THEMIS Instrument CDR 1 UCB, April 19-20, 2004 THEMIS Electric Field Instrument Fabrication, Integration, and Testing.

Slides:



Advertisements
Similar presentations
THEMIS Instrument PDRRob Duck 1 UCB, October 15-16, 2003 EFI Axial Booms (AXB) Preliminary Design Review Rob Duck Mechanical Engineering Department and.
Advertisements

THEMIS Instrument CDR 1 UCB, March 24-25, 2004 EFI AXIAL BOOMS (“AXB”) Critical Design Review Rob Duck Mechanical Engineering Department Space Sciences.
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012.
THEMIS Mission CDRInstrument I&T 1 UCB, June , 2004 Instrument Integration and Test Rick Sterling / Sharon Jelinsky University of California – Berkeley.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Integration and Test Critical Design Review Rick Sterling University of California – Berkeley Thm_CDR_IT_Revc.
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
THEMIS Mission CDREFI- 1 UCB, June 14-18, 2004 THEMIS Electric Field Instrument (EFI) Mission CDR The THEMIS EFI Team.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 THEMIS Electric Field Instrument (EFI) Instrument CDR The THEMIS EFI Team.
THEMIS Instrument Suite PERSuite T-V- 1 UCB, May 2, 2005 THEMIS Instrument Suite Thermal Vac Test Rick Sterling University of California, Berkeley.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
MPSREFI- 1 UCB, Oct 26, 2006 THEMIS MISSION PRE-SHIP REVIEW “Our Gateway to the Cape…” The Electric Field Instrument (EFI) John Bonnell University of California.
FM4/FM5 PSRSCM - 1UCB, May 5 th, 2006 THEMIS FM4/FM5 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) SEARCH COIL MAGNETOMETER (SCM) Michael Ludlam University of.
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Electrical Fabrication and Test.
THEMIS-SCM - PER THEMIS Instrument Suite PERSCM- 1 UCB, May 2, 2005 Search Coil Magnetometer Alain Roux, CETP.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
THEMIS Instrument PDRParts- 1 UCB, October 15-16, 2003 Parts Requirements Preliminary Design Review Jorg Fischer University of California - Berkeley.
THEMIS FGM CDR Peer ReviewBerlin, April 6, 2004 THEMIS FGM Engineering Peer Review SC Integration and Test Ellen Taylor University of California - Berkeley.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
FM1 Instrument Suite Pre-Ship Review (PSR)Thermal-1UCB, September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THERMAL Chris Smith University.
THEMIS Instrument Suite PEREFI- 1 UCB, May 2, 2005 THEMIS Electric Field Instrument (EFI) Instrument Suite PER The THEMIS EFI, IDPU and II&T Teams.
FM2 PPSRAGENDA 1 UCB, March ??, 2006 THEMIS PROBE FM2 PRE-ENVIRONMENTAL REVIEW INTRODUCTION Paul Turin LME University of California - Berkeley.
THEMIS EOMP ReviewEFINov 19, 2009 THEMIS Electric Field Instrument (EFI) Dr. John Bonnell Space Sciences Laboratory UC Berkeley.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
THEMIS Instrument FM2/FM3 PERSystems- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review System Overview Ellen Taylor University.
MAVEN CDR May 23-25, 2011 Particles and Fields Package Critical Design Review May , 2011 Integration and Test Dave Curtis PFP Package Manager Mars.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Overview and Status Keith Goetz University of Minnesota.
THEMIS MISSION PDRMAG BOOM- 1 UCB, November, 2003 Magnetometer Booms (MAGS) Mission Preliminary Design Review Hari Dharan Space Sciences Laboratory University.
FM1 Instrument Suite Pre-Ship Review (PSR)EFI- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) ELECTRIC FIELD INSTRUMENT John.
THEMIS Instrument FM2/FM3 PEREnvironments- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review Environments Jeremy McCauley University.
