Work Control Center Thomas Meighan D&D Lessons Learned Workshop June 25-26, 2002 PPPL.

Slides:



Advertisements
Similar presentations
Define the Scope of Work Long and short term schedules Schedules broken into reasonable tasks Tasks well defined in eList Proof of worker involvement in.
Advertisements

Archiving NCSX Construction Information Using the PPPL Windows Based Server.
Transition from the Long Shutdown to Hot Checkout: Pre-Hot Checkout Steve Suhring Operability Manager 6/6/13.
Implementation of Computer-Based Training Getting Started.
CHAPTER 7 Business Management.
Conducting Patient Safety Rounds with Staff. First Steps Set the stage –Unit and Hospital Leadership Support –Identify a “champion(s)” for each unit where.
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Plans for Diagnostic Removals, Storage, and Re-installations during NSTX Upgrade Outage B. Stratton NSTX Team Meeting 9/13/2011.
SE 464: Industrial Information systems Most Images and inform. used in these slides are SAP © Not to be used for other than educational purposes Systems.
Environmental Health and Safety Radiation Control and Radiological Services.
Nursing management FUNCTION NURSING MANAGEMENT PROCESS
NCSX NCSX DCT Project Meeting Raki Slide 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PROJECT MANAGEMENT.
MyFloridaMarketPlace Roundtable August 20, 2003 MyFloridaMarketPlace.
The Maintenance and Engineering Organization
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
Safety & Project Management by NABEEH JUM’AH. Eye on Safety  Proactive  Reactive.
NCSX May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 1 ACC Review Of Modular Coil Manufacturing Facility Station No. 5 [VPI] the NCSX Manufacturing.
Colorado Springs Utilities Environmental Services Functional Assessment Presentation for the American Public Power Association’s 2001 Engineering & Operations.
9/14/2015 IEEE Presentation Time-Based Management of Large Scale Network Models John Moseley P.E. Lead Network Model Engineer.
1/18/2005Module 41 How the NCSX Project Does Business Work Planning & Design Review Processes.
Office Layout Techniques and Space Requirements
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM What Am I Supposed To Do To Meet OSHA Standards?
Business Management Bishop Kearney High School Dr. Hays.
June 25-26, 2002D&D Lessons Learned Workshop1 Overview of the TFTR D&D Project Erik D. Perry D&D Lessons Learned Workshop June 25-26, 2002 PPPL.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
CASE STUDY EXAMPLE Work Process Flow Charts. WORK IDENTIFICATION / WORK ORDER PROCESSING Review Notification Asset Coordinator Notification complete and.
1. 1.To obtain knowledge concerning the various organizational structures associated with business. 2.To gain an understanding of each type of organizational.
SC Project Review of NCSX, April 8-10, 2008 Central Controls and Computing WBS51 & 52 P. Sichta WBS5 Work Package Manager.
HBR Best Practices Seminar Presented by CertifiedSafety Brady’s Landing June 30, 2005.
Contract Training Class I
Overview of TFTR D&D Hazards Jerry Levine Head, Environment, Safety & Health.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
ISM Annual Review and Declaration Lessons Learned CH2M HILL Hanford Group John McDonald.
Chapter 13 Project Management. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Define and give.
June 25-26, 2002D&D Lessons Learned Workshop1 Summary of Lessons Learned James H. Chrzanowski D&D Lessons Learned Workshop June 25-26, 2002 PPPL.
12/2/04Module 2D1 The NCSX Engineering Web – An Overview Part IV Engineering Management & Systems Engineering and Other.
Child Care Center Job Descriptions
Collider-Accelerator Department EBIS Commissioning Accelerator Readiness Review (ARR) Work Planning Human Performance Ray Karol May 2010 EBIS ARR.
J. Levine5/21/02 NCSX ENVIRONMENT, SAFETY & HEALTH (ES&H) NCSX Conceptual Design Review (CDR) May 21, 2002.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
Work Control Center Overview. 2 Purpose of Work Control Center Allow engineering to concentrate on developing procedures and technologies Allow field.
NSTX-U Construction Erik Perry Princeton Plasma Physics Laboratory NSTX Upgrade Readiness to Operate Review LSB B318 December 9-11, 2014 NSTX-U Supported.
Production Organization and Management Staff
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Compliance Suite™ Compliance Suite™ is Physical Plant’s software program for regulatory compliance and training tracking.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
Regulatory Streamlining Task Force Update Discussion Item December 6, 2011 Board of County Commissioners.
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
0 Software Quality Assurance Implementation Plan Briefing to the Board June 20, 2003.
Read to Learn Describe the overall purpose of management. Discuss the four functions of management.
Preparations for working on Station 1 November 22, 2005.
U N C L A S S I F I E D Operated by the Los Alamos National Security, LLC for the DOE/NNSA Los Alamos National Laboratory Maintenance Work Planner Training.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
Toolbox Meetings What is a toolbox meeting? An informal 5 to 15 minute meeting held by supervisors used to promote safety.
1 AGS RSVP Review 4-5 November 2004 Management Issues Philip Pile Collider-Accelerator Department 4 Feb 2004.
1 Important Factors in My Landing As suggested by Ed Schultz, I responded back their requirements with bullets of my experience. At first I thought I had.
Department of Defense Voluntary Protection Programs Center of Excellence Development, Validation, Implementation and Enhancement for a Voluntary Protection.
Department of Defense Voluntary Protection Programs Center of Excellence Development, Validation, Implementation and Enhancement for a Voluntary Protection.
Vaccination POD Just-in-Time Training. POD Supply Lead Vaccine Runners Supply Runners.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
1 Getting to Green at the Department of Energy Progress on OMB’s Environmental Sustainability Scorecard Andy Lawrence Director, Office of Nuclear Safety,
New Employee Orientation
National Veterinary Stockpile
Accelerator Operations Department Readiness (Part 2)
Preview of Access Processes for Working at SURF
Presentation transcript:

Work Control Center Thomas Meighan D&D Lessons Learned Workshop June 25-26, 2002 PPPL

June 25-26, 2002D&D Lessons Learned Workshop2 Work Control Center Purpose Under the guidance of the D&D Project Manager, the Work Control Center (WCC) coordinates all work activities between engineering, the Field supervisor, ES&H, Health Physics, and Rad waste. Reviewing the Engineering Work Packages (EWP), containing the D&D procedure and permits, for completeness.

June 25-26, 2002D&D Lessons Learned Workshop3 Work Control Center Reference: D-D&D-OP-AD-119 Rev.01 January 31, 2001 WORK CONTROL CENTER D&D Work Control Center Organizational Chart Industrial Hyg. Representative M. Lumia Construction Safety Don Gallant D&D Engineering WBS Manager J. Chrzanowski D&D Project Manager Erik Perry D-Site Shift Supervisor Wm. Blanchard R. Camp H. Carnavale G. Pearson Field Supervisors D. Gallagher/ T. Langella Lead Tech. & Crews WCC Planners J. Semler and F. Terlitz HP/Rad Waste Coordinator K. Rule Scheduler R. Strykowsky Clerical Support M. Tyrrell Work Control Center Manager T. Meighan Quality Control John Boscoe Frank Murphy Health Phys. Represent. Carl Tilson D&D Construction WBS Mgr. M. Viola D&D HP/Rad Waste WBS Manager K. Rule

June 25-26, 2002D&D Lessons Learned Workshop4 ENGINEERING GROUPS  Generates Engineering Work Packages (EWP’s ) WCC MANAGER  Assigns EWP number  Assigns EWP to Planner WCC PLANNERS  Review EWP for completeness  Submit package for scheduling WCC WORK MEETING  EWP’s placed on schedule WCC FILES  EWP’s are filed for future field activities PPPL INDUSTRIAL Hygienist HP & RAD WASTE REPRESENTATIVE PRE-JOB BRIEFING  EWP’s are reviewed with Field Crews, safety and engineering  Scheduled by WCC Planners FIELD WORK  Field crews supervised by lead techs  Field crews perform EWP activities  Field supervisors oversee all field activities POST JOB BRIEFING  Held at conclusion of each EWP  Lessons Learned  Scheduled by WCC Planners PPPL OPS CENTER CENTRAL CADD ROOM Return EWP TO WCC Near term activities added to schedule meeting Return completed EWP’s Process ECN’s (void/modify dwgs) Return completed EWP’s to Engineering EWP’s submitted to WCC PPPL TRAINING CENTER Return Pre & Post Job Briefings WEEKLY SCHEDULE MEETING (Rollover Mtg.)  Reviews schedule of EWP activities on a weekly basis FLOW CHART OF ENGINEERING WORK PACKAGE PROCESSING

