1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.

Slides:



Advertisements
Similar presentations
M.PEGORARO Grounding Workshop 24th Jan 08 DT GROUNDING & SHIELDING Presented by A. BENVENUTI.
Advertisements

Power distribution box XD1 top DTTF_Crate XD2 middle DTTF_Crate XD3 bottom DTTF_Crate Connection to DTTF_Crate through cable USE H07 ZZ-F 3G1,5 RACK S1D01.
LECC V. Bobillier1 Overview of LHCb Electronics installation aspects V. Bobillier; L. Roy; J. Christiansen CERN - LHCb.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
Walls crates cables gas chambers electronics CERN adb.
LHCb EP/LBD V. Bobillier 1 Cables and chicane mock up What we would like to define or test with the mock up: if the installation (of both cable.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
Infrastructure for LHCb Upgrade workshop – MUON detector Infrastructure for LHCB Upgrade workshop: MUON power, electronics, cable Muon upgrade in a nutshell.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
’ tall Empty space below this metal sheet 66’ 14’ 4’ 10’ Ceiling tiles = 24 Concrete blocks 14’ long There are two “styles” of Ceiling tile,
FEE LVPS 1. INTRODUCTION This section describes the Low Voltage Power Supplies (LVPS) for the TPC FEEs and RDOs. Plans currently call for all of the old.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Alex Madorsky University of Florida/Physics Track Finder production readiness review, Rice, August 2004 Track Finder Crate, Backplane and Parts Alex Madorsky.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Ken Wyllie, CERN Upgrade infrastructure, Feb LHCb Upgrade Electronics Infrastructure K. Wyllie & L. Roy.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
11 SSD Power and Cooling on the Cone STAR Integration Workshop Howard Matis May 16, 2008 STAR Integration Workshop Howard Matis May 16, 2008.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
DSS  Informal review Tuesday 24 th October 10:00 Room , organized by Laurent Roy.  Subsystems will not be allowed to run overnight or at weekends.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
SPD cabling issues I.Cable status II.Cabling inside VFE box III.Cable through chains (Gael) IV.Data spare cables V.Control bundles VI.Information for cabling.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
18 June 20031Integration Review B. Schmidt Outline: Overview of the support structures Requirements –Some details on electronics, cabling and piping Constraints.
17/03/2003 Referee Meeting M. Beretta 1 MDT Barrel - Complete LV-HV rack 6U 1U 4U 2U 45U 19” Tangential Fan High Voltage Crate Low Voltage Crate Heat Exchanger.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
Infrastructure for LHCb Upgrade workshop – MUON detector Infrastructure for LHCB Upgrade workshop: MUON power, electronics Muon upgrade in a nutshell LV.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
GROUNDING, SHIELDING & COOLING ISSUES ON LHCb ELECTRONICS AT THE LHC PIT 8 V.Bobillier, J.Christiansen, G.Corti, D.Lacarrère, R.Lindner, L.Roy, E.Thomas,
1 13 Octobre 2011 Laurent Roy ATCA Crate / Infrastructure in place -Rack in D3: dimension -Electrical power availability -Tell1 racks running in D3 (air.
V. Bobillier1 Cable installation status.
1. Efficient trigger for many B decay topologies Muon System CALORIMETERS PRS + ECAL+ HCAL RICH1 VERTEX LOCATOR Efficient PID Good decay time resolution.
PHENIX Safety Review Overview of the PHENIX Hadron Blind Detector Craig Woody BNL September 15, 2005.
Infrastructures and Installation of the Compact Muon Solenoid Data AcQuisition at CERN on behalf of the CMS DAQ group TWEPP 2007 Prague,
SPD VFE installation and commissioning (status and plans) I.Summary of VFE installation II.Stand alone VFE test: noise & offset III.Stand alone test: LED.
ATCA COOLING PROJECT INTERSHIP FINAL PRESENTATION Piotr Koziol.
LHCb Install Meeting - 12 / 05 / 2004 Paolo Guglielmini - TS / CV LHCb Cooling of the sub – detectors INNER TRACKER TRACKER TRIGGER RICH 1 RICH 2 Status.
Summary of FEE-Integration Meeting LNF, Summary of the Frascati meeting on chamber & front-end integration on 10 September 2003, provided.
Power, Cooling, Cables, Simulations of Heat Dissipation Short overview of ongoing work on these points Technical Coordination (Rolf Lindner et al.) Cooling.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
Status of integration in USA15. Status of rack layout 20/03/2015FTK Italia - A. Lanza2 Rack Y A2 equipped with turbine cooling system and nominal.
CALO News Pascal Perret LPC Clermont 22 January 2012.
DCal-ALICE integration and installation plan and status A. Tauro.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
ATLAS ATCA cooling evaluation project Claudio Bortolin (EP-ADO-PO) Michal Kalinowski (EP-ADO-PO) Lukasz Zwalinski (EP-DT-FS) ATLAS cooling team – 2016.
FTK infrastructures and DCS 02/12/20101FTK Initial Design Review - A. Lanza  Crates  Single rack layout  Cabling  Rack placement  DSS  DCS.
Cabling for LHCb Upgrade
TS2 preparatory meeting
Rack Design Proposal as of 01/03/2013
General aspects: Optical links :
VELO-installation meeting CERN, January 17, 2006
CMS Area Working Group Meeting
T1 Electronic status Conclusions Electronics Cards:
Electrical and electronic systems projects
Chamber Design and Integration RE3/1 and RE4/1
Fiber Installation for RUN 3&4
LHCb & EYETS
Pierluigi Paolucci - I.N.F.N. Naples
Track Finder Crate, Backplane and Parts
Needed for Team A on -End
Presentation transcript:

