Planning PERT - Project Evaluation and Review Technique) and CPM - Critical Path Method are network analysis techniques that are commonly used in project.
Operations Management Session 27: Project Management.
Project Management Project  A series of related jobs usually directed toward some major output and requiring a significant time to perform Project management.
A problem Four people come to a river in the night. There is a narrow bridge, but it can only hold two people at a time. They have one torch and, because.
 Microsoft Publisher is an easy to use desktop publishing application. It is different from Microsoft Word in that the emphasis is placed on page layout.
Critical Paths.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Management Techniques.
Combinations and Probability
Graphs, relations and matrices
Test Preparation Strategies
Please open your laptops, log in to the MyMathLab course web site, and open Quiz 3.6B. IMPORTANT NOTE: If you have time left after you finish the problems.
Chapter 6 Introduction to Microsoft Project
Graph Coloring.
Lecture 5 – Gantt Chart GANTT Charts Constructing GANTT Charts
7 Graph 7.1 Even and Odd Degrees.
More Graphs, Subgraphs and Trees Planarity and Coloring.
Project Management Project Planning Estimating Scheduling.
Critical Path Analysis
Why do you think it is important to have good manners?
ENGM91 ACTIVITY PLANNING Unit 2
Matrices Addition and Subtraction Competency Goal and Objective Competency Goal 1: The learner will use matrices and graphs to model relationships and.
Lecture 03: Theory of Automata:08 Finite Automata.
STAR Testing Understanding the challenge Test taking strategies the work Doing our best Being confident.
A brief summary of Critical Path (or network) Analysis Critical Path Analysis is a way of planning complex projects. It allows one to find those parts.
Planning Your Time. Why plan instead of just do? Time is one of the most critical resources in any project. Good planning spreads the necessary work over.
Lecture 07: Formal Methods in SE Finite Automata Lecture # 07 Qaisar Javaid Assistant Professor.
Spring 2015 Mathematics in Management Science Machine Scheduling Problem Statement of MSP Assumptions & Goals Priority Lists List Processing Algorithm.
Lesson Objective Understand what critical path analysis is Be able to prioritise events and create a precedence table Begin to use the precedence table.
Network Analysis Terminology
Network analysis Homework:
Project Management “Project Planning & Scheduling”
One Point Perspective Design and Technology. One Point Perspective Task 3 Here are some high quality examples of what we are aiming to produce by the.
Group competition Tonight: discussion translation printing.
Writing directions for detail and sequence Math Practices: Mathematically proficient students start by explaining the meaning of a problem and looking.
Vocabulary and Representations of Graphs. NC Standard Course of Study Competency Goal 1: The learner will use matrices and graphs to model relationships.
Local Hamburgers Click on green arrow to go forward step-by-step instructions.
CONFIDENTIAL 1 Algebra1 Graphing and Writing Inequalities.
Graphs A ‘Graph’ is a diagram that shows how things are connected together. It makes no attempt to draw actual paths or routes and scale is generally inconsequential.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
 Delay in project implementation invariably results in cost- overrun.  Delayed project implementation means delay in getting return on investments made.
Dr. Hany Abd Elshakour 2/18/ :27 PM 1. Dr. Hany Abd Elshakour 2/18/ :27 PM 2 Time Planning and Control Activity on Arrow (Arrow Diagramming.
WINTER Template Agree... or Disagree?. 1.Work with your partner to decide whether you agree or disagree with each answer/solution presented. 2.Write “A”
Inequality Task Cards 28 questions with QR scan codes including topics of: One-step inequalities, two step inequalities and word problems .
Project Scheduling. Why Are Projects Late? an unrealistic deadline established by someone outside the software development group changing customer requirements.
Planning and Scheduling.  A job can be made up of a number of smaller tasks that can be completed by a number of different “processors.”  The processors.
Critical Path Analysis - Worksheet
Unit – graph theory. Concept Characteristics What is a Graph……Really?
Teacher Notes: There is a famous problem in Discrete Mathematics called ‘The Bridges of Konigsberg’ in which it is said to be impossible to cross each.
Unit – graph theory. Concept Characteristics What is a Graph……Really?
Network analysis Homework:
Quick meals and snacks.
assemble-to-order (ATO) A system that produces standard modules to be
Graph Theory Unit 2.
Chapter 4 Review Math Analysis
Critical Path Method Farrokh Alemi, Ph.D.
Lesson Objective Understand Cascade diagrams and be able to use them to draw resource histograms.
7-7 Statistics The Normal Curve.
3.1 Earliest Start Times.
Planning and Scheduling
Lecture 7 PROJECT SCHEDULING Ferdinand Fassa.
Planning and Scheduling
Lesson Objective Understand Cascade diagrams and be able to use them to draw resource histograms.
Matching Equations and Graphs
5.2 Solving Systems of Equations Using Substitution (Warm-Up)
Presentation transcript:

Graphs Their Applications

NC Standard Course of Study Competency Goal 1: The learner will use matrices and graphs to model relationships and solve problems. Competency Goal 1: The learner will use matrices and graphs to model relationships and solve problems. Objective 1.02: Use graph theory to model relationships and solve problems. Objective 1.02: Use graph theory to model relationships and solve problems.

