Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.

Slides:



Advertisements
Similar presentations
14 June 2007VELOEddy Jans 0 Recent VELO-installation++ activities June 14, 2007 Potmeter calibration Bake-out Cabling & Commissioning.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
LHeC Experimental Beam Pipe
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Machine Detector Interface for the HL (MDI) CERN, April 15, 2011 Austin Ball, Helmut Burkhardt, Marzio Nessi.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
FP420 Vacuum Ray Veness. Contents o What is FP420? o How would it be installed in the LHC? o What would it look like? o What are the issues/interest for.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
10 October 2003S. DeBarger PEP-II Vacuum Failures PEP-II Machine Advisory Committee.
Challenges and Overview From Technical Coordination 27/08/2013 -FH1.
ATLAS EXPERIMENT INTEGRATION TASK: SPACE MANAGEMENT Tatiana Klioutchnikova 05/06/
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
1 Safety and Database Subsection ADO - PO - SA Safety achievement and future activitiesSafety achievement and future activities Database (see K. Pommes.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
G5 Beam Line Vacuum System. G5 Beamline Vacuum System Design  Bakeable and Particulate free to Class 100 Clean Room quality Require Clean room QA and.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
Preliminary View on the LHeC Experimental Vacuum Chambers Jonathan Bosch - University of Manchester And Ray Veness - TE/VSC J.Bosch and R.Veness LHeC -
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
Consolidation and Upgrade plans for the LHC Vacuum System
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
25 January 2007VELO sub-projectsEddy Jans 0 VELO-meeting January 25, 2007 Sub-projects: SX & SX connectorize cooling cables alignment procedure.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
Lab Activities: Chamber Baking & Mixing Station Flushing Claudio Curtis Dan PPS meeting 22 June, 2011.
Update on Experimental Beampipe Progress Ray Veness For Beampipe project team in AT/VAC and TS/MME With special thanks to: S.Calatroni, W.Cameron, D.Duarte,
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
1 st LTEX meeting Protecting the experimental caverns and personnel from a "sector 34 like" incident: work planned in the LHC tunnel Prepared by M GASTAL.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
Upgrade activities DT-LHCb coordination meeting 14 March 2016.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Movable beam pipe and NNC Study & prototype development Manchester 14/12/20091D. FP meeting.
ELENA installation progress F. Butin / ELENA collaboration.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Vacuum System P. Chiggiato TE-VSC
Roadmap for triplet cryostats
Status of LHC installation & New Installation Schedule
LIU Wire Scanner Milestones June 2017
Installation of an Instrument on a CERN machine
Machine-Experiment Interface
Preliminary Y-chamber specifications – First draft
LHC Experimental Vacuum Systems Status October ‘07
Long Shutdown for the LHC: Vacuum Beam Pipes
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Progress with Experimental Vacuum Chambers
Accelerator and Experiment Interface Session: LS2, LS3
Renovation of the 45-year old PS magnets
Upgrade Strategy for the Experimental Vacuum Systems
VELO-meeting January 25, 2007 Sub-projects: SX & SX
Presentation transcript:

Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination teams

LEMIC 29 IV 08Beampipe Status - R.Veness Contents o Last update to LEMIC in October 07 o ATLAS central section installations o VAX zones o Recent activities o Major installations in ATLAS and CMS o Looking forward o Access to chambers for NEG activation or removal o Consolidation activities o AT-VAC structure o Summary

LEMIC 29 IV 08Beampipe Status - R.Veness ATLAS: Lab activities o LUCID Integration o Both LUCID detectors have been integrated in between the VJ chamber and support by the LUCID/VAC team o VJ assemblies ready for installation in B.927 o Bakeout test (Jan ’08) o Half-length of ATLAS, fully NEG-coated, comprised of reserve chambers and supports o Tested NEG activation procedure, bakeout performance and support displacements due to thermal expansion o Also tested thermal load on LUCID with cooling during bakeout o No problems seen Integration of LUCID onto VJ in B.927 Bakeout test in B.927

LEMIC 29 IV 08Beampipe Status - R.Veness ATLAS: Cavern activities o VJ installation test (Jan ’08) o VJ assembly with dummy LUCID was installed in the cavern o Initial leak problems with TAS seal disappeared after few days o Envelope conflicts discovered with forward shielding – being resolved o Gas Injection System o Table + Injection Line + Pumping Line are all installed and being commissioned o baking, test of all instrumentation and connection to PVSS – Should be completed tomorrow VJ reserve chamber installed in ATLAS

LEMIC 29 IV 08Beampipe Status - R.Veness ATLAS: Cavern Activities (2) o Bakeout heater testing (in progess) o ATLAS bakeout jackets integrated into chambers o Permanent cabling down to cavern racks o detector closed during first bakeout, so no access to heaters o Tests to verify heater and thermocouple connections before endcap closure o Also test interlocks with PIXEL thermal control system o Remaining activities o Closing of endcaps around chambers o VT and VJ chambers (installation and test) plus final commissioning o 38 days of VAC activities before ready- for-beam (2 July by current schedule) VA chamber installed in ATLAS

LEMIC 29 IV 08Beampipe Status - R.Veness ALICE o RB24 installation o RB24 (non-experimental side) chambers and supports are being installed o ALICE final commissioning o RB 24 NEG activation week 21 (19/5) o ALICE ultra-pure gas pumping week 22 (26/5)

LEMIC 29 IV 08Beampipe Status - R.Veness CMS: Lab Activities o Reserve chambers ready and NEG coated: o Central pipe (stainless steel) o HF/CT2 (NEG coating in progress) o Forward pipe o NO SPARE for End-cap pipe o Installation tooling o Lifting beams and installation tooling all ready (and now in use!) o Common Be spare section o The prototype 1m long x 58mm ID beryllium chamber has been re-fitted as a spare o Stainless steel ends allow for the assembly at CERN of a spare for ALICE, ATLAS or CMS central pipes- these additional pieces have not been made o Status: Delivered to CERN, acceptance tests complete, in storage

