wednesday May 6, Primary Activities 1.Reviewed ERCOT System Outages and Failures 2.Reviewed Service Availability 3.Reviewed.
June 26 and July 31, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott August 5, 2014 TAC Update to RMS 1.
1 SCR756 – Enhancements to the MarkeTrak application –Fondly called - MarkeTrak Phase 3 –ERCOT CEO determined that SCR756 is not necessary prior to the.
1 TDTWG Report to RMS SCR Addressing ERCOT System Outages Tuesday, May 10.
TDTWG UPDATE TO RMS 1 Tuesday April 1, Reviewed ERCOT System Outages and failures ERCOT presented the monthly Incident Report Planned/Unplanned.
1 TAC Report to the ERCOT Board July 18, TAC Summary 4 PRRs for approval (3 unanimous) 4 PRRs for approval (3 unanimous) 5 Nodal PRRs for approval.
Retail Market Subcommittee Update to COPS Kathy Scott August 12,
ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745) TDTWG November 5, 2008.
Alternative Proposal SCR786 Retail Market Test Environment September 2015.
1 Status of True-up Settlements Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec April 26, 2003 Date we expect to be back to.
Retail Market Subcommittee Update to COPS Kathy Scott February 12,
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee May 7, 2009.
RMS Update to TAC June 7, RMS Activity Summary RMGRR052 File Naming Convention for Customer Billing Contact Information URGENT (Vote) RMS Procedures:
Retail Market Subcommittee Update to COPS Kathy Scott January 14,
Retail Market Subcommittee Update to TAC
Presentation transcript:

Retail Data Transport Upgrade ERCOT Recommendation ERCOT Public June 2015

2 ERCOT implemented the NAESB EDM v 1.6 standard in /06/2013 – SCR 776 was submitted to upgrade to v /21/2013 – PRS unanimously voted to recommend approval of the SCR as submitted. 08/07/2014 – TDTWG Requested that the SCR be withdrawn for the following reason – –New market processes affecting Retail Market Participants need to be further evaluated. Upon completion of this evaluation, the new market processes will be incorporated into a future System Change Request (SCR) for a retail data transport upgrade. For this purpose, TDTWG requests that SCR776 be withdrawn. –At its 8/5/14 meeting, RMS endorsed the TDTWG’s request for withdrawal of SCR776. History of Upgrade Request

3 Issue 1 – Risk exists where an unauthorized party could intercept the NAESB response and change it since the current NAESB EDM v1.6 (V1.6) standard does not allow for sufficient repudiation for EDM responses. Issue 2 – Since the implementation of V1.6 standard in 2004 the ERCOT retail market has implemented multiple new files types to accommodate various retail market processes. V1.6 does not accommodate the identification of these file types. Issue 3 – In the event of a failed transmission, V1.6 does not support the identification of previously attempted file transmissions. Issue 4 - V1.6 does not specify any response time for decryption errors following a previously accepted EDM response transmission. This gap allows for the possibility for unidentified and lost transactions. None of these issues is currently having an impact on the Market. Business Case for Proposed System Change – 4 Issues

4 ERCOT Impact Analysis posted January 9, 2014 Cost – between $400k and $500k (Note: This is only the ERCOT cost. Each MP would have an upgrade cost, as well.) Estimated project duration – 10 to 14 months Transition of all Market Participants to NAESB 2.2 is expected to occur within six months of project implementation. ERCOT will not support multiple platforms long-term. ERCOT Impact Analysis for SCR 776

5 The ERCOT Market will eventually need to upgrade to the latest NAESB Standard but due to the cost and duration of the project plus the lack of quantifiable benefit, we recommend postponing the effort until regulatory, security, or technology requirements necessitate the change. At that time a new SCR should be submitted to upgrade to the latest version of NAESB. (Current version is 3.0.) Note: If the Market feels that the benefits outweigh the cost, then ERCOT will be happy to facilitate the creation of a new SCR. ERCOT Recommendation

ERCOT Public 6 Questions