NuMI Lessons Learned DOE Perspective Who am I? Steve Webster – a DOE Federal Project Director at the Fermi Site Office Role during NuMI – was the Deputy.

Slides:



Advertisements
Similar presentations
RC Strategy Implementation. What we are asking for… Authorization to hire Black and Veatch to develop and issue the two RFPs associated with the RC Strategic.
Advertisements

A Joint Code of Practice Objectives and Summary Presentation
Effective Contract Management Planning
Contract and Project Management: A Field Perspective Moderator Michael Peek, PE CCE CFM Office of Engineering and Construction Management.
DUSEL Neutrino Beam Working Group 12/8/08 DUSEL Beam Working Group Dusel Beam Working Group Management Talk 8 December 2008 Dixon Bogert 1 Management Issues.
1 Integration of EMS and ISMS at the Idaho Cleanup Project Kliss McNeel November 1, 2006.
Construction (Design and Management) Regulations (NI) 2007 A Client’s Perspective Pat Hannaway CMIOSH MCIWEM MIWO I.Eng.
Presented by Team 4 Dennis Farley, Thomas Demana, Chetan Rao, Carlos Arguello-Mirazo, Jim Varghese August 29, 2011.
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
Module 11 Session 11.2 Visual 1 Module 11 Executing and Controlling the Work Session 11. 2: Managing Contracts.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
Determining the True Root Cause(s) of Accidents and Safety Incidents Incident Investigation and Analysis.
Supplier ESH Management Process Jose Valdez, CHST Benchmark Consulting Group, LLC.
David McGiven FAC: Construction Management Procurement October 2006 Facility Advisory Committee (FAC) Construction Management.
This material was developed by Compacion Foundation Inc and The Hispanic Contractors Association de Tejas under Susan Harwood Grant Number SH SH0.
Chapter 2 A Strategy for the Appraisal of Public Sector Investments.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Risk Assessment – An Essential Standard
Presented by: Insert Name Safety Management Consultant
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
The Key Process Areas for Level 2: Repeatable Ralph Covington David Wang.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
Chapter 10 Contemporary Project Management Kloppenborg
Fermilab Neutrino Beamline to DUSEL Mike Martens Fermilab PAC November 3, 2009.
Jennifer Thatcher, Director of Human Resources inSite Housing, Hospitality and Health Services Inc. Working Safe in your Residence.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 DOE IMPLEMENTATION WORKSHOP ASSESSING MY EMS Steven R. Woodbury
Implementing State Health Reform: Lessons for Policymakers Webinar for State Officials April 8, 2010.
The NuMI ES&H Experience with Application to DUSEL Don Cossairt & Mike Andrews September 22, 2008.
Laughton 7/04 Long Baseline Neutrino Program Tunneling Chris Laughton, Fermilab.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Choosing a Consultant. What is a consultant? A consultant is an individual (or, sometimes, a group or organization) that brings experience and expertise.
11 FSO Assessment of Fermilab QA Program Status September 14 – 18, 2009.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Stankiewicz. ESSENTIAL QUESTIONS What are the expectations of the police in US Society? What are the characteristics of police work? What are Wilson’s.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
Construction Safety at the UW Ron Fouty, Safety Director Capital Projects Office University of Washington.
Get Your "Party" Started: Establishing a Successful Third-party Evaluation Martha Thurlow, Ph.D. & Vitaliy Shyyan, Ph.D.—National Center on Educational.
DOE Order 413.3A Program and Project Management for the Acquisition of Capital Assets Catherine Santana Deputy Director, Project Management Systems, OECM.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
Copyright © 2014 by The University of Kansas Choosing a Consultant.
A FSP is a Program designed to identify and control hazards in order to establish and maintain food safety. (Based on HACCP principles) 1 version 2 Dec.2009.
Agency Construction Management :CM NOT AT-RISK
Work Control Process and Measuring Alignment Presented by: Mike Hughes, Bechtel National Operations Manager John Mathis, Bechtel National Safety Manager.
Aug. 22, 2007 CF7S Americas EDR Kick-Off A&E Selection the Fermi Process Tom Lackowski.
Scott Davis, Team Leader March 13,  SC DDFO established fiscal year 2009 Annual Performance Plan and assessments objectives, which included this.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
CHANGES AND WHAT THEY MEAN FOR YOU 2013 EJCDC CONSTRUCTION DOCUMENT SERIES Matthew Skidmore, P.E. NC AWWA-WEA 95 TH ANNUAL CONFERENCE.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.
“What was that?” NuMI: A case study in public participation Judy Jackson Fermilab Office of Communication October 13, 2008.
Transformation of a National Laboratory: ISMS Component Beth Streeper ISMS Program Manager Integrated Safety Management Workshop 2007 Brookhaven National.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Best Construction Practices Lessons Learned Gary Leonard General Counsel Fermi National Accelerator Laboratory.
Closeout Report on the Review Committee (CD-1) for the Long Baseline Neutrino Experiment (LBNE) Project at Fermi National Accelerator Laboratory October.
NCSX Hutch Neilson NCSX Project Manager NCSX Team Meeting January 20, 2005 Meeting Our Safety Management Responsibilities.
1 Six Year Improvement Program Public Hearings FY 2005 to FY 2010.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
How to Find a Water Project for The Community Engineering Corps J. Alan Roberson, P.E.Lindsey Geiger, ENV SP Director of Federal RelationsAssociate Engineer.
OHSAS Occupational health and safety management system.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
I P M 1 City of Fort Worth City Council Presented by Doug Rademaker, Deputy Director, PMO Ken Hall, IPM Program Manager, CH2M HILL October 6, 2009 I n.
Breakout Session Summary Construction
Galt Court Water Main Replacement
Environment, Safety and Health
Department Of Energy Review Linac Coherent Light Source Project
2006 Central Region Post Mortem Review
Presentation transcript:

