Time Planning and Con trol Time-Scaled Network. Processes of Time Planning and Control activities 1.Visualize and define the activities. Job Logic 2.Sequence.

Slides:



Advertisements
Similar presentations
Lecture Network Analysis
Advertisements

Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
D1: Critical Events And Critical Paths. D1: Critical Events And Paths A critical path is the list of activities on an activity network that, if they are.
PERT / CPM PERTProgram Evaluation & Review Technique CPMCritical Path Method.
Eleanor Roosevelt High School
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Construction Planning and Scheduling A G E NG 520 Schedule Computations Part #2 1. Definition and Computation of Total and Free Floats: Total Float : The.
Dr. Hany Abd Elshakour 5/4/2015 3:55 PM 1. Dr. Hany Abd Elshakour 5/4/2015 3:55 PM 2 Time Planning and Control Activity on Node Network and Precedence.
Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers are responsible for.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Resource Planning. 51 Resource Planning Estimating Schedule Activity Resource Requirements Determining what resources will be required (labor, equipment,
L ECTURE 5 – G ANTT C HART GANTT Charts Constructing GANTT Charts Staffing and Re-scheduling Project Management Software Software Project Management Maria.
Network planning Learning objectives After these lectures you should be able to: - Produce and analyse activities networks - Calculate earliest and latest.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
1 ARCH 435 PROJECT MANAGEMENT Lecture 3: Project Time Planning (Arrow Diagramming Technique) Activity on Arrow (AOA)
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Time Management
Importance of Project Schedules
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
Time Planning and Con trol Precedence Diagram.  Precedence Diagramming  An important extension to the original activity-on-node concept appeared around.
HIT241 - TIME MANAGEMENT Introduction
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
Lesson №2. is the unique activity that has a beginning and an end time, aimed at achieving a predetermined result/goal, the creation of a specific, unique.
System Analysis & Design Chapter V: Information System Planning 1.Introduction Nowadays, Information Systems plays the main role in success or failure.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Lecture 5 – Gantt Chart GANTT Charts Constructing GANTT Charts
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
Project Time Con trol. Control = Monitor + Compare + Analysis + Action  Definition: Controlling  Controlling involves making sure that the results achieved.
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
Time Planning and Control Activity on Node Network (AON)
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Project Management.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Management Concepts Gantt Chart – shows tasks as bars whose length indicates timing. PERT* chart (Network Diagram) – shows relationships between.
Dr. Hany Abd Elshakour 2/18/ :27 PM 1. Dr. Hany Abd Elshakour 2/18/ :27 PM 2 Time Planning and Control Activity on Arrow (Arrow Diagramming.
Software Project Scheduling By: Sohaib Ejaz Introduction A Gantt chart is a graphical representation of the duration of tasks against the progression.
Project Scheduling. Why Are Projects Late? an unrealistic deadline established by someone outside the software development group changing customer requirements.
PROJECT MANAGEMENT ENCE-7323 TO 763-N CLASS 3 September 17, 2001 Carl E. Edlund
Survey Training Pack Session 17 – Budgeting and timelines for survey design and implementation.
The Network Diagram. When to Do What?  Carrying out one activity after the other may result in project completion, but it will take the longest possible.
Time Planning and Control Time-Scaled Network
Time Planning and Control Activity on Node Network (AON)
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Time Management
Time Planning and Control Activity on Node Network (AON)
Developing a Project Plan
Critical Path Analysis
Time Planning and Control Time-Scaled Network
ENGINEERING MANAGEMENT (GE 404)
Activity on Node Approach to CPM Scheduling
ENGINEERING MANAGEMENT (GE 404)
Time Planning and Control Activity on Node Network (AON)
Project Planning By Phaik San Liew.
Chapter 6 Activity Planning.
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Exercise – A small building.
Importance of Project Schedules
Chapter 6 Activity Planning.
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Time Planning and Con trol Time-Scaled Network

Processes of Time Planning and Control activities 1.Visualize and define the activities. Job Logic 2.Sequence the activities (Job Logic). activity duration 3.Estimate the activity duration. 4.Schedule 4.Schedule of the project or phase. resources 5.Allocate and balance resources. update 6.Compare target, planned and actual dates and update as necessary. 7.Controlchanges 7.Control the time schedule with respect to changes. activities 1.Visualize and define the activities. Job Logic 2.Sequence the activities (Job Logic). activity duration 3.Estimate the activity duration. 4.Schedule 4.Schedule of the project or phase. resources 5.Allocate and balance resources. update 6.Compare target, planned and actual dates and update as necessary. 7.Controlchanges 7.Control the time schedule with respect to changes.

