St. Croix River Crossing S.P. 8221-82045 Contractor Informational Meeting May 15, 2013 Contact: Paul Kivisto, P.E. St. Croix Crossing Bridge Construction.

Slides:



Advertisements
Similar presentations
St. Anthony Falls Bridge Replacement Jon Chiglo, P.E., Project Manager.
Advertisements

Overview of New Practices & Policy Deck Issues. Topics Stakeholder Responsibilities Stakeholder Responsibilities Deflection Control Measures Deflection.
Mansoura University. Faculty Of Engineering. Civil Eng . Dept.
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next.
July Training Outline Part 1 Cost-per –SF and Detailed Estimate Pay Item Detailed Estimate Segments Bridge Level Data Segment Level Data Supports.
St. Croix River Crossing S. P
Indianapolis Airport Interchange Bridges Presented to: TRB Bridge Aesthetics Subcommittee January 11, 2005.
St. Croix River Crossing Project Public Information Meeting
St Croix River Crossing S.P Contractor Information Meeting 15 May 2013 River Spans.
Measurement for Civil Engineering works
Bridge Engineering (6) Superstructure – Concrete Bridges
By : Prof.Dr.\Nabil Mahmoud
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Spliced Precast Girders
Santa Maria River Bridges Widening. Project Location.
Chapter 34 Bridge Construction.
DEPARTMENT OF PUBLIC WORKS BUREAU OF ENGINEERING & CONSTRUCTION STRUCTURAL DESIGN SECTION REPLACEMENT OF BRIDGE NO. B-0427 ON DAIRY ROAD OVER OWL BRANCH.
POWERPOINT PRESENTATION
Totally Precast Concrete Bridges
Bridge Engineering (7) Superstructure – Reinforced Concrete Bridges
3 June Rapid Replacement of the Hood Canal Bridge Approach Spans Joseph Merth, P.E. Bridge Design Engineer 3 June 2008.
Reconstruction of the Eads Bridge Highway Deck
Wabash Pedestrian Bridge Design For Riverfront Development Committee INC. and The City of Terre Haute.
JAMES THOMSON C. ENG JACKED STRUCTURES SA JACKED STRUCTURES SA A New Approach to Constructing Underground Stations.
Region One Bridge Design – Robert Jose Tovar “If I have seen further it is by standing upon the shoulders of giants” – Isaac Newton.
Crane Bridge Design STJ Engineering Matt Albert AJ Chandler Noah Fehrenbacher Jake Gennicks Jake Wilhoit Rose-Hulman Institute of Technology.
ODOT Policy for Deck/Slab Closure Pours Sean Meddles, P.E. Assistant Administrator ODOT Office of Structural Engineering.
RM Product Update October 2009 Alexander Mabrich, PE, Msc Senior Engineering Consultant.
The Origin and history When the Sydney Harbor Bridge was opened by the Premier of New South Wales, Mr. Jack Lang on the 19th March 1932, the Harbor Bridge.
St. Anthony Falls Bridge By: Timothy Brewer St. Anthony Falls Bridge Backround Location: Minneapolis, Minnesota Design: Steel Truss Arch Bridge I-35.
ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
BRIDGE DESIGN SAIF HAROON BY Post-Doctoral Research Associate
Oakland Jr. High – STEM Classes – Project Update and 3D Printing March 26, 2015.
Spliced Girders A Producer’s Perspective
STRESS RIBBON BRIDGES PREPARED BY:SHAIKH MOHAMMADSOYAB A
Page 1 MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
WVDOH Accelerated Construction Concepts Benjamin Beerman, PE.
Bridge Engineering (5) Substructure – Abutments and Piers
August 30, 2012 Cost Estimate Review Closeout Presentation St. Croix River Crossing Project Minnesota and Wisconsin.
International Partnership Day.  An SPMT is used for transporting massive structures that are too large or heavy for normal trucks  The SPMT consists.
Presented by: Department of Transportation - Toll Bridge Program New Benicia-Martinez Bridge Project.
Draft for Discussion & Policy Purposes Only
1 9 th Oct Design and Construction of Main & Crescent Bridges.
1 Rehabilitation of 188 th Street over Grand Central Parkway PIN: X Contract #: D Deck Replacement October 2015.
BANDRA-WORLI SEA LINK BY : PRAJAPATI NIHAR V..
MC3D V1.1 - Match-Cast 3D Geometry Control Software
James C. Renick School of Education PSU AE Senior Thesis 2006 Mick Leso - Structural North Carolina A&T State University - Greensboro.
SFOBB East Span Seismic Safety Project San Francisco-Oakland Bay Bridge East Span Seismic Safety Project March 12, 2002 Contractor Outreach.
WEST DES MOINES LIBRARY ADDITION Team North Final Presentation Team North The Ace Mentor Program career direction for students in architecture,
Construction of the Route 460 Connector Phase 1 Breaks, Virginia Timothy Barry, PE Robert Bennett, EI June 10-13, 2012 Pittsburgh, PA.
Iron Range Tourism Bureau April 25, 2013 Hwy 53 Update.
Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc.
Condition of Prestressing of the Ft. Lauderdale- Hollywood Airport Deconstructed Segmental Bridges Luis M. Vargas Beiswenger Hoch and Associates.
Selection Criteria For Short-Span Bridges Construction Methods
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
Port of Everett MASTER PLAN UPDATE April 8, 2008.
Construction Methodology for Suramadu Main Bridge.
Totally Precast Concrete Bridges
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
Offsite manufactured Bridges
High Bridge Re-Deck Project
Required Drawings and Info for Formwork or Scaffold Design
Danube Bridge Vidin – Calafat
New Bridge Construction
Blatnik Bridge Management Study
PORT OF EVERETT MARINE TERMINALS MASTER PLAN UPDATE
Totally Precast Concrete Bridges
The Great Belt East Bridge
Presentation transcript:

St. Croix River Crossing S.P Contractor Informational Meeting May 15, 2013 Contact: Paul Kivisto, P.E. St. Croix Crossing Bridge Construction Engineer

The contract will be the governing document and anything we say here is to help contractors understand the draft plans and clarify items that may be in the contract. If there is a conflict between what is presented and the final plans and specifications the plans and specifications will prevail.

Bridge Plan and Elevation – Minnesota Approach Bridges

Bridge Plan and Elevation – Minnesota Approach – 5000 ft

Bridge Plan and Elevation – Minnesota Approach Bridges Basic Bridge Layout / Geometry Construction/Erection Points – Wetlands – Access Points – Balanced Cantilever Items – Segment Weights Substructure Alternatives

82045 – MN Approach Spans Two Alignments – 1400 ft Each Two Units per Alignment Unit 1 – Precast Concrete Box Superstructure Unit 2 – Cast-In-Place on Falsework

82045 – MN Approach Spans Unit 1E / 1W Unit 1E – 960’ Length – Precast Concrete Box Superstructure with CIP Pier Tables and 14’ Deep End Diaphragm – Span 1 – 190’ Span – 10’ Depth – Span 2 – 240’ Span – 10’ to 14’ Transition in Depth – Span 3 – 290’ Span – 14’ Depth – Span 4 – 236’ Span – 14’ Depth

82045 – MN Approach Spans Unit 1E / 1W Unit 1E

82045 – MN Approach Spans Unit 1E / 1W Unit 1E

82045 – MN Approach Spans Unit 1E / 1W Unit 1W – 1200’ Length – Precast Concrete Box Superstructure with CIP Pier Tables and 14’ Deep End Diaphragm – Span 1 – 190’ Span – 10’ Depth – Span 2 – 240’ Span – 10’ to 14’ Transition in Depth – Span 3 – 290’ Span – 14’ Depth – Span 4 – 190’ Span – 14’ Depth

82045 – MN Approach Spans Unit 1E / 1W Unit 1W

82045 – MN Approach Spans Unit 1E / 1W Unit 1W

82045 – MN Approach Spans Unit 2E and Unit 2W Two Alignments Separated Bridges / 1” Joint in Span 7 Cast-in-Place on Falsework Complex Geometry Due to Merging Onramp and Diverging Offramp Post-tensioned Longitudinally, Transversely in Deck and at Intermediate Pier Diaphragms

82045 – MN Approach Spans Unit 2E and Unit 2W Unit 2E – 750’ Unit 2W – 480’

82045 – MN Approach Spans Unit 2E and Unit 2W

Intermediate Diaphragm Post-Tensioning

82047 (North OffRamp) and (South OnRamp) Offramp – Combination of CIP on Falsework and Precast Balanced Cantilever Erection Onramp – Cast-in-Place on Falsework Varies in depth from 14 to 10 feet H-pile foundations

