OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.

Slides:



Advertisements
Similar presentations
OFFICE OF SCIENCE Kurt W. Fisher Review Committee Chair Office of Science, U.S. Department of Energy 1 Closeout Report.
Advertisements

Program Management Office (PMO) Design
Roadmap for Sourcing Decision Review Board (DRB)
Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
TITLE OF PROJECT PROPOSAL NUMBER Principal Investigator PI’s Organization ESTCP Selection Meeting DATE.
Management’s preliminary comments to the ERC Report.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager. CD-1 Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be.
DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
OFFICE OF SCIENCE Review of Critical Decision 1 for the Large Liquid Argon Detector for Neutron Physics (MicroBooNE) at Fermi National Accelerator Laboratory.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
OFFICE OF SCIENCE Review of Critical Decision 2 for the Large Liquid Argon Detector for Neutron Physics (MicroBooNE) at Fermi National Accelerator Laboratory.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
Management subcommittee closeout Jay Marx (chair, LBNL), Joel Butler (Fermilab), Stan Wojcicki (Stanford) Thanks to all for cooperation and openness!!
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,
Management February 20, Annual Review of the Muon Accelerator Program (MAP) Subcommittee members: Ron Prwivo, Ron Lutha, and Jim Kerby.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Closeout Report on the Review Committee (CD-1) for the Long Baseline Neutrino Experiment (LBNE) Project at Fermi National Accelerator Laboratory October.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
OFFICE OF SCIENCE Closeout Report by the Review Committee for the LHC-CMS Detector Upgrade Project Fermi National Accelerator Laboratory August 27, 2013.
Implementing Program Management Standards at Duke Energy.
GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
OFFICE OF SCIENCE DOE/SC CD-3c Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory June 14-16, 2016.
Principal Investigator ESTCP Selection Meeting
Camera PDR/CD1 Planning 19 September 2008
Project Management W. J. Foyt
Principal Investigator ESTCP Selection Meeting
LCLS Linac Technical Design Review Charge
Preparations for a Lehman Review
Management Breakout: MREFC Budget Summary Victor L
External Independent Review (EIR)
Instrument PDR Summary of Objectives
Principal Investigator ESTCP Selection Meeting
Linac Coherent Light Source (LCLS)
Preliminary Project Execution Plan
Conventional Facilities
Principal Investigator ESTCP Selection Meeting
Presentation transcript:

OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary objectives, and justified by the supporting documentation? The MicroBooNE project was given a cost cap of $19.0 M by OHEP. The Committee recommends increasing the upper range. Has all the work been appropriately identified, estimated and scheduled, including the work associated with performing the preliminary design, final design and value engineering? YES, project scope and duration are well defined and preliminary estimates and schedules are developed. 6.Is the documentation required by DOE O413.3A in order and ready for approval of the Critical Decision 1? Yes, the MicroBooNE project team has developed the requisite documentation for Critical Decision 1. However, some changes for consistency and clarity are needed.

OFFICE OF SCIENCE 2 3. Cost Estimate Gines, Fisher Findings Project was given a cost cap of $19 M by OHEP  Procedures for estimating cost and contingency are based on key assumptions and contingency rules  Cost estimates are documented in Basis of Estimates (BoE)  BoE created by L2 Managers; formalizes and documents estimate  BoE can have labor, M&S, and contingency estimates  For DOE MIE: project range is $17M-$19M, current point estimate is $18.785M (TEC=$15.322M and OPC=$3.463M)  NSF contribution is $1.632M  Detailed cost estimates by WBS; overall project contingency 33%

OFFICE OF SCIENCE 3. Cost Estimate Gines, Fisher Comments Key Assumptions Document and Value Engineering processes are recognized as good practices and should be continued Contingencies are not risk based, they follow the Contingency Analysis Rules A complete bottoms-up cost estimate will be needed for CD-2 From a cost and schedule perspective we believe the basis of estimate justifies the project duration, however, we believe that an increase in the cost range should be considered based on the scope presented Recommendations Complete bottoms-up cost estimate for CD-2 Consider increase funding range to a ceiling of $20M 3