1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector power supply

2Laurent Roy Back End (Tell40) ? Power supplies Patch Panel Patch cord long distance cable Chicane passage Patch Panel Cable chain Electronics Board Power Supplies Detector cables Existing Infrastructure Chain between detectors and FE UX85 Protected areaUX85 Detector side Shielding Wall 5 December 2012 Back End ~ 300m total length Tell40 on surface ? Pit 100m ~ 100m total length Option 1 Option 2

3 Detectors cable chains Used by Silicon Tracker, Outer Tracker, Calorimeters and MUON.  Space to check (change, install new ?) Laurent Roy 5 December 2012

4Laurent Roy Actual ‘long distance’ cables path Groove Rb 84 D3 D2 B1 5 December 2012  2 ‘chicane’ passages (one of each side of the wall)

5 5 December 2012 Laurent Roy

6  few tubes could be used for few additional cables (but not for optical fibers)  6 trays could be available by removing the analog velo cables  shielding wall to dismounted 5 December 2012 Analog Velo cables could be removed for new cables space (but only beginning LS2) full

7 UX85 B - ACCESS TO CABLE TRAYS (1)  Slide from D. LACARRERE CURRENT SITUATIONACCESS TO CABLE TRAYS BACK 1 - DETECTOR CLOSED - DUST PROTECTION USING PLASTIC FOILS – NO WORKS ON DETECTORS 2 - DISMANTLING METALLIC STRUCTURES (such as ladders, gangways, stairs,…) 3 - DISMANTLING 3 or 4 LAYERS ( ~ 50 concrete blocks of 7.5 t)  new lifting tools + platform 4 - REMOVING CONCRETE BLOCKS TO SURFACE (via PX84 shaft) – CLEANING 5 – SCAFFOLDING FOR CABLING – CABLING WORKS 6 - REMOVING PLASTIC FOILS – OPEN DETECTOR – WORKS ON DETECTORS 7 - DETECTOR CLOSED - REINSTALLATION PLASTIC FOILS FOR DUST PROTECTION 8 – RE-CONSTRUCTION OF UPPER PART OF SHIELD 9 – FINISHING WORKS (joints, painting, cleaning) 5 December weeks

8Laurent Roy other possibilities for cables installation 5 December 2012  to avoid to dismount the wall:  possibility to pass cables on the top of the wall (vault of the cavern)  If Tell40 on the surface: - pass through PM85 pit (platform used for Cryo PLCs free now -> for Patch panel racks ?)  possibility to make a second groove on the concrete floor below the concrete plug - or through PX85 pit

