1 Observatory I&T and Launch Campaign Flow Greg Jones May 20, 2009 JWST-PRES-012924.

Slides:



Advertisements
Similar presentations
Ray Lundquist, NASA GSFC
Advertisements

The Integration and Test Program of the James Webb Space Telescope
1 Ritva Keski-Kuha JWST Deputy OTE Manager May 19, 2009 JWST OTE Development Status JWST-PRES
Status of the James Webb Space Telescope (JWST) Optical Telescope Element (OTE) Northrop Grumman: Charlie Atkinson, Scott C. Texter NASA/GSFC: Lee Feinberg,
ISIM Integration & Test Mike Drury JWST-PRES
1 GAIA System Level Technical Reassessment Study Final Presentation ESTEC, April 23rd 2002 Part 1b Development & AIV.
KU Leuven MIRI team meeting
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems Radiator and X-LAT Assy1 GLAST Large Area Telescope:
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review 1 Presentation 8 of 12 Integration and Test GLAST Large Area Telescope: Pre-Shipment Review Integration.
GLAST LAT Instrument GLAST Monthly Mission Review October 5, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview October 5, 2007 Ken Fouts.
GLAST LAT Instrument LAT Monthly Status Review Aug 1, 2007 W N Johnson, NRL 1 GLAST Observatory TVAC at NRL Aug 1, 2007 Neil Johnson NRL
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
1 GLAST LAT Arrival at Spectrum Assuming That the LAT Transport Container Arrives on Flatbed Truck Question: Can Transport Cover Support Crane Lift With.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 14 March March 2005 LAT High Bay Operations Supporting Test Events LAT.
1 TIPS 4/18/2013 Status of JWST/ISIM Test Program Scott Friedman TIPS/JIM April 18, 2013.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Integration and Test Critical Design Review Rick Sterling University of California – Berkeley Thm_CDR_IT_Revc.
1 Engineering the James Webb Space Telescope Paul Geithner JWST Deputy Project Manager - Technical March 26, 2011.
A Finmeccanica Company 04/2000/1 EUSO Development Philosophy EUSO General Meeting Max Planck Institute for Physics Munich, November the 20th 2003.
1 NASA’s Goddard Space Flight Center 2005/4/14 LRO/CRaTER Technical Interchange Meeting LRO Mechanical Systems Giulio Rosanova / /
1 - ASP-05-STR1-263 M054-1 Tous droits réservés © Alcatel Space Industries All rights reserved Star One C1 - Insurance Presentation 8 - Satellite Test.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
GLAST LAT Project ACD CDR Jan 7-8, Section 7 Mechanical Ground Support Equipment GLAST Large Area Telescope: AntiCoincidence Detector (ACD) Mechanical.
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
James Webb Space Telescope Integrated Science Instrument Module Status Jamie Dunn JWST/ISIM Manager JWST Partner’s Workshop May 19, 2009 JWST-PRES
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
STEREO - Solar Terrestrial Relations Observatory Mission STEREO STEREO Science Team Meeting May 2, 2005 Presented by Edward Reynolds APL STEREO Project.
The Integrated Science Instrument Module Ground Test Matt Greenhouse ISIM Project Scientist NASA Goddard Space Flight Center 23 July 2010.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
James Webb Space Telescope (JWST) Project Status for the AAS Town Hall Phil Sabelhaus JWST Program Manager January 5, 2010.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 16 March 2005 LAT High Bay Operations Supporting Non-Test Events LAT Engineering.
MAVENIPSR3 - SWEA – March 1, SWEA Particles and Fields Package Pre-Ship Review March 1, 2013 Project-Level Assessment Jim Morrissey, MAVEN ISM Mars.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
1 JWST Functional Flow Diagrams and Schematic Block Diagrams.
Final Version Dick Bolt Code 302 May 13-17, 2002 Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF) Mission Success.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Overview LAT Environmental Test.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
Deep Impact FRRJan. 8, 2005Page 1 Deep Impact Overview/Status Flight Readiness Review January 8, 2005 Rick Grammier Project Manager.
Hubble Science Briefing
Mission Operations –Launch February 15, 2000 at 22:02:15 UTC = 14:02:15 PST –41 Days IOC and antenna deployment period –2 year science mission operations.
1 System Architecture Mark Herring (Stephen Merkowitz Presenting)
Goddard Space Flight Center Cryogenics and Fluids Branch Status of the AMS-02 Cryocooler January 2007 TIM.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Operations and Logistics LAT Environmental.
SWT Overview 1 UCB, Nov15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Mission Overview Peter R. Harvey Project Manager University of California - Berkeley.
20c - 1 NASA’s Goddard Space Flight Center Propulsion Chuck Zakrwski NASA/GSFC Code 597 August 16-17, 2005.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
JWST Mission CDR Northrop Grumman Space Systems Redondo Beach (CA) April 10-16, 2010.
June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota
THEMIS MRRI&T − 1GSFC, January 5, 2007 Integration and Test.
KSC Ground Operations Timeline. KSC CGSE TIM A Technical Interchange Meeting regarding the Cryo Ground Support Equipment was held at KSC November 1 st.
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
THEMIS MRRSystems - 1 GSFC, Jan 5, 2007 Systems Engineering.
Micro Arcsecond X-ray Imaging Mission Pathfinder (MAXIM-PF) Mechanical George Roach Dave Peters 17 May 2002 “Technological progress is like an axe in the.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration with PFP, Qualification, ATLO 2011 March 28 Dave Curtis.
The Space Telescope and The Lagrangian Point.  Launch Scheduled for 2018 by European Space Agency  18 Segment Primary Mirror (Gold-plated Beryllium;
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
Lunar Reconnaissance Orbiter (LRO) SRR/Mechanical System August 16-18, 2005
GLAST Large Area Telescope:
Solar Probe Plus FIELDS V1234 Mechanical Pre-Ship Review May 26, 2017
Double Star: Experiment Activities
Environmental Test Planning
Baseline CPT Test Baseline CPT Testing June 2017 Mission Simulation 2
Integration and Test GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
Integration, Test, and Verification
Thermal Vacuum Test: Plans and Procedures
Integration and Test Organization Chart
SDO Integration and Test (I&T) Subsystem Mission PDR
GLAST Large Area Telescope
Presentation transcript:

1 Observatory I&T and Launch Campaign Flow Greg Jones May 20, 2009 JWST-PRES

2 GSFC SSDIF NGST M8, M4 TV NGST M8 GSFC SSDIF ISIM I&T Spacecraft Panel I&T OTE I&T Sunshield I&T OTE Structure I&T GSFC SSDIF, JSC 32 OTE/ISIM I&T Cryo Optics Test Spacecraft Element I&T Facility N/A I&T Responsibility Execution NASA NGST ITT ESA / Arianespace CSG S5C, S5B, BAF, ZL3 M8, LATF, M4 Vibe Complete Observatory I&T Launch Site I&T LV Integ Launch NGST M8 NGST R8 Sunshield Pathfinders (EPF/IVA) Observatory EM Test Bed (EMTB) NGST M8 OTE Pathfinder Structure JSC 32GSFC SSDIF Pathfinder Optics Integration Pathfinder Cryo Optics Test NGST M3 Propulsion Module I&T JWST I&T Flow Overview

3 Stowed & Deployed Modal Tests Integrate Structure Receive OTE Structures Integrate Flight Optics Configure “cup-up” Install SMA Install PMSAs Install AOS Ambient Align Verif Center Section Wings SMSS DTA Harness Integrate Flight ISIM/IEC (Begin OTIS I&T) Pre- Environmental Testing Stowed Dynamics Tests Post- Environmental Testing Observatory (OTE/ISIM) Cryo Test Prep/Ship To NGST OTIS Deployment Test To Full Observatory I&T Alignment Metrology PMSA Gap Meas. 1 st Motion Tests Ambient Elect Functional COCI Test Verifies OTE-ISIM alignment Optical and Thermal Performance Flight Spare Cryocooler Electrical Functional with CCTS EM SC Sim, EM IC&DH, Flt ADU Wing Deployment SMSS Deployment DTA Deployment Alignment Metrology PMSA Gap Meas. Ambient Elect Functional COCI Test Integrate Flight ISIM Integrate Flight IEC Integrate Flight TMS Ship to GSFC SSDIF Ship to JSC/ CryoVac Prep PMSAsAOSSMAISIMIEC PF Acoustics PF Sine Vibe Deployment Tests Wing Deployment SMSS Deployment DTA Deployment OTE and OTIS I&T Flow Overview