82047 (North OffRamp) 960’ Length – Combination of One Span that is CIP on Falsework with Remaining Spans Precast Cantilever Erection – CIP Pier Tables and 14’ Deep End Diaphragm – Span 1 – 150’ Span – 10’ Depth – Varying Width – Span 2 and 3 – 190’ Span – 10’ Depth - BC – Span 4 – 230’ Span – 10’ to 14’ Transition in Depth – Span 5 – 190’ Span – 14’ Depth – 1000’ Radius

82047 (North OffRamp) General Layout

82047 (North OffRamp) Cross-sections

82048 (South OnRamp) 630’ Length – Cast-in-Place on Falsework – Span 1 – 122’ Span – 10’ Depth – Span 2 – 190’ Span – 10’ Depth – Span 3 – 190’ Span – 10’ to 14’ Transition in Depth – Span 4 – 120’ Span – 14’ Depth – Two Phase Construction – XCEL Storage Tracks

82048 (South OnRamp) General Layout

82048 (South OnRamp) Cross-sections

Bridge Plan and Elevation – MN Approach - Construction Wetlands Access Points Balanced Cantilever Construction Segment Weights Cast-in-Place on Falsework

Bridge Plan and Elevation – MN Approach - Construction Wetlands

Bridge Plan and Elevation – MN Approach - Construction Wetlands – Wetlands on Minnesota Approach – Forested Wetlands near Minnesota bank – Commitments made to minimize impacts and to preserve water quality

Bridge Plan and Elevation – MN Approach - Construction Wetlands – Anticipated Impacts

Bridge Plan and Elevation – MN Approach - Construction Access Points – Highway Access – TH 36 and TH 95 – Rail Access – UPRR – River Access – Offload from Barge to Bank Provisions for Trestles into St. Croix River to Allow Use of Barges for Segment Delivery

Bridge Plan and Elevation – MN Approach - Construction Access Points - Highway Access – 14’ Depth – 45’ Width – 8.5’ Length – Up to 120 tons – Transport and Erection – Elevation Drop from TH 95 Down to River

Bridge Plan and Elevation – MN Approach - Construction Access Points – St. Croix River

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Ground Based Crane Erection – Requires Series of Access Roads Adjacent to Cantilever Segment Hauler Requires Crossing UPRR Track at Grade – Traffic Control Requirements at TH 95 – Shoring Towers at Piers – Tip Props Shown with Pier 4 Erection

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Unit 1E

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Unit 1W

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Unit 1W

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – 82047

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Ground Based Cranes – 80 to 120 ton Segments (7.5’ to 8.5’ Lengths) – TH95, UPRR, XCEL Storage Tracks, Wetland Impact – Use of Internal PT-Bars

Bridge Plan and Elevation – MN Approach - Construction Access Points - Highway Access

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Adjacent Access to Cantilevers

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Traffic Control Requirements at TH 95

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Shoring Towers at Piers

Bridge Plan and Elevation – MN Approach - Construction Balanced Cantilever Construction – Tip Props Shown with Pier 4 Erection

Bridge Plan and Elevation – MN Approach - Construction Segment Weights – Typical 10’ Segment – 83 tons – Typical 10’ Segment (Deviator) – 105 tons – Typical 14’ Segment - 90 tons – Typical 14’ Segment (Deviator) – 120 tons – 10’ Precast Pier Segment – 120 tons – 10’ Precast End Segment – 120 tons

Bridge Plan and Elevation – MN Approach - Construction Segment Weights

Bridge Plan and Elevation – MN Approach - Construction Cast-in-Place on Falsework

Bridge Plan and Elevation – MN Approach - Construction Cast-in-Place on Falsework – Bridge – Unit 1E / Unit 2W 14’ Deep Pier Tables 14’ Deep End Segments – Bridge – Unit 2E / Unit 2W – Bridge – Span 1, Pier 1 and Pier 4 Table, and Pier 5 End Diaphragm – Bridge Two Phase Construction / Post-tensioning

Bridge Plan and Elevation – MN Approach - Construction Cast-in-Place on Falsework – Bridge – Cast Span 1 Concrete and Pier 1 Table – Post-tension Longitudinal Web Tendons and Supplementary Bottom Slab tendons – Precast Segment Erection on Span 2 Side of Pier 1

Bridge Plan and Elevation – MN Approach - Construction Cast-in-Place on Falsework – Bridge 82048