not  The original project network is not plotted to a time scale.  When drawing a time-scaled diagram, two time scales can be used: one in terms of working days and the other as calendar dates. one dimensional line  Each activity is shown as a one dimensional line rather than as a two dimensional box. duration  The horizontal length is equal to its estimated time duration (beginning at its ES and ending with its EF values). not  The original project network is not plotted to a time scale.  When drawing a time-scaled diagram, two time scales can be used: one in terms of working days and the other as calendar dates. one dimensional line  Each activity is shown as a one dimensional line rather than as a two dimensional box. duration  The horizontal length is equal to its estimated time duration (beginning at its ES and ending with its EF values).  TIME-SCALED DIAGRAM

The following activity list represents the job logic and the durations of activities for a small engineering project. Draw a time- scaled network for the project, determine project time and calculate the activities float times.  Example 1 ActivityDepends onDuration (day) EBCGFAHDIJEBCGFAHDIJ B, C A E C, D None E, F A F G, H, I

 Example  Project completion time = 18 working days  Critical Path: A, D, F, I, J. ActivityABCDEFGHIJ Total float Free float ActivityDepends onDuration (day) EBCGFAHDIJEBCGFAHDIJ B, C A E C, D None E, F A F G, H, I Time-scaled DiagramA D C B F I E G H J

 Verticalsolid (dashed) lines dependence  Vertical solid (dashed) lines indicate sequential dependence of one activity on another.  In effect, time-scaled networks are merely extensions of bar charts. free float  When an activity has an early finish time that precedes the earliest start of activities following, the time interval between the two is the free float of the activity.  Float timeshorizontal dashed lines  Float times are shown as horizontal dashed lines.  Verticalsolid (dashed) lines dependence  Vertical solid (dashed) lines indicate sequential dependence of one activity on another.  In effect, time-scaled networks are merely extensions of bar charts. free float  When an activity has an early finish time that precedes the earliest start of activities following, the time interval between the two is the free float of the activity.  Float timeshorizontal dashed lines  Float times are shown as horizontal dashed lines.  TIME-SCALED DIAGRAM: Explained

 Free float  Free float or activity float is the amount of time that an activity’s completion time may be delayed without affecting the earliest start of succeeding activity.  Total float  Total float or path float is the amount of time that an activity’s completion may be delayed without extending project completion time.  Total float  Total float or path float is the amount of time that an activity’s completion may be delayed without affecting the earliest start of any activity on the network critical path.  Free float  Free float or activity float is the amount of time that an activity’s completion time may be delayed without affecting the earliest start of succeeding activity.  Total float  Total float or path float is the amount of time that an activity’s completion may be delayed without extending project completion time.  Total float  Total float or path float is the amount of time that an activity’s completion may be delayed without affecting the earliest start of any activity on the network critical path.  TIME-SCALED DIAGRAM: Explained

 Activity float owned path or total float is shared by all activities along a slack path  Activity float is “owned” by an individual activity, whereas path or total float is shared by all activities along a slack path.  Total path float time for activity (i-j) is the total float associated with a path.  Activity float owned path or total float is shared by all activities along a slack path  Activity float is “owned” by an individual activity, whereas path or total float is shared by all activities along a slack path.  Total path float time for activity (i-j) is the total float associated with a path.  TIME-SCALED DIAGRAM: Explained

 Advantages of Time-scaled Diagram checking daily project needs  Very suitable device for checking daily project needs of different resources, and for the advance detection of conflicting demands among activities for the same resource. financial management  Useful for project financial management applications.  Disadvantages of Time-scaled Diagram  Because it is drawn by manual drafting methods, the level of effort needed to modify and update them is very large.  Dependencies among activities are not always so obvious as they are on the activity on node network.  Advantages of Time-scaled Diagram checking daily project needs  Very suitable device for checking daily project needs of different resources, and for the advance detection of conflicting demands among activities for the same resource. financial management  Useful for project financial management applications.  Disadvantages of Time-scaled Diagram  Because it is drawn by manual drafting methods, the level of effort needed to modify and update them is very large.  Dependencies among activities are not always so obvious as they are on the activity on node network.  TIME-SCALED DIAGRAM: Explained

A market survey Example2: TSN A market survey ActivityDescriptionpredecessorsDuration, week APlan survey—1 BHire personnelA1 CDesign questionnaireA3 DTrain personnelB, C2 ESelect samples of customersC1 FPrint questionnaireC1 GConduct surveyD,E,F3 HAnalyze resultsG2 The following activity list represents the job logic and the durations of activities for a market survey project. Draw a time- scaled network for the project, determine project time and calculate the activities float times.

 Example  Project completion time = 11 working days  Critical Path: A, C, D, G, H. ActivityABCDEFGH Total float Free float Time-scaled Diagram ActivityDescriptionpredecessorsDuration, week APlan survey—1 BHire personnelA1 CDesign questionnaireA3 DTrain personnelB, C2 ESelect samples of customersC1 FPrint questionnaireC1 GConduct surveyD,E,F3 HAnalyze resultsG2 A B C D H G E F