4 Integrate Core Assy Install +/-J2 Mid Booms Install FWD & AFT Structures Integrate Skeleton on Bus Structure Deployed Alignments With Membrane Simulators Stowed Alignments Integrate Membranes Lidar shape check for each membrane To SCE I&T 1 st Sunshield System Deployment Fold and Stow Structural Alignments Verification With MGSE OTE Test set driven Fold 5 membranes simultaneously Z-fold pattern Sunshield I&T

5 Integrate Cryocooler Integrate Propulsion Module Propulsion Module Harnesses Flt CryoCooler Flt ICDH Panels & Units Flt SW B1 EM ADU CRANE Integrate Equip & J2 Panels on Flt Structure Validated FSW B2.1 CST -1, GSEG-1 DSN/TDRS RF Compat. Vans Ambient Functional Thermal Vacuum Test Remove HGA/MGA & SA To Observatory I&T Post- Env Ambient Functional Validated FSW B2.2 CST-2, GSEG-2, Fault Modes ACS End-To-End Polarity SCE Mass Properties Mass Lateral CG Post-Env Deployments 1 st motion on SC Offline deployment Install Radiator Shades, SA, Antennas Pre-Env Deployments HG Antenna Omni Antenna Solar Array Radiator Shades MLI Stowed Modal PF 3 Axis Sine Vibration Dynamics Tests Spacecraft I&T Flat-Sat Electrical Integration

6 Ambient Functional Integrate SCE and OTIS Receive SCE Receive OTIS Dynamics Tests Post Dynamics Functional Post- Dynamics Deployments CST-3 EMC GSEG-3 Reinstall SA, HGA Acceptance Acoustic Accept. Sine Vibe Separation Shock CST-4 GSEG-4 Fault Modes Stowed Alignments HGA 1 st Motion SA 1 st Motion RS 1 st Motion DTA Deploy SS Deploy SMSS 1 st Motion OTE Wing Deploy Receive PAF Deploy SS UPSs Remove MGSE OTE Swap EM/Flt ADUs Mate SC-OTIS CryoCooler He fill /verif Alignment Check Elect Integration Stow SS Observatory I&T

7 Launch Site I&T Summary Flow S5C Operations Limited Functional Test Receive GSE Receive Observatory Transport OBS from Airport to S5C Ground Segment End- to-End Test Rotate to vertical Move into NASA clean tent Remove contamination bag Post ship inspection S5 Payload/Hazardous Processing Facilities S5E (Fueling preparation building) Setup NASA clean tent EGSE Validation Remove from Container GSE Preps OCOE to LV Umbilical End-to-End

8 Launch Site I&T Summary Flow S5B Operations Weigh Observatory /Mass Props Load Propellant, Pressurant, Leak Test Observatory Flight Readiness Review (FRR) Transfer Observatory in CCU3 to BAF Establish CCU3 AC & Configure for Transport Transfer Observatory to S5B Blue indicates Integrated LV and Observatory Operations Install OBS on Adapter

9 Launch Site I&T Summary Flow BAF Operations Pre-Encapsulation Red/Green Tag Operations Hoist & Mate Observatory to PLA/ Upper Stage Fairing/ Observatory Encapsulation Observatory to Launch Vehicle I/F Test Remove contamination cover just prior to encapsulation BAF ( Final Assembly Building) ZL3 (Launch Pad) OBS Aliveness Test Blue indicates Integrated LV and Observatory Operations Remove NEA safing plugs

10 Launch Site I&T Summary Flow Launch Pad Operations Countdown & Launch Transport Observatory on LV to Pad BAF ( Final Assembly Building) ZL3 (Launch Pad) Mission Dress Rehearsal Observatory Final Preps & Closeout Observatory Launch Countdown Rehearsal Final Red Tag/Green Tag Removal Blue indicates Integrated LV and Observatory Operations