June 25-26, 2002D&D Lessons Learned Workshop5 Work Control Center Located next to TFTR Test Cell Provides meeting room Provides the WCC staff with office space

June 25-26, 2002D&D Lessons Learned Workshop6 Work Control Center Meeting Room Safety Meetings Pre & Post Jobs Training Room Daily Meetings

June 25-26, 2002D&D Lessons Learned Workshop7 Work Control Center Tracking Work Packages The Work Control Center Status Board, kept current by the planners, serves as a good tool for the Construction Manager, Planners, and other groups in the WCC. The Status Board is an overview of jobs in progress, readiness of new work packages and location of activities to avoid work crew congestion.

June 25-26, 2002D&D Lessons Learned Workshop8 Work Control Center D&D Work Order Reference to the EWP and Primavera Activity (Master Schedule No.) Primavera is a program used for Scheduling; Tracking Schedule vs. Expenses. (R. Strykowsky) Work and Safety Description

June 25-26, 2002D&D Lessons Learned Workshop9 Work Control Center D&D Work Order Contains all necessary permits. Procedure No. D-Site Work permit Radiation Work permit Tritium Line Break permit Flame permits. Confined space permit Penetration Permit

June 25-26, 2002D&D Lessons Learned Workshop10 Work Control Center What worked well –Tracking packages A Log Spread Sheet was kept to track all Work Packages past, present and future which helped to get parts and equipment prior to the start of each job. –Work Control Center Status Board The Status Board served as a job scheduling aid to minimize field congestion, which prevented crews from working on top of each other. –Credit card Having a couple people in the project with Government credit cards, issued through Procurement, stream lined the purchasing of items under a pre-set dollar limit.

June 25-26, 2002D&D Lessons Learned Workshop11 Work Control Center What Worked Well (cont.) Location of the Work Control Center –Due to its close proximity to the Test Cell, the WCC provided a convenient location for communication between the field and engineering. –The WCC also provides a quiet location for daily meetings as well as Pre and Post Job Briefings, training, etc.

June 25-26, 2002D&D Lessons Learned Workshop12 Work Control Center Meetings (Played an important part of D&D Project) Plan of the Day –Attendees- Project Manager along with the WCC, Construction Manager, Field Supervisors, Lead Techs, Health Physics/Rad. Waste Representative, Industrial Hyg., Construction Safety, Engineering and the DOE Representative). –Purpose - To coordinate the day’s activities and to resolve conflicts between the various work groups or activities. Daily C-Site –Attendees- Deputy Director of the Lab, NSTX Operations Representatives, Head of Engineering, D&D Project Manager and a representative from all the departments in the Laboratory. –Purpose- To discuss the daily experimental run plan for everyone associated with running the Fusion experiment in the Test Cell next to the TFTR Test Cell. Since both projects share some common space. All attendees are invited to report on the activities of the day to avoid any conflicts.

June 25-26, 2002D&D Lessons Learned Workshop13 Work Control Center Meetings -Continued Weekly Rollover –Attendees- WCC Representative, Shift Supervisor for the Operating Experiment, Department Representatives, Health Physics, ERWM, Industrial Hygiene, and the ES&H Representatives. –Purpose - The WCC Scheduler provides the weekly PPPL Rollover Meeting with a 4-week look ahead of activities being planned for D&D. The Rollover Schedule lists all the activities occurring at D-Site. Weekly WCC/Project –Attendees- Project Manager along with the WCC, Construction Manager, Field Supervisors, Engineering, Health Physics/Rad. Waste Representative, Industrial Hygienist, and the DOE Representative. –Purpose - The long range schedule and any issues which may affect work or schedule are addressed.

June 25-26, 2002D&D Lessons Learned Workshop14 Work Control Center Conclusion In conclusion, the Work Control Center (WCC) concept has worked so well that PPPL is incorporating this concept, on a smaller scale, into upcoming projects at the Laboratory. This includes the removal activities for the PBX machine and for the eventual assembly of the new National Compact Stellarator Experiment (NCSX) Project.