9Laurent Roy Optical Fibers cable 5 December 2012 Example: Optical cable (up to 18x12=216 fibres or 18x24=432) multimode – 50/125 μm – OM2 (500Mhz.km) Operation wavelength 850 nm 96 fibers (8 ribbons of 12) - MPO connectors Total: 87 installed (8350 fibers) - length mini: 43m – maxi: 65m space in cable tray~2cm2/cable  Need new fibers for LHCb upgrade (OM4 ?) -between detector and Tell40 -between Tell40 and DAQ ?

10Laurent Roy Space for additional electronics in D3 (12 space available for crates) 5 December 2012  today 25 VME Tell1 crates installed ->could be replaced by new ATCA crates

11Laurent Roy Possibility to install also electronics in D2  Row E “Detector Extension” powered by same transformer as D3  5 racks completely empty Tell1 test rack Serveurs+switch tests Force10 Test Modal 5 December 2012

12Laurent Roy  Electrical power available per rack distribution designed for 11 kW/rack max. When equipped with distribution box:  7 single phase power outlets, 16 A circuit breakers (one use for air ventilation unit)  Cooling power (mixed water):enough for this electrical power / rack Frond End racks in D3 consumption: ~ 70 kW (~ 300 kW available in total) D2 ‘Detector extension’ row: ~ 4 kW (~ 80 kW available) 5 December 2012

13Laurent Roy ATCA crate: maxi 14 boards x 250W = ~3.5 kW  total for 2 crates = ~7.0 kW maxi /rack (4 times more than now !)  Install an additional 2U exchanger or try to install only one crate per rack maximum. Rack in D3 dimensions: 2m54 x 60 cm x 90 cm - Useful space : height 56U (2m49) ~10U need to be free at the bottom for cabling and water valve access / width 19’’ (48,3cm) / depth ~73cm -Level1 crates : 11U (9U+2U Fan) x 19” x ~72cm  replaced by new ATCA crate: 13U? (mechanical adaptation)  48V DC Power supply put below the air deflector ? 5 December 2012

14Laurent Roy -Cooling: vertical air flow mixed water exchanger Air temperature inside the rack with 2 exchangers: ~ ˚C - Safety aspect (DSS): Thermo switch: 40 ˚C (increase to 60 ˚C possible), Smoke detection, CO2 automatic triggering.  ATCA Crate need to be adapted (by the company?) to be compatible with vertical air flow. water:16 ˚C 5 December 2012

15 5 December 2012 Laurent Roy Low Voltage – High Voltage power supplies  LV (Maraton): Possibility to install additional AC/DC Wiener module in existing crates Sub-detectorAC/DC crate (6 slots) Total slot available Velo14 RICH113 RICH212 Trigger Tracker12 Inner Tracker11 Outer Tracker10 Calorimeter64 Muon512  Additional crate can be installed for HV (except Muon) Sub-detectorHV crateSpace for new crate Velo1 CAEN HV+1 ISEG HV+ (+1 LV CAEN )1 RICH11 HV ISEG1 RICH21 HV ISEG1 Trigger Tracker1 HV CAEN1 Inner Tracker1 HV CAEN1 Outer Tracker2 HV CAEN3 Calorimeter1 (400V) HP4 Muon2 HV CAEN +1 HV PNPI +1 HV GEM0

16Laurent Roy CONCLUSION Electrical power: no big modifications needed (in UX85) Additional transformers to install at the surface for new PCs Farm. Cooling and Ventilation: enough power but mechanics adaptation in racks needed Enough Space for new electronics crates in the barracks (racks to be adapted). Cables: few solutions exist for new ‘long distance cables’ installation But heavy work (dismount wall?, groove in the concrete?,…) necessary Cable chain to be replaced?  Existing infrastructure not incompatible with electronics Upgrade. But preparing work not to be underestimated 5 December 2012

17Laurent Roy spare slide 5 December 2012