OFFICE OF SCIENCE 4 4. Schedule and Funding Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary objectives, and justified by the supporting documentation? From a cost and schedule perspective we believe the basis of estimates justifies the project duration, however, we believe that an increase in the cost range should be considered. Has all the work been appropriately identified, estimated and scheduled, including the work associated with performing the preliminary design, final design and value engineering? The project has appropriately identified, estimated and scheduled the work commensurate with the requirements of CD-1. An integrated plan to get to CD-2 was not presented. 6.Is the documentation required by DOE O413.3A in order and ready for approval of the Critical Decision 1? Yes, the MicroBooNE project team has developed the requisite documentation for Critical Decision 1. However, some changes for consistency and clarity are needed.

OFFICE OF SCIENCE 5 4. Schedule and Funding Gines, Fisher Findings MicroBooNE Project CD-4 is scheduled for 3 rd quarter 2014 Project is currently utilizing Microsoft Project but will move to Primavera Project Resource Loaded Schedule (RLS) contains 930 Tasks Critical Path is tied to access to the MiniBooNE enclosure Project CD-4 date includes 12 months of float Current funding profile includes $3.5M in OPC and $10.6M in MIE with $4.7M contingency Funding profile; R&D $2M in FY10, MIE TEC $17M in FY11-FY13 Contingency is identified at ~33% of project cost

OFFICE OF SCIENCE 4. Schedule and Funding Gines, Fisher Comments A detailed integrated schedule laying out the path forward for CD-2 was not presented to the committee Recommendations  A comprehensive schedule to CD-2 requires development 6

OFFICE OF SCIENCE 7 5. Management and ES&H Gilchriese, Fisher, Gines 3.Does the proposed project team have adequate management experience, design skills and laboratory support to produce a credible technical, cost and schedule baseline? The project will require more management attention and a well defined, integrated plan to obtain CD-2 approval. 4.Are ES&H/QA aspects being properly addressed at the project’s current stage of development? Yes, the MicroBooNE project team has developed a draft NEPA Project Information Form, an Integrated Safety Management Document and a Quality Assurance Plan. 5.Is the DOE project scope well defined within the DOE and NSF funded collaboration? Are all the other parts of the project understood to be the responsibility of the other collaborators? The DoE (and NSF) project scope is well defined for this stage of the project. The cost range should be updated. Scope contingency should be identified. 6.Is the documentation required by DOE O413.3A in order and ready for approval of the Critical Decision 1? Yes, after some minor changes for consistency and clarity.

OFFICE OF SCIENCE 8 5. Management and ES&H Gilchriese, Fisher, Gines Findings  The project management organization is operational, although some personnel are in acting or part-time positions  The costs of project management were estimated to be $1817K(base) + $316K(contingency) = $2.1M(total), or about 10% of the total (DoE+NSF) cost.  Project documentation appropriate for a CD-1 review was produced, but some minor further developments are needed to obtain CD-1 approval  ES&H procedures and documentation are appropriate for CD-1 approval

OFFICE OF SCIENCE 9 5. Management and ES&H Gilchriese, Fisher, Gines Comments  Project integration and systems engineering is a key function of the overall Project Management and is understaffed.  The level of engineering supported by Project Management funding (WBS 1.1) is low. The Project should re-evaluate the relative need for engineering vs a Deputy Project Manager  More effort is needed to evaluate risks, quantify their impact on cost/schedule, and put in place procedures implemented by the Project Management to prioritize, reduce and retire risks.

OFFICE OF SCIENCE Management and ES&H Gilchriese, Fisher, Gines Recommendations  Produce a detailed plan/milestones for all deliverables/actions required for CD-2 and communicate this plan to the L2 managers and Collaboration by the end March  Develop a coherent strategy (and the critical milestones) with FNAL management for the D&D of MiniBooNE and the subsequent conversion of the enclosure for MicroBooNE by the end of April.  Identify potential items of scope contingency, their costs and the impact on scientific goals by June.