Planning How does a contractor organize all of the jobs needed to complete a project? How do your parents manage to get all parts of a Thanksgiving dinner done at the same time? Although day-to-day planning may be a simple activity, the planning of extensive projects may require very detailed preparation.

Organized Planning Business owners usually can not function properly when haphazard planning is used. Business owners usually can not function properly when haphazard planning is used. A more scientific, organized method must be used. A more scientific, organized method must be used.

Example The Central High yearbook staff has only 16 days left before the deadline for completing their yearbook. The Central High yearbook staff has only 16 days left before the deadline for completing their yearbook. They are running behind schedule and still have several tasks to finish. They are running behind schedule and still have several tasks to finish. The tasks remaining and the times it takes to do each task are listed in the following table. The tasks remaining and the times it takes to do each task are listed in the following table.

Example (cont’d) Task Time A. Buy Film 0 B. Load Cameras 1 day C. Take Photos of Clubs 3 D. Take Sports Photos 2 E. Take photos of Teachers 1 F. Develop Film 2 G. Design Layout 5 H. Print and Mail Pages 3

Example (cont’d) Will it be possible for the yearbook to be completed on time if the tasks have to be done one after the other? Will it be possible for the yearbook to be completed on time if the tasks have to be done one after the other? If some tasks can be done at the same time, could the deadline be met? If some tasks can be done at the same time, could the deadline be met? As you can see, some of the yearbook staff jobs can be done at the same time and yet many of them can not be started until others have been completed. As you can see, some of the yearbook staff jobs can be done at the same time and yet many of them can not be started until others have been completed.

Example (cont’d) Assuming the following prerequisites, how soon can the project be completed? Assuming the following prerequisites, how soon can the project be completed? TaskTime Prerequisite Task Start0 A. Buy film 1NONE B. Load cameras 1A C. Take photos of clubs 3B D. Take sports photos 2C E. Take photos of Teachers 1B F. Develop film 2 D, E G. Design layout 5 D, E H. Print and mail pages 3 G, F

Making a Graph Drawing a diagram or a graph of this information makes it easier to see the relationships among the tasks. Drawing a diagram or a graph of this information makes it easier to see the relationships among the tasks. In the following graph, tasks are represented by points, or vertices, and the arrows, or edges, indicate which tasks must be finished before a new task can begin. In the following graph, tasks are represented by points, or vertices, and the arrows, or edges, indicate which tasks must be finished before a new task can begin.

Graphing (cont’d) Each edge also shows the number of days it takes to complete the preceding task. Each edge also shows the number of days it takes to complete the preceding task. Note that tasks with the same prerequisites are aligned vertically. Although this is not necessary, it makes the graph easier to read. Note that tasks with the same prerequisites are aligned vertically. Although this is not necessary, it makes the graph easier to read.

Graph Start AB C E D F G H Finish

Practice Problems In Exercises 1 through 4, draw a graph and label the vertices for each task table. 1. Task TimePrerequisites Start0 A5NONE B6A C4A D4B E8 B, C F4C G10 D, E, F Finish

Practice Problems (cont’d) 2. Task TimePrereq. Start0 A1None B2None C3 A, B D5B E5C F5 C, D G4 D, E H4 E, F Finish 3. Task TimePrereq.Start0 A5None B7A C4A D3B E7 B, C F5C G8 D, E, F Finish

Practice Problems (cont’d) 4. Task TimePrerequisites Start0 A5None B8 A, D C9 B, I D7None E8B F12I G4 C, E, F H9None I5 D, H Finish

Practice Problems (cont’d) 5. In order to get a family dinner completed in the shortest amount of time, Mrs. Shu listed the following tasks: TaskTime Prerequisite Task Start0 A. Wash Hands B. Defrost hamburger C. Shape meat into patties D. Cook hamburgers E. Peel and slice potatoes F. Fry potatoes G. Make salad H. Set table I. Serve food

Practice Problems (cont’d) a. Construct reasonable time estimates in minutes for each of these tasks and label the prerequisites. b. Construct a graph of the table. c. What is the least amount of time needed to prepare dinner?

Practice Problems (cont’d) 6. Your best friend, Matt, has always been very disorganized. He is now trying to get ready to leave for college and desperately needs your help. a. Develop a table of at least six activities that will need to be completed to get Matt on his way. Give the times and prerequisites of these activities.

Practice Problems (cont’d) b. Construct a corresponding graph. c. What is the least amount of time it will take to get Matt off to school?

Practice Problems (cont’d) 7. Consider the following graph: Start 0 0 A B 2 4 C 3 D E 4 2 F 1 3 G 4 Finish

Practice Problems (cont’d) Complete the task table below for this graph. TaskTime Prerequisite Task Start0 A B C D E F G Finish