NuMI Lessons Learned DOE Perspective Who am I? Steve Webster – a DOE Federal Project Director at the Fermi Site Office Role during NuMI – was the Deputy Federal Project Director for NuMI during most of the Project and the Federal Project Director at the end of the Project

Discussion Areas Safety Baseline Development and Management Resource Availability/Project Priority Contract Management Summary

Safety The injury rate for the NuMI tunnels and halls contractor was unacceptably high. One severe injury led to a DOE Type A accident investigation and a work stoppage. (Key findings of the report related to flow down of ES&H requirements to sub-tier contractors, adequacy of the hazard analysis process, root cause analysis of incidents, lessons learned sharing, and oversight) This safety culture led to implementation of corrective actions which included the contractor replacing the superintendent and safety manager, increased oversight by Fermilab and FSO, a heavy safety emphasis in project reviews, initiation of pre-shift safety meetings, and Fermilab implementing safety incentives in the follow on contract for service buildings and outfitting. Safety performance is important in all projects. It’s even more important in projects with underground construction.

Baseline Development and Management NuMI was re-baselined when it was about 50% complete. The original baseline was at least partially top down driven. The TPC went from $138M to $171M, a $33M increase, or 24%. Additionally, the CD-4 date was slipped 2 years. Contributing factors included: underestimating underground excavation and beamline components costs and lack of priority relative to other large high priority projects at Fermilab, which made adding resources difficult.

Baseline Development and Management (Cont.) Lessons learned from the re-baselining effort include: Re-baselining was not easy in 2001, in today’s environment it would be even more difficult The CD-2 baseline should include contingency related to resource availability and priority, if these are possible issues. Estimates for underground excavation should be thoroughly reviewed (I am not implying this is easy, NuMI had multiple independent estimates) Designs should be thoroughly reviewed for over specification and for conflict between designs and performance specifications (underground water treatment) Adequate engineering resources need to be applied (technical components) The baseline approved at CD-2 needs to have adequate cost and schedule contingency. Projects can’t assume re-baselining will be possible.

Resource Availability/Project Priority NuMI Project performance was negatively affected by a lack of priority within Fermilab. Other projects resource needs were filled before considering NuMI’s. (engineering support for beamline components design) The realities of project priority should be considered in baseline development.

Contract Management Management of the tunnels and halls contract was handled by Fermilab, the AE, and consultants. Issues related to the contract included: Safety concerns Contractor performance/management issues Claims management SBO contract management went well

Contract Management (Cont.) Safety: Safety performance was a concern throughout the life of the tunnels and halls contract. Extensive oversight (Fermilab, FSO, and consultant) was required. The impact on the project included work stoppage and implementation of a requirement for pre-shift meetings, resulting in contractor claims for delay ($ and time). Plan safety into the contract and contract management. Contractor performance/management issues: The tunnels and halls contractor did not meet the schedule requirements, contributing factors included not meeting staffing plans and the performance of the tunnel boring machine. (given the slope of the tunnel and the geology, the tunnel boring machine was not a good fit) Fermilab did not have in-house expertise in tunneling contract management. Relied heavily on the AE and consultants. The contract included a disputes resolution process, which did not work. Implement a contract management process that will proactively manage contract performance issues.

Contract Management (Cont.) Claims Management – Disputes Resolution Board did not work. Claims and counter claims were essentially resolved “on the court room steps” Relied heavily on outside consultants (consultants performed well, however was an awkward contractual relationship) Significant outside pressure was received, including political pressure on DOE Political pressure, including from the Italian Consulate DOE-HQ offering “help”, including strongly recommending bringing in a mediator

Summary Issues to consider in future projects: Safety performance and oversight of underground construction contractor’s needs to be considered from contract solicitation on (possible inclusion of incentives) At baseline the project should have sufficient contingency given the type work and the level of design completeness of technical components The future projects should consider including contingency related to project priority Underground construction contracts, by their nature, are subject to significant contractor claims. Expect claims and be prepared to deal with them. An appropriate contract management process should be chosen. The use of a construction manager is recommended.

Summary (Cont.) Positives from NuMI Lessons learned from the tunnels and halls contract were included in follow-on work. Safety incentives were successfully included in the Service Building and Outfitting contract Pre-shift safety meetings were institutionalized Project performed well after re-baselining Contract claims were settled out of court The bottom line: project was successful, but there are things that could have been done differently