LEMIC 29 IV 08Beampipe Status - R.Veness CMS: Cavern Activities o Forward pipe o Installed Mar ‘08 o Leak problems with TAS seal, eventually resolved o Central pipe o Installed Apr ’08 o Leak tested OK o HF/CT2- assembly o Installed 25/4/08 o Gas injection system o Installed in cavern, connections in progress o Commissioning expected ~20 th May o Remaining tasks o End cap pipe ‘-’ due for installation tomorrow o 45 days of VAC activities before chamber commissioned on 16 th June - ! o Installation and bakeout teams in parallel o Pure gas filling, PIXEL installation, final closing and pumping come after this Central Pipe installation HF/CT2 chambers installed on ‘-’ side

LEMIC 29 IV 08Beampipe Status - R.Veness LHCb o Recent activites o Re-configuring beampipe protection for detector tests o VELO testing o VELO handover meetings – still some details to agree o Reserve chambers o UX85/1 chamber: o large leak discovered during final testing before sending for NEG coating o CERN workshops will re-manufacture another spare for end May 08 o UX85/2 and /3 chambers mechanically complete and tested o Remaining activities o Final pure gas pump-out to be scheduled o Dates need to be coordinated with other experiments

LEMIC 29 IV 08Beampipe Status - R.Veness Access to, or Removal of Beampipes o Possible scenarios requiring access or removal o Re-activation of NEG following extended use [normal] o Re-activation of NEG following accidental saturation [urgent] o Leak in beampipe due to damage during intervention [critical] o Current Situation o All experimental vacuum chambers are ‘single point failure’ items for the LHC machine o One spare exists (or will before first beam) for most chambers o Exceptions are: CMS endcap pipe, ALICE RB26 chambers o Spares for beryllium chambers are in stainless steel for ATLAS, ALICE, CMS and aluminium for LHCb o A 1m beryllium section with stainless steel ends exists at CERN as a common replacement for ATLAS, ALICE and CMS o NEG activation equipment o ATLAS and ALICE-RB26 equipment is permanently installed o ALICE-central pipe, CMS and LHCb equipment is (basically) removable

LEMIC 29 IV 08Beampipe Status - R.Veness Access to, or Removal of Beampipes (2) o Proposed Actions o Produce a spare CMS endcap pipe [but not ALICE RB26 chambers?] o Evaluate (VAC+Experiments) the time for these ‘long’ interventions o Inform and get approval from LHC managment o Depending on results, either: o Look for ‘emergency’ methods of reducing these access times o Consider additional procedures or access restrictions to minimise chance of access being required Time to activate NEG Time to remove chamber ATLASShortLong (VI) ALICE CPLong ALICE RB26ShortLong CMSShort LHCbShort? (VELO)

LEMIC 29 IV 08Beampipe Status - R.Veness Currently Requested Consolidation Activities o ATLAS o Replace stainless steel VA chambers with aluminium (2 years) o Replacement VI beryllium chamber for PIXEL upgrade (5 years) o ATLAS and CMS (inner triplet upgrade) o Replace TAS chambers with larger diameter (3 years) o Re-design and replace remote flanges with larger diameter versions (3 years) o Re-design and replace 19m pumping stations with larger diameter versions (2 years) o LHCb o Replace defective UX85/3 beryllium chamber – approval in progress (Target: 2009/10 shutdown) o Re-optimise UX85/2 and UX85/3 fixed supports for lower-Z versions (Target: 2009/10 shutdown) o Replace stainless steel with aluminium bellows (2 years) o Replace VELO boxes (VAC support for NIKHEF) (TBD) Dates are estimates for design and manufacture from time of project approval

LEMIC 29 IV 08Beampipe Status - R.Veness Experimental Vacuum: Re-structuring for Operation o Completion of installation o The AT-VAC/EN section (R.Veness) remains the contact for completing the installation of the experimental sectors o Vacuum operation o The AT/VAC-LHC section (V.Baglin) will take over operation of the experimental sectors from commissioning- operational questions should be addressed to him o Interventions, consolidation and upgrade o R.Veness will be the contact for planning annual shutdown activities o AT/VAC-LHC will take over vacuum-related interventions o AT/VAC-EN will undertake mechanical interventions o AT/VAC-EN will be responsible for new beampipe and support design

LEMIC 29 IV 08Beampipe Status - R.Veness Summary o Installation of experiments o ALICE and LHCb largely complete - the few remaining activities must be carefully scheduled as resources are stretched o ATLAS final closure started, but still 38 days work remain o CMS going well – 3 chambers in last 2 weeks, still 4 more to install, 45 more days of activity o Operation and consolidation o Access scenarios and times need to be clarified and agreed by management o Please make sure we are included early in planning the 2008/9 shutdown o We will need to coordinate between all experiments and find extra resources if justified by volume of work o Work is starting on consolidation tasks, we need to: o Verify the list of tasks o Agree the scope, schedule and financing

LEMIC 29 IV 08Beampipe Status - R.Veness Additional Material

LEMIC 29 IV 08Beampipe Status - R.Veness Contract timescale for Phase 1 beryllium pipes Market survey placed Finance committee approval for contract placement Call for tenders Contract placed ATLAS chamber delivered to CERN Chamber assembled ready for installation Integration into PIXEL starts in SR1 Total contracting and manufacture: 4 years, 2 months Installation in ATLAS starts Total project duration: 6 years, 5 months Engineering design agreed