THEMIS SUITE PRE-ENVIRONMENTAL REVIEW 1 UCB May 2, 2005 THEMIS Pre-Environmental Review Instrument Verification Overview Ellen Taylor University of California.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
THEMIS INSTRUMENT CDR Peer ReviewSYSTEM- 1 UCB, April 19, 2004 TITLE: Test Flow RFA CODE: UCB-10 REQUESTED BY: Preble SPECIFIC REQUEST: We recommend that.
THEMIS Instrument PDR 1 UCB, April 19-20, 2004 Spin Plane and Axial Boom Preamps & Sensor Cable Fabrication Critical Design Review Daniel Schickele University.
THEMIS Instrument CDR Bill Donakowski/ EFI Radial Boom 1 UCB, April EFI Radial Boom (SPB Spin Plane Boom) Bill Donakowski
THEMIS Instrument PDRGSE- 1 UCB, October 15-16, 2003 IDPU Ground Support Equipment Preliminary Design Review F. Harvey University of California - Berkeley.
SWT Overview 1 UCB, Nov15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Mission Overview Peter R. Harvey Project Manager University of California - Berkeley.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
THEMIS MISSION PDRINSTRUMENT OVERVIEW- 1 UCB, November, 2003 THEMIS INSTRUMENT PAYLOAD SYSTEM OVERVIEW Dr. Ellen Taylor University of California - Berkeley.
FGM peer CDR GSE - 1 Berlin, April 6, 2004 Ground Support Equipment Concept (GSE) Werner Magnes Institut für Weltraumforschung (IWF) Austrian Academy of.
FM2/FM3 PSR FM4/FM5 PERSCM - 1UCB, November 10, 2005 THEMIS FM2/FM3 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THEMIS FM4/FM5 INSTRUMENT SUITE PRE- ENVIRONMENTAL.
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Operational Concept.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Instrument Testing to Date Michael Ludlam for EFW.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 EFI Preamp Sensor G.T. Delory, A. Hull, D. Schickele, J. Bonnell & The EFI Team University of California.
FM2/FM3 IPSR AND FM4/FM5 IPERSYS - 1 UCB, November 10, 2005 THEMIS INSTRUMENT SUITE FM2/FM3 PRE-SHIP REVIEW FM4/FM5 PRE-ENVIRONMENTAL REVIEW SYSTEM OVERVIEW.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 535 IDPU Chassis Bill Donakowski Mechanical Engineer UCB/SSL.
THEMIS Instrument Pre-Environmental Review 1 UCB 5/02/2005 THEMIS Instrument Pre-Environmental Review Project Status May 2, 2005 Peter R. Harvey THEMIS.
THEMIS MRRSystems - 1 GSFC, Jan 5, 2007 Systems Engineering.
FM1 Instrument Suite PSRSCM - 1UCB, September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) SEARCH COIL MAGNETOMETER (SCM) Michael Ludlam.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 Thermal Design Christopher Smith RBSP Thermal Engineer Space.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Systems Engineering Michael Ludlam Space Sciences.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes Sept 30 – Oct RBSP EFW ICDR1 Integration and Test Michael Ludlam (EFW Systems Engineer)
THEMIS Mission CDREFI- 1 UCB, June 14-18, 2004 EFI Subsystem Design, Fabrication, and Test Status.
THEMIS IDPU PDRPCB- 1 UCB, October 16, 2003 IDPU Power Control Board (PCB) Peter Berg University of California - Berkeley.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
THEMIS-SCM SCM – OVERALL RESSOURCES – STATUS versus REQUIREMENTS ItemSpecificationStatus Sensor Bandwith Sensor Sensitivity Up to 4 kHz 1 pT/√Hz at 10.
THEMIS FM2/3 Instrument Suite PEREFI- 1 Telecon, Aug 30, 2005 THEMIS Instrument FM2/3 Pre-Environmental Review Electric Field Instrument (EFI) The THEMIS.
Solar Probe Plus – FIELDS Main Electronics Package
Spacecraft Interface and I&T
(EFW Systems Engineer) University of California, Berkeley
THEMIS Electric Field Instrument (EFI)
Solar Probe Plus – FIELDS Verification Instrument mini-PER (V5)
THEMIS INSTRUMENT SUITE
Boom Electronics Board (BEB)
THEMIS FM4/FM5 INSTRUMENT SUITE
THEMIS Electric Field Instrument
University of California, Berkeley
Integration and Test Organization Chart
Presentation transcript:

THEMIS Instrument CDR 1 UCB, April 19-20, 2004 THEMIS Electric Field Instrument Fabrication, Integration, and Testing

THEMIS Instrument CDR 2 UCB, April 19-20, 2004 Assembly and Test To-Date ETUs One AXB assembled March ’04; initial TVAC complete; vibe testing week of April 12 or 19 ’04. One SPB assembled week of April 12 ’04; vibe testing week of April 12 or 19 ’04. One prototype and two ETU Sensor Cables fabricated March 29 – April 9, ’04; integrated with ETU Preamp PWBs and ETU SPB and AXB for vibe testing. Two ETU Preamp PWB assembled April 9 ’04; integrated with ETU Preamp PWBs and ETU SPB and AXB for vibe testing.

THEMIS Instrument CDR 3 UCB, April 19-20, 2004 Near-Term Testing Mechanical AXB and SPB Vibe (week of April 12 or 19). SPB TVAC (Deploy Testing) (early May; pending completion of B20 “Bayside” refurbishment). AXB and SPB Deploy Calibrations (late April to early May). Need to be substantially complete by early May to support RFQs on FLT Machining. Thermal Long-Eclipse Thermal Simulation for Preamp Electrical Integrated electrical testing of EFI and BEB (late April to early May; EFI/BEB EGSE complete; Faraday Boxes complete in late April). Suite-Level Testing (II&T) Suite-Level testing May 10 to July 27; EFI delivers late May.

THEMIS Instrument CDR 4 UCB, April 19-20, 2004 Facilities ETU Testing Refurbished UCBSSL Silver B20 “Bayside” TVAC Chamber –Accommodates up to 4 SPB. UCBSSL Addition High Bay “Geoffrey” TVAC Chamber –Accommodates fully-deployed AXB vertically. Vibe Testing done off-site. FLT Testing Same facilities as ETU, plus: New UCBSSL Silver B20 “EFI Snout” TVAC Chamber –Accommodates fully-deployed AXB horizontally. Vibe testing done off-site.

THEMIS Instrument CDR 5 UCB, April 19-20, 2004 Calibration Mechanical and Electro-Mechanical SPB Deploy Length –Turns Count –Deploy Rate AXB Deploy Length –Repeatability –Stiffness and Straightness SPB Door SMA and AXB Deploy FrangiBolt Currents Electrical EFI/BEB Calibration –Quiescent and Operational Currents –DC Functional Tests (Gain, Offset, CMRR, Linearity, 0.1% Matching) –AC Functional Tests (Transfer Function, CMRR, Slew Rate, Linearity) EFI/SCM/FGM via DFB Phase Intercalibration –See Suite-Level I&T.

THEMIS Instrument CDR 6 UCB, April 19-20, 2004 SPB Assembly and Test Plan

THEMIS Instrument CDR 7 UCB, April 19-20, 2004 SPB Assembly and Test Plan

THEMIS Instrument CDR 8 UCB, April 19-20, 2004 SPB Assembly and Test Plan

THEMIS Instrument CDR 9 UCB, April 19-20, 2004 Instrument (Suite) I&T Plan Integration and Test Instrument I&T takes place at UCBSSL. Environmental (TVAC, Vibe, Suite EMC as per THM-SYS- 005 Environmental Verification Spec). Limited and Comprehensive Performance Testing: –SPB Motor Simulators (aka. Motor-in-a-Box) and AXB Test FrangiBolts (aka. FrangiBolt-in-a-Box) used for pre- and post- environmental functional tests of deploy mechanisms, as well as dummy electrical loads during “fake” TVAC deploy testing. –Internal DC and AC functional test capability used for pre- and post-environmental functional tests of sensors; sensors may be directly stimulated via ACTEST line on Test/Enable plug. End-to-End SPB and AXB TVAC Deploy Testing (IDPU- controlled; using SPB Takeup Reels, AXB Horiz. Deploy Track in EFI Snout). Phase intercalibration between EFI, SCM, and FGM performed using EFI Test/Enable Plugs, SCM Mu-Metal Box, FGM TCU and 12-channel, 16-bit, +/- 10-V National Instruments DAC system.

THEMIS Instrument CDR 10 UCB, April 19-20, 2004 S/C (Probe) I&T Plan Integration and Test Probe I&T takes place at Swales Aerospace. Environmental (TVAC, Vibe, Shock, EMI; as per THM-SYS- 005 Environmental Verification Spec). Limited and Comprehensive Performance Testing: –Sensors via internal DC and AC Functional Test capability, monitored through ITOS. –Actuators via external Boom Loads Simulator (BLS) and Test/Enable plugs, monitored through ITOS. –Sensors may be stimulated externally via breakout on BLS, if required (non-standard test). Red/Green tag items: –One red tag Snout Cover per SPB (4 total). –One red/green Test/Enable plug per SPB (4 total). –One red tag Tube Cover per AXB (2 total). –One red/green Test/Enable plug supporting both AXBs (1 total)