The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.

Slides:



Advertisements
Similar presentations
GRO Project Management Handbook
Advertisements

Contract Management and Regulation Vickram Cuttaree The World Bank St. Petersburg – May 24, 2008.
Fiscal Law Proposal Mary Margaret Evans Director DRAFT.
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
© 2013 Cairn India Limited MEASURES TO BE TAKEN AT DESIGN STAGE FOR IMPROVING QUALITY GATED PROCESS Anirban Ghosh Senior Manager- Quality Assurance CAIRN.
Program Management Office (PMO) Design
Design/Build Solutions to your construction projects, large and small.
PROMOTING A COORDINATED GROUNDWATER MANAGEMENT FOR LAGOS STATE: WAY FORWARD By PROFESSOR E.O. LONGE, PhD FACULTY OF ENGINEERING DEPARTMENT OF CIVIL & ENVIRONMENTAL.
Project Delivery Approaches for Wastewater Utilities in Minnesota June 24, 2008 Metropolitan Council Environment Committee.
Babcock International Group Plc SH V0.05 Project Status Reviews APM SWWE Event, 31/01/2012 Pete Ricketts FAPM Babcock Marine,
State of California Lahontan Water Quality Control Board Update on Salt & Nutrient Management Plans.
Ensuring Better Services and Fair Value “Introduction and roadmap to implementation of ISO in Zambia’s water utilities” Kasenga Hara March 2015.
4/28/20151 PRESENTED BY NAKABAGO JOHN CONTRACT MANAGEMENT AND ADMINISTRATION IPPU PRESENTATION JOHN NAKABAGO.
UNRESTRICTED Infrastructure Assessment as Viewed by Technology Holders IAEA Technical Meeting December 10-12, 2008 R. Godden.
Getting Certified In Consultant Selection Steps and Processes Diana Foster.
Procurement and Tendering Presentation to [NAME OF CLIENT] [YOUR NAME] [DATE]
Construction Industry Development Board development through partnership “Towards Uniform Conditions of Contract and Specifications in South Africa” South.
1 Water Services Training Group 16 th Annual Conference Water Sector Reform Programme Implementation INEC, Killarney, 8 th November 2012.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
1 PMIG PUBLIC SECTOR PROCUREMENT BEST PRACTICES & LESSONS LEARNED Kevin James Barrie Kroukamp.
Release & Deployment ITIL Version 3
> taking best practice to the world International Experience with Performance Based Maintenance Contracts.
Effective Methods for Software and Systems Integration
FIDIC CONFERENCE 2005, BEIJING Workshop 13 Design & Build - Role of Consulting Engineers in the Tender Process Tse Yau Shing.
Construction Category Management Planning Version 1.1 (May 2015)
1 Module 4: Designing Performance Indicators for Environmental Compliance and Enforcement Programs.
MYLARAM ENGINEERING SOLUTIONS SWAPNALOK COMPLEX, 6 TH FLOOR S.D. ROAD,SECUNDERABAD TELANGANA INDIA.
1 “Lessons Learned - Construction of the National Enrichment Facility” Stephen Cowne Director, Quality & Regulatory Affairs Louisiana Energy Services (LES)
Free Powerpoint Templates Page 1 Free Powerpoint Templates How do we do it? Class 7.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Current Design and Implementation Challenges of Road Projects on the Coastland Ron Rahaman Chief Roads and Bridges Officer Ministry of Public Works Works.
An Introduction to World Bank Organization and Operations Jean-Charles Crochet Senior Transport Economist World Bank.
Energy, Environmental Impacts, and Sustainable Development Presented by Cat Shrier, Ph.D., P.G. Water Resources Planner (403)
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.1 Steps in the Licensing Process Geoff Vaughan University.
BSBPMG501A Manage Project Integrative Processes 4.4 Monitor and Control Project Work The process of tracking, reviewing and regulating the progress made.
Project Management Models
:: February 2005 :: :: presentation to :: Global Water PPPs : Meeting the Challenge Richard M. Temple Hogan & Hartson One Angel Court London EC2R 7HJ Tel:
BSBPMG505A Manage Project Quality Manage Project Quality Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG505A.
Annual Conference October 2011 Water Services Training Group 15 th Annual Conference Water Services in Ireland – Organisational modernisation and new challenges.
SEVESO II transposition and implementation – possible approaches and lessons learned from MS/NMS SEVESO II transposition and implementation – possible.
Using ISMS Principles and Functions in Developing an ARRA Readiness Review Process Presented by Linda K. Rogers Assessments & Readiness Programs Manager.
Special Railways Phase III Proposed approach to regulatory changes Jakarta 16 May 2011.
Implementation Strategy July 2002 STANDARDS DEVELOPMENT LIFECYCLE PROCESS ORP Publishes & Maintains 8 Standing Committee Recommends Approval / Disapproval.
MURRUMBIDGEE CATCHMENT MANAGEMENT AUTHORITY Presentation to UNESCO HELP Meeting 4 March 2005 Lee O’Brien - Chairperson Murrumbidgee Catchment Management.
Lesson 1: Examining Professional Project Management Topic 1A: Identify Project Management Processes.
River Corridor Closure Project Safety People Results End State and Final Closure Jeff A Lerch Manager, Long Term Stewardship June 1 and 2, 2006.
PUBLIC–PRIVATE PARTNERSHIP (PPP) FRAMEWORK AND GUIDELINES Syed M. Ali Zaidi, P.Eng. PM(Stanford), Ph.D. Director, Strategic Partnerships Alberta Infrastructure.
Water Services Trust Fund A presentation for Water Services Boards and Water Service Providers Eng. John Orwa 1  Support provided by the WSTF  Expectations.
RECOMMENDATIONS OF THE GOVERNOR ’ S TASK FORCE ON CONTRACTING AND PROCUREMENT REVIEW Report Overview PD Customer Forum September 2002.
Water Services Trust Fund Official Signing of the 2 nd Call for Proposals Contracts Tuesday 30 th March, 2010 WSTF-Funded Projects: WSTF Support, Expectations.
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
The Design/Build Contract. What Is A Design/Build Contract? Contract that combines design & construction into one agreement The design/build team provides.
Implementing Program Management Standards at Duke Energy.
Safe roads, Reliable journeys, Informed travellers “how the HA is addressing the needs of safety in future maintenance and construction within the design.
Sustainable Direction Ltd PM – The STH Way sustainable direction ltd. 6 Twigworth Court Business Centre Twigworth, Gloucester GL2 9PG UK T +44 (0) 1452.
AGRO PARKS “The Policy Cycle” Alex Page Baku November 2014.
11th Turkish Accountancy Forum June 2016 Stephen Heathcote Executive Director - Markets.
Rob Connatser NSS Instrument Work Packages and XLPM.
How to succeed in International Tenders Ing. Miloš TKÁČ MTC – Engineering / Consulting / Sales Južná trieda 93 – P.c. Strojár, Košice tel.: 055 / 6808.
Water Services Trust Fund Field Monitors Training Workshop
FP&M SETA - Artisan Regulations
Project Management Processes
DTF implementation Roles and responsibilities
Establishment of a regulatory review and assessment process
Safety Management System Implementation
Environmental Commitments
What is Project Management?
IAEA RER/9/141: Improving National Infrastructure for Safety   Regional Workshop on Regulatory Enforcement and Inspection Vilnius, Lithuania 11 September.
Energy Storage Roadmap & Flexibility Roadmap Information Session
Presentation transcript:

The Challenge to Install 1,300 New Water Meters

Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley ~600 sites in Murrumbidgee Valley Data forwarded to NOW and SWC

Sites: Upper Murray Regulated, unregulated and groundwater sites

Sites: Murrumbidgee Regulated entitlement licences only

Challenge 1: Early Planning Align stakeholder expectations Scope the practical challenges in detail Integrate two projects into a single contract Ensure legislative backing (installing meters into private infrastructure) Collect extensive site data Prepare project plan

Challenge 2: Procurement Appoint Managing Contractor Draft the meter specifications and establish supply contracts.

Challenge 3: Detailed Planning Site data proofing Prepare concept designs Identify resource requirements WHS, QA and Environmental assessment procedures Prepare a work schedule Establish the Guaranteed Maximum Price Review and approve

Challenge 4: Implementation Landholder consultation Appoint subcontractors Site variability (!) Buried sites (unable to inspect prior) Clarity in specifications for installers Consistency in subcontractor outputs (QA)

Murray Status (31 May 2012)

Murrumbidgee Status (31 May 2012)

Original Site

Site Under Construction

Completed Site

Lessons Require reliable site data Regulatory support is critical Benefits from an experienced team Appropriate landholder consultation Need for some flexibility Clear specifications and quality control Good data management Fast roll-out possible with good planning.

Thank you Stephen Moore